Raipur-Kaddukhal Motor Road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5323 |
Sanction Cost: |
510.00 lakh |
Length:
|
KM. |
District: |
Tehri |
Block: |
Jaunpur |
Constituency: |
Dhanaulti |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1060
Package Name: 
UEAP/PWD/C56
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 12-01-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C56
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 03-02-2015
Intended Completion Date: 11-07-2016
|
Total Bond Cost: 91997972.9 (919.98 lakh)
Variation Cost: 12444241.30 (124.44 lakh) Hence Total Bond Cost is 104442214.2 (1044.42 lakh)
|
Sub Project Cost: 452.40 lakh
Variation Cost of Sub Project: 6074530.00 (60.75 lakh)
Total Sub Project Cost:
513.15 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1379970 for 30 days
LD Analysis for Milestone2: calculated LD is Rs 3035934 for 66 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.53 KM | 8.44 | 25-04-2015 | 31-05-2015 | 1.53 KM | 1.53 KM | 1.89 | 8.44 | 2. | R/Wall, B/ Wall Type Protection works | 1756.00 m | 66.75 | 08-04-2015 | 30-11-2015 | 1756.00 m | 1756.00 m | 14.93 | 66.75 | 3. | G-2 | 0.10 KM | 0.71 | 01-05-2015 | 31-07-2015 | 0.10 KM | 0.00 KM | 0 | 0.00 | 4. | G-3 | 0.10 KM | 0.72 | 01-05-2015 | 31-07-2015 | 0.10 KM | 0.00 KM | 0 | 0.00 | 5. | BM i/c Prime Coat, Tack Coat | 2.26 KM | 37.42 | 01-06-2015 | 31-10-2015 | 2.26 KM | 2.26 KM | 8.37 | 37.42 | 6. | SDBC i/c Tackcoat | 9.45 KM | 149.19 | 01-06-2015 | 31-10-2015 | 9.45 KM | 9.45 KM | 33.37 | 149.19 | 7. | Cause Way | 41.00 No | 58.95 | 01-02-2015 | 31-12-2015 | 25.00 No | 25.00 No | 13.18 | 58.95 | 8. | longitudinal Drain | 5178.00 m | 65.88 | 01-02-2015 | 31-12-2015 | 5178.00 m | 5178.00 m | 14.74 | 65.88 | 9. | Crash Barrier | 245.00 m | 7.84 | 01-02-2015 | 31-05-2015 | 245.00 m | 245.00 m | 1.75 | 7.84 | 10. | Parapet | 321.00 No | 27.30 | 15-07-2015 | 31-12-2015 | 321.00 No | 321.00 No | 6.11 | 27.30 | 11. | Road Furniture | 560.00 No | 23.95 | 01-05-2015 | 30-09-2015 | 560.00 No | 560.00 No | 5.36 | 23.95 |
Total Amount: |
447.15 |
|
99.68 |
445.72 |
|
Remarks:
No Remarks
Work Program Made On:
11-06-2015 } ?>
Updation of work program on:
10-01-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 06-June-2015 | 44.96 lakh | 2. | 26-August-2015 | 76.53 lakh | 3. | 20-October-2015 | 48.31 lakh | 4. | 19-February-2016 | 15.26 lakh | 5. | 25-May-2016 | 44.61 lakh | 6. | 30-August-2016 | 28.53 lakh | 7. | 08-December-2016 | 147.47 lakh | 8. | 31-May-2017 | 36.99 lakh | 9. | 30-June-2017 | 26.21 lakh | 10. | 29-July-2017 | 26.01 lakh | 11. | 25-September-2017 | 47.19 lakh |
Total |
542.07 lakh |
% Payment | 105.64 % |
|
Advance Amount: 91.00 lakh
Recovered Amount: 91.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
Sanitation Facility, debris disposal, Query, DG set |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 520 No. of Test Done : 533 No. of Test Passed : 520 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.86 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 15 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-10-2016 | Ch. 72+00 | Temperature checking | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
2. | 07-10-2016 | Km72 | BM LAYING | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
3. | 28-08-2015 | 54.700 | HP Stone filling in progress | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
4. | 28-08-2015 | CH.49+000 | Causeway | Asha rawat | JE | DEA ADB Dehradun | See Pic |
5. | 28-08-2015 | 45+275 | Completed kuccha drain. | Asha rawat | JE | DEA ADB Dehradun | See Pic |
6. | 28-08-2015 | 29+575 | Completed R/W(RR 1:5) | Asha rawat | JE | DEA ADB Dehradun | See Pic |
7. | 28-08-2015 | 58.775 | Construction of KC drain in progress | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
8. | 28-08-2015 | Ch.59+450 | K.c drain. | Asha rawat | JE | DEA ADB Dehradun | See Pic |
9. | 05-08-2015 | 61.100 | Causeway Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
10. | 05-08-2015 | 61.100 | Causeway Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
11. | 04-08-2015 | 54.000 | RW Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
12. | 03-08-2015 | Ch19+075 | Causeway with R/W | Asha rawat | JE | DEA ADB Dehradun | See Pic |
13. | 03-08-2015 | 54.00 | RW Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
14. | 09-05-2015 | Km 29.850 | R/W in progress | Shankar Ram | SE | ADB Circle | See Pic |
15. | 09-05-2015 | Km 19.250 | R/w is being started after excavation | Shankar Ram | SE | ADB Circle | See Pic |
|
|