Suwakholi-Bhawaan-Sarot chapra-Nagum Motor Raod
Work Completed
|
Project: |
UEAP-RB |
UID: |
5324 |
Sanction Cost: |
585.00 lakh |
Length:
|
KM. |
District: |
Tehri |
Block: |
Jaunpur |
Constituency: |
Dhanaulti |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1060
Package Name: 
UEAP/PWD/C56
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 12-01-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C56
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 03-02-2015
Intended Completion Date: 11-07-2016
|
Total Bond Cost: 91997972.9 (919.98 lakh)
Variation Cost: 12444241.30 (124.44 lakh) Hence Total Bond Cost is 104442214.2 (1044.42 lakh)
|
Sub Project Cost: 467.58 lakh
Variation Cost of Sub Project: 6369711.30 (63.7 lakh)
Total Sub Project Cost:
531.28 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1379970 for 30 days
LD Analysis for Milestone2: calculated LD is Rs 3035934 for 66 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.10 KM | 0.71 | 20-04-2015 | 31-05-2015 | 1.10 KM | 1.10 KM | 0.16 | 0.71 | 2. | R/Wall, B/ Wall Type Protection works | 831.00 m | 276.22 | 28-04-2015 | 31-12-2015 | 831.00 m | 831.00 m | 60.8 | 276.22 | 3. | G-2 | 0.10 KM | 0.71 | 01-05-2015 | 31-10-2015 | 0.10 KM | 0.10 KM | 0.16 | 0.71 | 4. | G-3 | 0.10 KM | 0.72 | 01-05-2015 | 31-10-2015 | 0.10 KM | 0.10 KM | 0.16 | 0.72 | 5. | BM i/c Prime Coat, Tack Coat | 1.83 KM | 36.38 | 01-05-2015 | 31-10-2015 | 1.83 KM | 1.83 KM | 8.01 | 36.38 | 6. | SDBC i/c Tackcoat | 5.90 KM | 29.01 | 01-05-2015 | 31-10-2015 | 5.90 KM | 5.90 KM | 6.39 | 29.01 | 7. | Cause Way | 13.00 No | 57.54 | 01-04-2015 | 30-11-2015 | 13.00 No | 13.00 No | 12.67 | 57.54 | 8. | longitudinal Drain | 10370.00 m | 45.57 | 03-02-2015 | 30-09-2015 | 10370.00 m | 10370.00 m | 10.03 | 45.57 | 9. | Parapet | 285.00 No | 5.31 | 01-07-2015 | 31-10-2015 | 285.00 No | 285.00 No | 1.17 | 5.31 | 10. | Road Furniture | 147.00 No | 2.14 | 01-05-2015 | 31-10-2015 | 147.00 No | 147.00 No | 0.47 | 2.14 |
Total Amount: |
454.31 |
|
100 |
454.31 |
|
Remarks:
No Remarks
Work Program Made On:
11-06-2015 } ?>
Updation of work program on:
10-01-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-August-2015 | 58.66 lakh | 2. | 07-October-2015 | 158.84 lakh | 3. | 07-November-2015 | 25.36 lakh | 4. | 17-March-2016 | 21.64 lakh | 5. | 25-May-2016 | 56.76 lakh | 6. | 06-July-2016 | 95.64 lakh | 7. | 16-November-2016 | 13.37 lakh | 8. | 31-May-2017 | 14.86 lakh | 9. | 29-July-2017 | 16.03 lakh | 10. | 25-September-2017 | 26.05 lakh |
Total |
487.21 lakh |
% Payment | 91.7 % |
|
Advance Amount: 91.00 lakh
Recovered Amount: 91.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 520 No. of Test Done : 533 No. of Test Passed : 520 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 98.05 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 10 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-09-2015 | 17.525 | Plant site visit by SE sir | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
2. | 21-09-2015 | Km18( CH.17+825) | R/w work in progress | Asha rawat | JE | DEA ADB Dehradun | See Pic |
3. | 27-08-2015 | 17.300 | G2 layer for Causeway has been completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
4. | 27-08-2015 | 18.025 | Completed R.W. mts. are being taken | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
5. | 17-07-2015 | 21.650 | R.W. mts. are going on | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
6. | 17-07-2015 | 16.750 | R.W.is being constructed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
7. | 17-07-2015 | 16.700 | R.W. Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
8. | 16-07-2015 | Km11 ch.(10+950) | R/w | Asha rawat | JE | DEA ADB Dehradun | See Pic |
9. | 09-05-2015 | Km16.750 | R/W &scupper in progress | Shankar Ram | SE | ADB Circle | See Pic |
10. | 08-05-2015 | Km 16.750 | R/w &scupper in progress | Shankar Ram | SE | ADB Circle | See Pic |
|
|