Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Guptkashi Kalimath Kotma Jaal Chaumasi Agreement signed
Project: UEAP-RB UID: 5201 Sanction Cost: 538.00  lakh Length: 18.000 KM.
District: Rudraprayag Block: unknown Constituency: Kedarnath Circle:
DEA: DEA UEAP Rudraprayag DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1011        Package Name:  UEAP/PWD/C9        Tender Date: 08-02-2014        Current Status: Agreement signed        Achieved on Date: 18-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C9      Contractor Name: Bharat Construction
Start Date:  08-08-2014      Intended Completion Date:  07-02-2016     
Total Bond Cost: 59482400 (594.82 lakh)        Variation Cost: -46794437.50 (-467.94 lakh)    Hence Total Bond Cost is   12687962.5 (126.88 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 6007682 for 202 days        LD Analysis for Milestone2: calculated LD is Rs 5442603 for 183 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.60 KM11.1401-05-201530-05-20151.60 KM0.40 KM0.692.79
2.R/Wall, B/ Wall Type Protection works741.00 m98.8215-01-201525-05-2015741.00 m610.00 m20.1581.35
3.GSB/RBI/G-11.55 KM9.7301-05-201520-05-20151.55 KM0.00 KM00.00
4.G-21.55 KM7.4105-03-201505-04-20151.55 KM0.00 KM00.00
5.G-31.55 KM7.8510-05-201530-05-20151.55 KM0.00 KM00.00
6.PC/CC i/c Prime Coat, Tack Coat2.65 KM41.5415-05-201515-06-20152.65 KM0.00 KM00.00
7.Cause Way4.00 No11.0008-03-201520-05-20154.00 No0.00 No00.00
8.Culverts/Scupper 22.00 No20.5508-03-201525-05-201522.00 No1.00 No0.230.93
9.longitudinal Drain14770.00 m45.3301-05-201530-06-201514770.00 m1675.00 m1.275.14
10.Crash Barrier3100.00 m105.4015-05-201515-06-20153100.00 m2328.00 m19.679.15
11.Parapet750.00 No25.2015-05-201520-06-2015750.00 No0.00 No00.00
12.Road Furniture1679.00 No19.8220-06-201530-06-20151679.00 No0.00 No00.00
Total Amount: 403.79 41.94   169.36
Remarks: No Remarks       Work Program Made On: 26-02-2015        Updation of work program on: 22-07-2016       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-March-20157.92  lakh
2.05-September-2015116.95  lakh
3.27-December-20160.62  lakh
Total 125.49  lakh
% Payment 98.9 %
Advance Amount:  59.48  lakh        Recovered Amount:  59.48  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 0   No. of Test Done : 42    No. of Test Passed : 42   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.74
Number of Notice(s) issued: 77

Mobile Pic Upload

Number of Pics Available on Web Repository: 42
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-07-2015Ch 19+500Road damaged due to heavy rainAshok GuptaREDSC Rudraprayag See Pic
2.23-07-2015Ch 20+400Road damaged due to rainAshok GuptaREDSC Rudraprayag See Pic
3.23-07-2015Ch 19+230Culvert completAshok GuptaREDSC Rudraprayag See Pic
4.23-07-2015Ch 11+200R/W in progressAshok GuptaREDSC Rudraprayag See Pic
5.15-05-2015C- 9, ch10+310Slip clearanceAshok GuptaREDSC Rudraprayag See Pic
6.15-05-2015C - 9, ch 11+175R/W excavation in progressAshok GuptaREDSC Rudraprayag See Pic
7.15-05-2015C - 9, ch 11+425R/W excavation in progressAshok GuptaREDSC Rudraprayag See Pic
8.14-05-2015C9 guptkasi kalimat kotma jalchomasi road ch11.425Excavation for foundation of R wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
9.14-05-2015C9 guptkasi kalimat kotma jalchomasi road ch12.550R wall for causeway in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
10.14-05-2015C9 gupta kalimat kotma jalchomasi road ch17.050Embankment work in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
11.14-05-2015C9 guptkasi kalimat kotma jalchomasi road ch19.225Culvert in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
12.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch15.425R Wall completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
13.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch11.175R Wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
14.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch10.250JCB workingAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
15.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch10.270R wall completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
16.26-04-2015C 9 , ch 15+400R/W inprogressAshok GuptaREDSC Rudraprayag See Pic
17.29-03-2015C 9, ch 18+400R/W inprogressAshok GuptaREDSC Rudraprayag See Pic
18.29-03-2015C 9, ch 18+400Site visit SE SrinagarAshok GuptaREDSC Rudraprayag See Pic
19.29-03-2015C 9, ch 18+400R/W inprogressAshok GuptaREDSC Rudraprayag See Pic
20.27-03-2015Ch 10.050R wall in progress c9Anil Kumar MittalEEUEAP R&B Rudraprayag See Pic