Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tehri-Ghansali-Tilwara (Km 2700- 6102) Work Completed
Project: UEAP-RB UID: 5306 Sanction Cost: 312.00  lakh Length: 34.020 KM.
District: Tehri Block: Bhilangana Constituency: Ghanshali Circle:
DEA: DEA UEAP Tehri DSC: Royal Haskoning DHV DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1046        Package Name:  UEAP/PWD/C43        Tender Date: 11-09-2014        Current Status: Agreement signed        Achieved on Date: 10-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C43      Contractor Name: Betal Singh Kumai
Start Date:  06-03-2015      Intended Completion Date:  02-09-2016     
Total Bond Cost: 24089093 (240.89 lakh)        Variation Cost: 7090181.60 (70.9 lakh)    Hence Total Bond Cost is   31179274.6 (311.79 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.88 KM7.0204-03-201530-04-20150.88 KM0.88 KM2.997.02
2.R/Wall, B/ Wall Type Protection works1776.00 m171.8501-04-201531-12-20151776.00 m1776.00 m73.23171.85
3.SDBC i/c Tackcoat2.90 KM37.1801-06-201530-06-20153.35 KM3.35 KM15.8437.18
4.Cause Way2.00 No9.1701-04-201531-12-20152.00 No2.00 No3.919.17
5.longitudinal Drain1700.00 m9.4501-04-201531-12-20151700.00 m1700.00 m4.039.45
Total Amount: 234.67 100   234.67
Remarks: No Remarks       Work Program Made On: 17-05-2015        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-May-201515.05  lakh
2.06-June-201510.57  lakh
3.20-June-201531.19  lakh
4.28-August-201523.94  lakh
5.07-October-201570.14  lakh
6.17-November-201520.43  lakh
7.19-March-201619.98  lakh
8.18-May-201647.66  lakh
9.24-June-201660.64  lakh
10.18-October-20164.76  lakh
Total 304.36  lakh
% Payment 97.63 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 328   No. of Test Done : 336    No. of Test Passed : 328   No. of Test Failed : 2   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.78
Number of Notice(s) issued: 62

Mobile Pic Upload

Number of Pics Available on Web Repository: 7
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-10-201537.450Wire crates work in progressJitendra Kumar 2JEUEAP R&B Tehri See Pic
2.05-10-201537.450Retaining wall completeJitendra Kumar 2JEUEAP R&B Tehri See Pic
3.21-05-2015Km38.060B/W & D/S wall of causeway completeShankar Ram SEADB Circle See Pic
4.21-05-2015Km 38.950B/W completeShankar Ram SEADB Circle See Pic
5.01-04-2015Install of HMP in progGaza-Nakot pkgC-39Jitendra KumarREDSC3 ADB See Pic
6.01-04-2015HMP campMaterials collection for bituminous work in program in pkg C-39Jitendra KumarREDSC3 ADB See Pic
7.01-04-2015HMP installation in program for bituminous work in Gaza- Nakot ,C-39Gaza-Nakot C-39Jitendra KumarREDSC3 ADB See Pic