Sonprayag-Triyuginarayan
Work Completed
|
Project: |
UEAP-RB |
UID: |
5205 |
Sanction Cost: |
811.00 lakh |
Length:
|
12.500 KM. |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA UEAP Rudraprayag |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1033
Package Name: 
UEAP/PWD/C30
Tender Date: 07-04-2014
Current Status: Agreement signed
Achieved on Date: 01-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C30
Contractor Name: Gaurav Builder
|
Start Date: 10-12-2014
Intended Completion Date: 09-06-2016
|
Total Bond Cost: 81709393.5 (817.09 lakh)
Variation Cost: -1753515.43 (-17.54 lakh) Hence Total Bond Cost is 79955878.07 (799.56 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 5515425 for 135 days
LD Analysis for Milestone2: calculated LD is Rs 3390965 for 83 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.23 KM | 1.22 | 01-05-2014 | 15-05-2015 | 0.23 KM | 0.23 KM | 0.16 | 1.22 | 2. | R/Wall, B/ Wall Type Protection works | 1089.00 m | 91.89 | 15-12-2014 | 06-06-2016 | 1089.00 m | 1089.00 m | 11.84 | 91.89 | 3. | GSB/RBI/G-1 | 0.82 KM | 6.27 | 01-05-2015 | 27-05-2016 | 0.82 KM | 0.82 KM | 0.81 | 6.27 | 4. | G-2 | 0.88 KM | 6.02 | 01-05-2015 | 28-05-2016 | 0.88 KM | 0.88 KM | 0.78 | 6.02 | 5. | G-3 | 3.83 KM | 26.07 | 05-05-2015 | 28-05-2016 | 3.83 KM | 3.83 KM | 3.36 | 26.07 | 6. | BM i/c Prime Coat, Tack Coat | 10.63 KM | 249.28 | 15-05-2015 | 29-05-2016 | 10.63 KM | 10.63 KM | 32.11 | 249.28 | 7. | SDBC i/c Tackcoat | 11.58 KM | 141.19 | 01-06-2015 | 30-05-2016 | 11.58 KM | 11.58 KM | 18.19 | 141.19 | 8. | Cause Way | 2.00 No | 8.67 | 23-01-2016 | 30-05-2016 | 2.00 No | 2.00 No | 1.12 | 8.67 | 9. | Culverts/Scupper | 9.00 No | 12.64 | 01-03-2015 | 05-06-2016 | 9.00 No | 9.00 No | 1.63 | 12.64 | 10. | longitudinal Drain | 10554.00 m | 73.30 | 01-05-2015 | 06-06-2016 | 10554.00 m | 10554.00 m | 9.44 | 73.30 | 11. | Crash Barrier | 4208.00 m | 117.82 | 30-05-2015 | 30-05-2016 | 4208.00 m | 4208.00 m | 15.18 | 117.82 | 12. | Parapet | 625.00 No | 32.21 | 01-06-2015 | 06-06-2016 | 625.00 No | 625.00 No | 4.15 | 32.21 | 13. | Road Furniture | 5608.00 No | 9.66 | 15-06-2015 | 05-06-2016 | 5608.00 No | 5608.00 No | 1.24 | 9.66 |
Total Amount: |
776.24 |
|
100 |
776.24 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015 } ?>
Updation of work program on:
08-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 20.25 lakh | 2. | 08-May-2015 | 8.76 lakh | 3. | 20-June-2015 | 23.98 lakh | 4. | 25-July-2015 | 44.12 lakh | 5. | 08-October-2015 | 18.34 lakh | 6. | 26-October-2015 | 57.93 lakh | 7. | 06-November-2015 | 72.40 lakh | 8. | 30-November-2015 | 15.94 lakh | 9. | 22-January-2016 | 25.93 lakh | 10. | 08-February-2016 | 54.58 lakh | 11. | 29-February-2016 | 63.40 lakh | 12. | 19-March-2016 | 24.96 lakh | 13. | 22-April-2016 | 82.79 lakh | 14. | 14-June-2016 | 128.46 lakh | 15. | 29-June-2016 | 36.18 lakh | 16. | 06-August-2016 | 66.54 lakh | 17. | 28-October-2016 | 29.15 lakh | 18. | 27-December-2016 | 25.63 lakh | 19. | 22-August-2017 | 0.20 lakh |
Total |
799.54 lakh |
% Payment |
100 % |
|
Advance Amount: 81.71 lakh
Recovered Amount: 81.71 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 2082 No. of Test Done : 2097 No. of Test Passed : 2097 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.21 |
Number of Notice(s) issued: 66 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 44 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-07-2016 | 0+060 | BM & SDBC CORE CHEKING BY SE | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
2. | 11-02-2016 | Ch. 4.625, Sonprayag Triyuginarayan motor road. | Measurements checking of K C drain. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
3. | 11-02-2016 | Ch. 5.980, Sonprayag Triyuginarayan motor road. | Crash barrier measurements checking. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
4. | 14-10-2015 | Plant site C30 sonprayag triyuginarayan | BM Production checking temp. | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
5. | 14-10-2015 | Plant site C30 sonprayag triyuginarayan road | Breaking stone ballast | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
6. | 21-07-2015 | C30 sonp. Triyug. mr ch 9.470 | R wall under const. | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
7. | 21-07-2015 | C 30 sonp. Triyu. mr ch 2.845 | B wall completed | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
8. | 04-07-2015 | Ch 11+625 | Culvert work in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
9. | 04-07-2015 | Ch 10+304 | K C Drain in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
10. | 19-06-2015 | C30sonprayag triyuginarayan road ch11.760 | Check thickness of BM | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
11. | 19-06-2015 | C30 sonprayag triyginarayan road check 12.200 | Check thickness of BM | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
12. | 04-06-2015 | C30sonprayag triguginarayan road ch 11.440 | R Wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
13. | 04-06-2015 | C30sonprayag triguginarayan road ch2.450 | B wall complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
14. | 04-06-2015 | C30 sonprayag triguginarayan road ch9.450 | G-3 complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
15. | 04-06-2015 | C30sonprayag triguginarayan road ch11.400 | G-3 complete in km12 | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
16. | 04-06-2015 | C30sonprayag triguginarayan road ch11.675 | Kutcha drain in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
17. | 04-06-2015 | C30sonprayag triguginarayan road ch11.715 | Culvert in half width complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
18. | 04-06-2015 | C30sonprayag triguginarayan road ch11.760 | R Wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
19. | 04-06-2015 | C30sonprayag triguginarayan road ch12.065 | Culvert in half width complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
20. | 04-06-2015 | C30 sonprayag triguginarayan road plant site | Weigh bridge at HMP | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
|
|