Pilkhi-Gadoliya Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5301 |
Sanction Cost: |
479.00 lakh |
Length:
|
8.500 KM. |
District: |
Tehri |
Block: |
Bhilangana |
Constituency: |
Ghanshali |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1015
Package Name: 
UEAP/PWD/C13
Tender Date: 26-04-2014
Current Status: Agreement signed
Achieved on Date: 15-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C13
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 07-11-2014
Intended Completion Date: 20-01-2017
Original End Date: 06-04-2016 |
Total Bond Cost: 43969327 (439.69 lakh)
Variation Cost: 6529180.00 (65.29 lakh) Hence Total Bond Cost is 50498507 (504.99 lakh)
|
Sub Project Cost: 371.00 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 131910 for 6 days
LD Analysis for Milestone2: calculated LD is Rs 2440335 for 111 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.49 KM | 10.43 | 25-11-2014 | 27-07-2016 | 0.49 KM | 0.49 KM | 2.63 | 10.43 | 2. | R/Wall, B/ Wall Type Protection works | 1207.00 m | 168.01 | 15-11-2014 | 01-10-2015 | 1207.00 m | 1207.00 m | 42.39 | 168.01 | 3. | GSB/RBI/G-1 | 0.40 KM | 2.85 | 15-02-2015 | 15-05-2015 | 0.47 KM | 0.47 KM | 0.72 | 2.85 | 4. | G-2 | 0.61 KM | 3.21 | 15-02-2015 | 15-05-2015 | 0.61 KM | 0.61 KM | 0.81 | 3.21 | 5. | G-3 | 2.08 KM | 12.17 | 15-02-2015 | 15-05-2015 | 2.08 KM | 2.08 KM | 3.07 | 12.17 | 6. | BM i/c Prime Coat, Tack Coat | 2.08 KM | 45.07 | 15-05-2015 | 30-04-2016 | 2.08 KM | 2.08 KM | 11.37 | 45.07 | 7. | SDBC i/c Tackcoat | 9.82 KM | 58.12 | 15-05-2015 | 15-10-2015 | 9.82 KM | 9.82 KM | 14.66 | 58.12 | 8. | Cause Way | 3.00 No | 18.33 | 15-06-2015 | 15-12-2015 | 3.00 No | 3.00 No | 4.63 | 18.33 | 9. | Culverts/Scupper | 12.00 No | 43.38 | 15-06-2015 | 15-10-2015 | 12.00 No | 12.00 No | 10.95 | 43.38 | 10. | Crash Barrier | 750.00 m | 18.75 | 01-05-2015 | 31-05-2015 | 750.00 m | 750.00 m | 4.73 | 18.75 | 11. | Parapet | 480.00 No | 11.42 | 15-09-2015 | 03-10-2015 | 480.00 No | 480.00 No | 2.88 | 11.42 | 12. | Road Furniture | 1197.00 No | 4.59 | 01-05-2015 | 30-06-2015 | 1197.00 No | 1197.00 No | 1.16 | 4.59 |
Total Amount: |
396.33 |
|
100 |
396.33 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015 } ?>
Updation of work program on:
21-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-December-2014 | 14.70 lakh | 2. | 10-March-2015 | 22.99 lakh | 3. | 20-March-2015 | 11.65 lakh | 4. | 11-June-2015 | 42.38 lakh | 5. | 08-September-2015 | 17.46 lakh | 6. | 20-October-2015 | 43.29 lakh | 7. | 07-November-2015 | 21.83 lakh | 8. | 06-February-2016 | 29.21 lakh | 9. | 25-May-2016 | 34.46 lakh | 10. | 06-July-2016 | 123.16 lakh | 11. | 16-November-2016 | 33.90 lakh | 12. | 24-June-2017 | 17.08 lakh | 13. | 27-September-2017 | 26.10 lakh |
Total |
438.21 lakh |
% Payment | 118.12 % |
|
Advance Amount: 44.00 lakh
Recovered Amount: 44.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 829 No. of Test Done : 858 No. of Test Passed : 829 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 106 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-08-2016 | Asena village | Plantation program is held by executive engg...one plant is equal to the 100 No's of Son | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
2. | 15-08-2016 | Km 4 near asena village | Plantation program is held by executive engg. One plant is equal to the 100 No's of Son So Save tree. | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
3. | 15-08-2016 | 2+850 | Plantation program is held in Pilki Gadoliya by executive engg. ADB UEAP | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
4. | 15-08-2016 | 2+725 | Plantation program is held in pkg C -13 With executive engg sir.. | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
5. | 13-08-2016 | 12+300 | Measure thickness after core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
6. | 13-08-2016 | 7+200 | Measure thickness after core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
7. | 13-08-2016 | 6+960 | Measure thickness after core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
8. | 13-08-2016 | 6+960 | Core cutting test | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
9. | 13-08-2016 | 4+740 | Measure thickness of BM & SDBC by core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
10. | 13-08-2016 | 4+740 | Core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
11. | 13-08-2016 | 4+515 | Core cutting of BM SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
12. | 13-08-2016 | 3+400 | Measure core thickness & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
13. | 13-08-2016 | 2+740 | Core cutting of BM & SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
14. | 13-08-2016 | 2+010 | Measure thickness of core by Barnier's & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
15. | 13-08-2016 | 2+010 | Core cutting test of BM & SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
16. | 13-08-2016 | 0+045 | Core cutting of SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
17. | 12-08-2016 | 5+350 | Visit by Executive engineer sir ( MBCB horizontal post work is in progress) | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
18. | 10-08-2016 | 5+100 | Horizontal post of MBCB is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
19. | 30-07-2016 | 10+750 | Vartical post of MBCB is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
20. | 22-07-2016 | 0+800 | Vertical post of MBCB work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
|
|