Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pratapnagar-Tehri Agreement signed
Project: UEAP-RB UID: 5303 Sanction Cost: 917.00  lakh Length: 30.000 KM.
District: Tehri Block: Jakhanidhar Constituency: Pratapnagar Circle:
DEA: DEA UEAP Tehri DSC: DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1039        Package Name:  UEAP/PWD/C36        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 23-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C36      Contractor Name: ESPAN Infrastructure Ltd
Start Date:  19-03-2015      Intended Completion Date:  04-10-2016     
Total Bond Cost: 64955326.7 (649.55 lakh)        Variation Cost: 22926045.00 (229.26 lakh)    Hence Total Bond Cost is   87881371.7 (878.81 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2143548 for 66 days        LD Analysis for Milestone2: calculated LD is Rs 389736 for 12 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.17 KM12.3115-04-201530-05-20153.17 KM3.17 KM2.0212.31
2.R/Wall, B/ Wall Type Protection works1665.00 m145.2401-07-201531-08-20151665.00 m1665.00 m23.78145.24
3.GSB/RBI/G-14.05 KM5.0901-06-201531-08-20154.05 KM4.05 KM0.835.09
4.G-24.10 KM5.3001-06-201531-08-20154.10 KM4.10 KM0.875.30
5.G-35.61 KM15.0801-06-201531-08-20155.61 KM5.61 KM2.4715.08
6.BM i/c Prime Coat, Tack Coat9.00 KM83.4415-09-201530-11-20159.00 KM9.00 KM13.6683.44
7.SDBC i/c Tackcoat19.69 KM175.0801-03-201630-06-201619.69 KM19.69 KM28.66175.08
8.Cause Way2.00 No9.8201-07-201529-02-20162.00 No2.00 No1.619.82
9.Culverts/Scupper 17.00 No2.8801-07-201529-02-201617.00 No17.00 No0.472.88
10.longitudinal Drain11500.00 m13.2501-07-201529-02-201611500.00 m11500.00 m2.1713.25
11.Crash Barrier3230.00 m74.2901-06-201531-08-20153230.00 m3230.00 m12.1674.29
12.Parapet1170.00 No57.9001-07-201529-02-20161170.00 No1100.00 No8.9154.44
13.Road Furniture1367.00 No11.1501-06-201631-08-20161367.00 No0.00 No00.00
Total Amount: 610.83 97.61   596.22
Remarks: No Remarks       Work Program Made On: 09-08-2015        Updation of work program on: 09-01-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.24-March-20150.10  lakh
2.20-June-201522.50  lakh
3.08-October-201534.26  lakh
4.22-January-2016150.61  lakh
5.29-March-201633.55  lakh
6.29-April-2016195.32  lakh
7.02-June-201649.93  lakh
8.25-October-2016108.51  lakh
9.17-December-2016152.61  lakh
10.28-March-201745.28  lakh
11.21-April-201728.07  lakh
12.17-June-201741.96  lakh
Total 862.7  lakh
% Payment 98.17 %
Advance Amount:  65.00  lakh        Recovered Amount:  65.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): Sanitation Facility, DG set
Detailed report of this subproject
Quality
Test Information not Available.
Quality Ranking in %: 89.39
Number of Notice(s) issued: 68

Mobile Pic Upload

No Pics Available on Web Repository
( last 20 Pics)
No Pic uploaded.