Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Suwakholi-Bhawaan-Sarot chapra-Nagum Motor Raod Work Completed
Project: UEAP-RB UID: 5324 Sanction Cost: 585.00  lakh Length: KM.
District: Tehri Block: Jaunpur Constituency: Dhanaulti Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1060        Package Name:  UEAP/PWD/C56        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 12-01-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C56      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  03-02-2015      Intended Completion Date:  11-07-2016     
Total Bond Cost: 91997972.9 (919.98 lakh)        Variation Cost: 12444241.30 (124.44 lakh)    Hence Total Bond Cost is   104442214.2 (1044.42 lakh) 
Sub Project Cost: 467.58  lakh        Variation Cost of Sub Project: 6369711.30  (63.7 lakh)       Total Sub Project Cost:   531.28 lakh
LD Analysis for Milestone1: calculated LD is Rs 1379970 for 30 days        LD Analysis for Milestone2: calculated LD is Rs 3035934 for 66 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.10 KM0.7120-04-201531-05-20151.10 KM1.10 KM0.160.71
2.R/Wall, B/ Wall Type Protection works831.00 m276.2228-04-201531-12-2015831.00 m831.00 m60.8276.22
3.G-20.10 KM0.7101-05-201531-10-20150.10 KM0.10 KM0.160.71
4.G-30.10 KM0.7201-05-201531-10-20150.10 KM0.10 KM0.160.72
5.BM i/c Prime Coat, Tack Coat1.83 KM36.3801-05-201531-10-20151.83 KM1.83 KM8.0136.38
6.SDBC i/c Tackcoat5.90 KM29.0101-05-201531-10-20155.90 KM5.90 KM6.3929.01
7.Cause Way13.00 No57.5401-04-201530-11-201513.00 No13.00 No12.6757.54
8.longitudinal Drain10370.00 m45.5703-02-201530-09-201510370.00 m10370.00 m10.0345.57
9.Parapet285.00 No5.3101-07-201531-10-2015285.00 No285.00 No1.175.31
10.Road Furniture147.00 No2.1401-05-201531-10-2015147.00 No147.00 No0.472.14
Total Amount: 454.31 100   454.31
Remarks: No Remarks       Work Program Made On: 11-06-2015        Updation of work program on: 10-01-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-August-201558.66  lakh
2.07-October-2015158.84  lakh
3.07-November-201525.36  lakh
4.17-March-201621.64  lakh
5.25-May-201656.76  lakh
6.06-July-201695.64  lakh
7.16-November-201613.37  lakh
8.31-May-201714.86  lakh
9.29-July-201716.03  lakh
10.25-September-201726.05  lakh
Total 487.21  lakh
% Payment91.7 %
Advance Amount:  91.00  lakh        Recovered Amount:  91.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 520   No. of Test Done : 533    No. of Test Passed : 520   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 98.05
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 10
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-09-201517.525Plant site visit by SE sirAnuj Kumar SinghAEUEAP R&B Tehri See Pic
2.21-09-2015Km18( CH.17+825)R/w work in progressAsha rawatJEDEA ADB Dehradun See Pic
3.27-08-201517.300G2 layer for Causeway has been completedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
4.27-08-201518.025Completed R.W. mts. are being takenAnuj Kumar SinghAEUEAP R&B Tehri See Pic
5.17-07-201521.650R.W. mts. are going onAnuj Kumar SinghAEUEAP R&B Tehri See Pic
6.17-07-201516.750R.W.is being constructedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
7.17-07-201516.700R.W. CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
8.16-07-2015Km11 ch.(10+950)R/wAsha rawatJEDEA ADB Dehradun See Pic
9.09-05-2015Km16.750R/W &scupper in progressShankar Ram SEADB Circle See Pic
10.08-05-2015Km 16.750R/w &scupper in progressShankar Ram SEADB Circle See Pic