Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Sonprayag-Triyuginarayan Work Completed
Project: UEAP-RB UID: 5205 Sanction Cost: 811.00  lakh Length: 12.500 KM.
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA UEAP Rudraprayag DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1033        Package Name:  UEAP/PWD/C30        Tender Date: 07-04-2014        Current Status: Agreement signed        Achieved on Date: 01-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C30      Contractor Name: Gaurav Builder
Start Date:  10-12-2014      Intended Completion Date:  09-06-2016     
Total Bond Cost: 81709393.5 (817.09 lakh)        Variation Cost: -1753515.43 (-17.54 lakh)    Hence Total Bond Cost is   79955878.07 (799.56 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 5515425 for 135 days        LD Analysis for Milestone2: calculated LD is Rs 3390965 for 83 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.23 KM1.2201-05-201415-05-20150.23 KM0.23 KM0.161.22
2.R/Wall, B/ Wall Type Protection works1089.00 m91.8915-12-201406-06-20161089.00 m1089.00 m11.8491.89
3.GSB/RBI/G-10.82 KM6.2701-05-201527-05-20160.82 KM0.82 KM0.816.27
4.G-20.88 KM6.0201-05-201528-05-20160.88 KM0.88 KM0.786.02
5.G-33.83 KM26.0705-05-201528-05-20163.83 KM3.83 KM3.3626.07
6.BM i/c Prime Coat, Tack Coat10.63 KM249.2815-05-201529-05-201610.63 KM10.63 KM32.11249.28
7.SDBC i/c Tackcoat11.58 KM141.1901-06-201530-05-201611.58 KM11.58 KM18.19141.19
8.Cause Way2.00 No8.6723-01-201630-05-20162.00 No2.00 No1.128.67
9.Culverts/Scupper 9.00 No12.6401-03-201505-06-20169.00 No9.00 No1.6312.64
10.longitudinal Drain10554.00 m73.3001-05-201506-06-201610554.00 m10554.00 m9.4473.30
11.Crash Barrier4208.00 m117.8230-05-201530-05-20164208.00 m4208.00 m15.18117.82
12.Parapet625.00 No32.2101-06-201506-06-2016625.00 No625.00 No4.1532.21
13.Road Furniture5608.00 No9.6615-06-201505-06-20165608.00 No5608.00 No1.249.66
Total Amount: 776.24 100   776.24
Remarks: No Remarks       Work Program Made On: 26-02-2015        Updation of work program on: 08-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201520.25  lakh
2.08-May-20158.76  lakh
3.20-June-201523.98  lakh
4.25-July-201544.12  lakh
5.08-October-201518.34  lakh
6.26-October-201557.93  lakh
7.06-November-201572.40  lakh
8.30-November-201515.94  lakh
9.22-January-201625.93  lakh
10.08-February-201654.58  lakh
11.29-February-201663.40  lakh
12.19-March-201624.96  lakh
13.22-April-201682.79  lakh
14.14-June-2016128.46  lakh
15.29-June-201636.18  lakh
16.06-August-201666.54  lakh
17.28-October-201629.15  lakh
18.27-December-201625.63  lakh
19.22-August-20170.20  lakh
Total 799.54  lakh
% Payment 100 %
Advance Amount:  81.71  lakh        Recovered Amount:  81.71  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 2082   No. of Test Done : 2097    No. of Test Passed : 2097   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.21
Number of Notice(s) issued: 66

Mobile Pic Upload

Number of Pics Available on Web Repository: 44
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-07-20160+060BM & SDBC CORE CHEKING BY SERavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
2.11-02-2016Ch. 4.625, Sonprayag Triyuginarayan motor road.Measurements checking of K C drain.Atul ShandilyaAEUEAP R&B Chamoli See Pic
3.11-02-2016Ch. 5.980, Sonprayag Triyuginarayan motor road.Crash barrier measurements checking.Atul ShandilyaAEUEAP R&B Chamoli See Pic
4.14-10-2015Plant site C30 sonprayag triyuginarayanBM Production checking temp.Anil Kumar MittalEEUEAP R&B Rudraprayag See Pic
5.14-10-2015Plant site C30 sonprayag triyuginarayan roadBreaking stone ballastAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
6.21-07-2015C30 sonp. Triyug. mr ch 9.470R wall under const.Sudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
7.21-07-2015C 30 sonp. Triyu. mr ch 2.845B wall completedSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
8.04-07-2015Ch 11+625Culvert work in progressAshok GuptaREDSC Rudraprayag See Pic
9.04-07-2015Ch 10+304K C Drain in progressAshok GuptaREDSC Rudraprayag See Pic
10.19-06-2015C30sonprayag triyuginarayan road ch11.760Check thickness of BMAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
11.19-06-2015C30 sonprayag triyginarayan road check 12.200Check thickness of BMAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
12.04-06-2015C30sonprayag triguginarayan road ch 11.440R Wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
13.04-06-2015C30sonprayag triguginarayan road ch2.450B wall completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
14.04-06-2015C30 sonprayag triguginarayan road ch9.450G-3 completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
15.04-06-2015C30sonprayag triguginarayan road ch11.400G-3 complete in km12Anil Kumar MittalEEUEAP R&B Rudraprayag See Pic
16.04-06-2015C30sonprayag triguginarayan road ch11.675Kutcha drain in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
17.04-06-2015C30sonprayag triguginarayan road ch11.715Culvert in half width completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
18.04-06-2015C30sonprayag triguginarayan road ch11.760R Wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
19.04-06-2015C30sonprayag triguginarayan road ch12.065Culvert in half width completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
20.04-06-2015C30 sonprayag triguginarayan road plant siteWeigh bridge at HMPAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic