Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pilkhi-Gadoliya Motor Road Work Completed
Project: UEAP-RB UID: 5301 Sanction Cost: 479.00  lakh Length: 8.500 KM.
District: Tehri Block: Bhilangana Constituency: Ghanshali Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1015        Package Name:  UEAP/PWD/C13        Tender Date: 26-04-2014        Current Status: Agreement signed        Achieved on Date: 15-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C13      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  07-11-2014      Intended Completion Date:  20-01-2017      Original End Date:  06-04-2016
Total Bond Cost: 43969327 (439.69 lakh)        Variation Cost: 6529180.00 (65.29 lakh)    Hence Total Bond Cost is   50498507 (504.99 lakh) 
Sub Project Cost: 371.00  lakh       
LD Analysis for Milestone1: calculated LD is Rs 131910 for 6 days        LD Analysis for Milestone2: calculated LD is Rs 2440335 for 111 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.49 KM10.4325-11-201427-07-20160.49 KM0.49 KM2.6310.43
2.R/Wall, B/ Wall Type Protection works1207.00 m168.0115-11-201401-10-20151207.00 m1207.00 m42.39168.01
3.GSB/RBI/G-10.40 KM2.8515-02-201515-05-20150.47 KM0.47 KM0.722.85
4.G-20.61 KM3.2115-02-201515-05-20150.61 KM0.61 KM0.813.21
5.G-32.08 KM12.1715-02-201515-05-20152.08 KM2.08 KM3.0712.17
6.BM i/c Prime Coat, Tack Coat2.08 KM45.0715-05-201530-04-20162.08 KM2.08 KM11.3745.07
7.SDBC i/c Tackcoat9.82 KM58.1215-05-201515-10-20159.82 KM9.82 KM14.6658.12
8.Cause Way3.00 No18.3315-06-201515-12-20153.00 No3.00 No4.6318.33
9.Culverts/Scupper 12.00 No43.3815-06-201515-10-201512.00 No12.00 No10.9543.38
10.Crash Barrier750.00 m18.7501-05-201531-05-2015750.00 m750.00 m4.7318.75
11.Parapet480.00 No11.4215-09-201503-10-2015480.00 No480.00 No2.8811.42
12.Road Furniture1197.00 No4.5901-05-201530-06-20151197.00 No1197.00 No1.164.59
Total Amount: 396.33 100   396.33
Remarks: No Remarks       Work Program Made On: 26-02-2015        Updation of work program on: 21-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-December-201414.70  lakh
2.10-March-201522.99  lakh
3.20-March-201511.65  lakh
4.11-June-201542.38  lakh
5.08-September-201517.46  lakh
6.20-October-201543.29  lakh
7.07-November-201521.83  lakh
8.06-February-201629.21  lakh
9.25-May-201634.46  lakh
10.06-July-2016123.16  lakh
11.16-November-201633.90  lakh
12.24-June-201717.08  lakh
13.27-September-201726.10  lakh
Total 438.21  lakh
% Payment118.12 %
Advance Amount:  44.00  lakh        Recovered Amount:  44.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 829   No. of Test Done : 858    No. of Test Passed : 829   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 106
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-08-2016Asena villagePlantation program is held by executive engg...one plant is equal to the 100 No's of SonShivendra PrakashAEUEAP- CA Tehri See Pic
2.15-08-2016Km 4 near asena villagePlantation program is held by executive engg. One plant is equal to the 100 No's of Son So Save tree.Shivendra PrakashAEUEAP- CA Tehri See Pic
3.15-08-20162+850Plantation program is held in Pilki Gadoliya by executive engg. ADB UEAPShivendra PrakashAEUEAP- CA Tehri See Pic
4.15-08-20162+725Plantation program is held in pkg C -13 With executive engg sir..Shivendra PrakashAEUEAP- CA Tehri See Pic
5.13-08-201612+300Measure thickness after core cuttingShivendra PrakashAEUEAP- CA Tehri See Pic
6.13-08-20167+200Measure thickness after core cuttingShivendra PrakashAEUEAP- CA Tehri See Pic
7.13-08-20166+960Measure thickness after core cuttingShivendra PrakashAEUEAP- CA Tehri See Pic
8.13-08-20166+960Core cutting testShivendra PrakashAEUEAP- CA Tehri See Pic
9.13-08-20164+740Measure thickness of BM & SDBC by core cuttingShivendra PrakashAEUEAP- CA Tehri See Pic
10.13-08-20164+740Core cuttingShivendra PrakashAEUEAP- CA Tehri See Pic
11.13-08-20164+515Core cutting of BM SDBCShivendra PrakashAEUEAP- CA Tehri See Pic
12.13-08-20163+400Measure core thickness & found satisfactoryShivendra PrakashAEUEAP- CA Tehri See Pic
13.13-08-20162+740Core cutting of BM & SDBCShivendra PrakashAEUEAP- CA Tehri See Pic
14.13-08-20162+010Measure thickness of core by Barnier's & found satisfactoryShivendra PrakashAEUEAP- CA Tehri See Pic
15.13-08-20162+010Core cutting test of BM & SDBCShivendra PrakashAEUEAP- CA Tehri See Pic
16.13-08-20160+045Core cutting of SDBCShivendra PrakashAEUEAP- CA Tehri See Pic
17.12-08-20165+350Visit by Executive engineer sir ( MBCB horizontal post work is in progress)Shivendra PrakashAEUEAP- CA Tehri See Pic
18.10-08-20165+100Horizontal post of MBCB is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
19.30-07-201610+750Vartical post of MBCB is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
20.22-07-20160+800Vertical post of MBCB work is in progressShivendra PrakashAEUEAP- CA Tehri See Pic