Khirshu-Khedakhal-Kandai-Khankra
Work Completed
|
Project: |
UEAP-RB |
UID: |
5204 |
Sanction Cost: |
1193.00 lakh |
Length:
|
38.600 KM. |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
|
DEA: |
DEA UEAP Rudraprayag |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1032
Package Name: 
UEAP/PWD/C29
Tender Date: 07-04-2014
Current Status: Agreement signed
Achieved on Date: 14-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C29
Contractor Name: Bharat Construction
|
Start Date: 20-10-2014
Intended Completion Date: 19-04-2016
|
Total Bond Cost: 118060040 (1180.6 lakh)
Variation Cost: -5097216.00 (-50.97 lakh) Hence Total Bond Cost is 112962824 (1129.63 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 10861520 for 184 days
LD Analysis for Milestone2: calculated LD is Rs 10389280 for 176 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.91 KM | 1.76 | 01-05-2015 | 14-04-2016 | 0.91 KM | 0.91 KM | 0.15 | 1.76 | 2. | R/Wall, B/ Wall Type Protection works | 737.00 m | 109.67 | 17-11-2014 | 16-04-2016 | 737.00 m | 737.00 m | 9.46 | 109.67 | 3. | GSB/RBI/G-1 | 0.35 KM | 1.99 | 01-05-2015 | 14-04-2016 | 0.35 KM | 0.35 KM | 0.17 | 1.99 | 4. | G-2 | 1.34 KM | 6.05 | 05-05-2015 | 14-04-2016 | 1.34 KM | 1.34 KM | 0.52 | 6.05 | 5. | G-3 | 2.88 KM | 13.79 | 10-05-2015 | 14-04-2016 | 2.88 KM | 2.88 KM | 1.19 | 13.79 | 6. | BM i/c Prime Coat, Tack Coat | 18.80 KM | 500.12 | 10-05-2015 | 16-04-2016 | 18.80 KM | 18.80 KM | 43.12 | 500.12 | 7. | SDBC i/c Tackcoat | 19.96 KM | 233.81 | 15-05-2015 | 17-04-2016 | 19.96 KM | 19.96 KM | 20.16 | 233.81 | 8. | Cause Way | 11.00 No | 41.79 | 22-02-2015 | 16-04-2016 | 11.00 No | 11.00 No | 3.6 | 41.79 | 9. | Culverts/Scupper | 11.00 No | 25.03 | 22-02-2015 | 17-04-2016 | 11.00 No | 11.00 No | 2.16 | 25.03 | 10. | longitudinal Drain | 19401.00 m | 16.75 | 15-01-2015 | 04-03-2016 | 19401.00 m | 19401.00 m | 1.44 | 16.75 | 11. | Crash Barrier | 3932.00 m | 86.54 | 20-04-2015 | 17-04-2016 | 3932.00 m | 3932.00 m | 7.46 | 86.54 | 12. | Parapet | 95.00 No | 41.75 | 05-05-2015 | 17-04-2016 | 95.00 No | 95.00 No | 3.6 | 41.75 | 13. | Road Furniture | 9588.00 No | 80.80 | 01-06-2015 | 16-04-2016 | 9588.00 No | 9588.00 No | 6.97 | 80.80 |
Total Amount: |
1159.85 |
|
100 |
1159.85 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015 } ?>
Updation of work program on:
08-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 02-March-2015 | 5.49 lakh | 2. | 31-March-2015 | 15.92 lakh | 3. | 25-May-2015 | 21.99 lakh | 4. | 11-June-2015 | 61.99 lakh | 5. | 17-August-2015 | 88.56 lakh | 6. | 18-October-2015 | 38.02 lakh | 7. | 10-November-2015 | 30.70 lakh | 8. | 12-December-2015 | 89.41 lakh | 9. | 03-February-2016 | 20.98 lakh | 10. | 19-March-2016 | 53.75 lakh | 11. | 31-March-2016 | 43.82 lakh | 12. | 12-April-2016 | 117.55 lakh | 13. | 30-April-2016 | 70.16 lakh | 14. | 30-May-2016 | 228.12 lakh | 15. | 30-June-2016 | 262.50 lakh | 16. | 28-October-2016 | 43.19 lakh | 17. | 02-June-2017 | 27.73 lakh | 18. | 26-August-2017 | 0.20 lakh |
Total |
1220.08 lakh |
% Payment |
108.02 % |
|
Advance Amount: 118.06 lakh
Recovered Amount: 118.06 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 2861 No. of Test Done : 2903 No. of Test Passed : 2903 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.84 |
Number of Notice(s) issued: 80 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 92 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-10-2015 | C29 Khirsu khedakhal khankra Road | R Wall in progress at ch 38.080 | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
2. | 26-09-2015 | C29 khirsu khankra ch 38.100 | C/O R wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
3. | 26-09-2015 | C29 ch37.630 | Katcha drain in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
4. | 26-09-2015 | C29 khirsu khedakhal khankra road check 34.600 | HMP installation in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
5. | 14-09-2015 | Km 36.260, C-29 4K motor road. | R wall under construction. | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
6. | 27-07-2015 | C 29 khirsu khera khal mr ch 38.100 | R wall under construction | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
7. | 20-07-2015 | 4 K mr ch km 35 | Crash barier fixing | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
8. | 20-07-2015 | 4k mr ch 38.100 | R wall under const. | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
9. | 03-06-2015 | C _ 29, ch 32+425 | R/W in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
10. | 03-06-2015 | C - 29, ch 34+350 | Drain work in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
11. | 30-05-2015 | C29 khirsu khedakhal khankra road ch30.410 | Causeway in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
12. | 30-05-2015 | C9 khirsu khedakhal khankra road ch36.180 | R wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
13. | 16-05-2015 | C29 khirsu khedakhal khankra road ch34.490 | Causeway in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
14. | 16-05-2015 | C29 khirsu khedakhal khankra road km37 | R Wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
15. | 05-05-2015 | Ch29 khirsu khedakhal khnkra road ch27.800 | Crash barrier in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
16. | 05-05-2015 | C29 khirsu khedakhal hankra road ch25.310 | Excavation of R Wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
17. | 05-05-2015 | C 29, ch 36+230 | R / W inprogress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
18. | 05-05-2015 | C29khirsu khedakhal khankra road ch31.250 | Breaking of stone ballast | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
19. | 05-05-2015 | C29 khirsu khedakhal khankra road ch36.230 | R wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
20. | 05-05-2015 | C29 khirsu khedakhal khankra road ch 36.260 | Causeway in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
|
|