Tehri-Ghansali-Tilwara (Km 2700- 6102)
Work Completed
|
Project: |
UEAP-RB |
UID: |
5306 |
Sanction Cost: |
312.00 lakh |
Length:
|
34.020 KM. |
District: |
Tehri |
Block: |
Bhilangana |
Constituency: |
Ghanshali |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1046
Package Name: 
UEAP/PWD/C43
Tender Date: 11-09-2014
Current Status: Agreement signed
Achieved on Date: 10-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C43
Contractor Name: Betal Singh Kumai
|
Start Date: 06-03-2015
Intended Completion Date: 02-09-2016
|
Total Bond Cost: 24089093 (240.89 lakh)
Variation Cost: 7090181.60 (70.9 lakh) Hence Total Bond Cost is 31179274.6 (311.79 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.88 KM | 7.02 | 04-03-2015 | 30-04-2015 | 0.88 KM | 0.88 KM | 2.99 | 7.02 | 2. | R/Wall, B/ Wall Type Protection works | 1776.00 m | 171.85 | 01-04-2015 | 31-12-2015 | 1776.00 m | 1776.00 m | 73.23 | 171.85 | 3. | SDBC i/c Tackcoat | 2.90 KM | 37.18 | 01-06-2015 | 30-06-2015 | 3.35 KM | 3.35 KM | 15.84 | 37.18 | 4. | Cause Way | 2.00 No | 9.17 | 01-04-2015 | 31-12-2015 | 2.00 No | 2.00 No | 3.91 | 9.17 | 5. | longitudinal Drain | 1700.00 m | 9.45 | 01-04-2015 | 31-12-2015 | 1700.00 m | 1700.00 m | 4.03 | 9.45 |
Total Amount: |
234.67 |
|
100 |
234.67 |
|
Remarks:
No Remarks
Work Program Made On:
17-05-2015 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-May-2015 | 15.05 lakh | 2. | 06-June-2015 | 10.57 lakh | 3. | 20-June-2015 | 31.19 lakh | 4. | 28-August-2015 | 23.94 lakh | 5. | 07-October-2015 | 70.14 lakh | 6. | 17-November-2015 | 20.43 lakh | 7. | 19-March-2016 | 19.98 lakh | 8. | 18-May-2016 | 47.66 lakh | 9. | 24-June-2016 | 60.64 lakh | 10. | 18-October-2016 | 4.76 lakh |
Total |
304.36 lakh |
% Payment |
97.63 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 328 No. of Test Done : 336 No. of Test Passed : 328 No. of Test Failed : 2 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.78 |
Number of Notice(s) issued: 62 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 7 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-10-2015 | 37.450 | Wire crates work in progress | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
2. | 05-10-2015 | 37.450 | Retaining wall complete | Jitendra Kumar 2 | JE | UEAP R&B Tehri | See Pic |
3. | 21-05-2015 | Km38.060 | B/W & D/S wall of causeway complete | Shankar Ram | SE | ADB Circle | See Pic |
4. | 21-05-2015 | Km 38.950 | B/W complete | Shankar Ram | SE | ADB Circle | See Pic |
5. | 01-04-2015 | Install of HMP in prog | Gaza-Nakot pkgC-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
6. | 01-04-2015 | HMP camp | Materials collection for bituminous work in program in pkg C-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
7. | 01-04-2015 | HMP installation in program for bituminous work in Gaza- Nakot ,C-39 | Gaza-Nakot C-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
|
|