Lambgaon-Pratapnager-Tehri MR (Km. 19.00)
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5313 |
Sanction Cost: |
162.00 lakh |
Length:
|
0.040 KM. |
District: |
Tehri |
Block: |
Pratapnagar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1101
Package Name: 
UEAP/PWD/C-107
Tender Date: 18-06-2016
Current Status: Agreement signed
Achieved on Date: 31-01-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-107
Contractor Name: Pioneer Foundation Engineers
|
Start Date: 23-02-2017
Intended Completion Date: 22-09-2017
|
Total Bond Cost: 14797199.48 (147.97 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 924875 for 125 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.10 KM | 2.94 | 28-04-2017 | 28-05-2017 | 0.10 KM | 0.10 KM | 1.99 | 2.94 | 2. | R/Wall, B/ Wall Type Protection works | 90.00 m | 143.22 | 15-05-2017 | 15-08-2017 | 90.00 m | 80.00 m | 86.03 | 127.31 | 3. | Other Allied Works & Finishing Work | 1.00 Job | 1.81 | 24-04-2017 | 01-08-2017 | 1.00 Job | 1.00 Job | 1.22 | 1.81 |
Total Amount: |
147.97 |
|
89.25 |
132.06 |
|
Remarks:
No Remarks
Work Program Made On:
11-09-2017 } ?>
Updation of work program on:
21-09-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 15-June-2017 | 81.12 lakh | 2. | 29-July-2017 | 11.20 lakh |
Total |
92.32 lakh |
% Payment |
62.39 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
Staff not deputed yet
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
Test Information not Available. |
Quality Ranking in %: 95.00 |
Number of Notice(s) issued: 18 |
Mobile Pic Upload |
No Pics Available on Web Repository |
( last 20 Pics) |
No Pic uploaded. |
|