Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Gaza-Nakot Work Completed
Project: UEAP-RB UID: 5304 Sanction Cost: 431.00  lakh Length: 16.000 KM.
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle:
DEA: DEA UEAP Tehri DSC: Royal Haskoning DHV DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1042        Package Name:  UEAP/PWD/C39        Tender Date: 26-04-2014        Current Status: Agreement signed        Achieved on Date: 20-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C39      Contractor Name: Shiv Shankar Construction Company
Start Date:  10-11-2014      Intended Completion Date:  09-05-2016     
Total Bond Cost: 37684616 (376.85 lakh)        Variation Cost: 5115499.58 (51.15 lakh)    Hence Total Bond Cost is   42800115.58 (428 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.51 KM3.4701-11-201431-12-20140.51 KM0.51 KM0.933.47
2.R/Wall, B/ Wall Type Protection works1482.00 m36.9825-11-201430-06-20151482.00 m1482.00 m9.9136.98
3.GSB/RBI/G-10.13 KM0.5710-04-201519-04-20150.13 KM0.13 KM0.150.57
4.G-20.13 KM0.4512-04-201521-04-20150.13 KM0.13 KM0.120.45
5.G-30.13 KM0.4820-04-201529-04-20150.13 KM0.13 KM0.130.48
6.BM i/c Prime Coat, Tack Coat1.10 KM28.2315-03-201527-04-20151.10 KM1.10 KM7.5628.23
7.SDBC i/c Tackcoat11.00 KM139.4820-03-201522-05-201511.00 KM11.00 KM37.36139.48
8.Culverts/Scupper 10.00 No20.9930-11-201431-05-201510.00 No10.00 No5.6220.99
9.longitudinal Drain20000.00 m14.4401-04-201529-04-201520000.00 m20000.00 m3.8714.44
10.Crash Barrier3750.00 m88.2030-11-201429-06-20153750.00 m3750.00 m23.6388.20
11.Parapet475.00 No12.6530-11-201431-05-2015475.00 No475.00 No3.3912.65
12.Road Furniture1072.00 No27.3901-06-201501-08-20151072.00 No1072.00 No7.3427.39
Total Amount: 373.33 100   373.33
Remarks: No Remarks       Work Program Made On: 26-02-2015        Updation of work program on: 22-07-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-December-20147.97  lakh
2.10-February-201535.75  lakh
3.09-March-201549.42  lakh
4.26-March-20157.00  lakh
5.29-May-2015190.23  lakh
6.26-June-201529.31  lakh
7.07-November-201512.63  lakh
8.15-January-201630.91  lakh
9.29-February-201623.21  lakh
10.05-May-201630.75  lakh
11.29-July-20172.23  lakh
Total 419.41  lakh
% Payment 97.99 %
Advance Amount:  52.62  lakh        Recovered Amount:  52.62  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 155   No. of Test Done : 157    No. of Test Passed : 155   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.75
Number of Notice(s) issued: 75

Mobile Pic Upload

Number of Pics Available on Web Repository: 27
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.14-01-2016ch.19+025Core cuttingAsha rawatJEDEA ADB Dehradun See Pic
2.09-05-201513+700Laying of B.MAsha rawatJEDEA ADB Dehradun See Pic
3.09-05-2015km17Laying of Tack coatAsha rawatJEDEA ADB Dehradun See Pic
4.09-05-2015Km17Laying of SDBCAsha rawatJEDEA ADB Dehradun See Pic
5.24-04-20150+150Compaction for BM laying surfaceSudarshan kumar PMEDSC3 ADB See Pic
6.24-04-2015C-39 ch. 0+350Cleaning by Compressor for SDBC layingSudarshan kumar PMEDSC3 ADB See Pic
7.24-04-2015C-39 ghaza - nakotSDBC laying in progressSudarshan kumar PMEDSC3 ADB See Pic
8.24-04-2015Hot mix plant runing for BM/ SDBCHMPSudarshan kumar PMEDSC3 ADB See Pic
9.08-04-2015HMPMaterials for bituminous work at plant site in c-39 is satisfiedJitendra KumarREDSC3 ADB See Pic
10.08-04-2015HMPInstallation of hmp has completed c-39Jitendra KumarREDSC3 ADB See Pic
11.08-04-2015HMPInstallation of hmp is ok in gaja nakot rd c-39Jitendra KumarREDSC3 ADB See Pic
12.02-04-2015Install of HMP in progGaza- Nakot c-39Jitendra KumarREDSC3 ADB See Pic
13.02-04-2015Material collection in program at HMP campGaza-Nakot C-39Jitendra KumarREDSC3 ADB See Pic
14.24-03-20156+560 to 7+000Excavation of foundation for MBC in prog.Jitendra KumarREDSC3 ADB See Pic
15.24-03-20152+200to6+560Cement used for concrete mix in foundations of MBCJitendra KumarREDSC3 ADB See Pic
16.24-03-20152+200to6+560MBC work in gaza-Nakoi c39Jitendra KumarREDSC3 ADB See Pic
17.24-03-20156+280to6+560MBC in prog gaza-nakot c39Jitendra KumarREDSC3 ADB See Pic
18.24-03-20152+200to6+560MBC work in prog gaza-Nakot C-39Jitendra KumarREDSC3 ADB See Pic
19.23-03-2015HMP in km78 of NH-94HMP is established for gaza nakot m/roadShankar Ram SEADB Circle See Pic
20.09-03-2015Km-7Constn of parapets is in progressShankar Ram SEADB Circle See Pic