Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pokhri-Gopeshwar Motor Road Agreement signed
Project: UEAP-RB UID: 5119 Sanction Cost: 582.00  lakh Length: KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1054        Package Name:  UEAP/PWD/C51        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C51      Contractor Name: R.G. Buildwell.
Start Date:  05-03-2015      Intended Completion Date:  15-03-2017      Original End Date:  04-09-2016
Total Bond Cost: 49371747 (493.72 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 1258986 for 51 days        LD Analysis for Milestone2: calculated LD is Rs 5653094 for 229 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.25 KM0.5715-07-201515-08-20150.25 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works1246.00 m164.1215-03-201510-02-20173746.00 m1100.00 m9.9642.55
3.GSB/RBI/G-10.02 KM0.1915-04-201512-10-20160.03 KM0.02 KM0.030.13
4.G-20.06 KM0.4015-04-201514-10-20160.07 KM0.06 KM0.070.34
5.G-30.78 KM5.2915-04-201516-10-20160.78 KM0.78 KM1.095.29
6.BM i/c Prime Coat, Tack Coat0.84 KM24.2901-04-201520-10-20160.84 KM0.84 KM5.0224.29
7.SDBC i/c Tackcoat2.62 KM50.8801-04-201525-10-20163.30 KM2.62 KM8.3540.39
8.Cause Way23.00 No136.9819-09-201505-03-201723.00 No0.00 No00.00
9.Culverts/Scupper 79.00 No7.2301-04-201531-01-201779.00 No60.00 No1.135.49
10.longitudinal Drain24000.00 m41.0101-04-201501-01-20172800.00 m2800.00 m8.4841.01
11.Crash Barrier585.00 m18.7201-12-201515-02-2017585.00 m585.00 m3.8718.72
12.Road Furniture1146.00 No23.3801-12-201515-03-20171148.00 No700.00 No2.958.71
13.Other Allied Works & Finishing Work 3.00 Job10.7610-01-201715-03-20173.00 Job0.00 Job00.00
Total Amount: 483.82 40.95   186.92
Remarks: No Remarks       Work Program Made On: 26-02-2015        Updation of work program on: 15-03-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.03-June-201517.33  lakh
2.21-July-201518.51  lakh
3.28-August-201517.08  lakh
4.05-November-201554.43  lakh
5.11-March-201612.47  lakh
6.04-August-201653.86  lakh
7.24-October-201677.19  lakh
8.10-December-201667.51  lakh
9.07-February-201750.64  lakh
10.24-March-201726.13  lakh
11.29-April-201748.25  lakh
Total 443.4  lakh
% Payment 89.8 %
Advance Amount:  49.37  lakh        Recovered Amount:  36.18  lakh        Balance to be Recovered  13.19  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): workmen Insurance
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 62   No. of Test Done : 92    No. of Test Passed : 92   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.57
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 49
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion channel work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
2.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12RCC wall completedRachna BahugunaJEUEAP R&B Chamoli See Pic
3.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion channel work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
4.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion channel work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
5.26-07-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion work over PCC block in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
6.26-07-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion work over PCC block in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
7.05-06-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion work in progress for Toe DamRachna BahugunaJEUEAP R&B Chamoli See Pic
8.05-06-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12PCC block completed for Gabbion wallRachna BahugunaJEUEAP R&B Chamoli See Pic
9.24-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12RCC work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
10.24-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Reinforcement completed for RCC wallRachna BahugunaJEUEAP R&B Chamoli See Pic
11.13-05-2017Slip zone/km12 from pokhariReinforcements cheking for RCC Wall.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
12.13-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Reinforcement in progress for RCC wallRachna BahugunaJEUEAP R&B Chamoli See Pic
13.13-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Self driven soil anchor in progress for nala stopperRachna BahugunaJEUEAP R&B Chamoli See Pic
14.06-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12PCC for RCC retaining wallRachna BahugunaJEUEAP R&B Chamoli See Pic
15.02-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 1230m gabbion stopper work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
16.29-04-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 1230m gabbion stopper work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
17.26-04-2017Chronic slip zone km 12Gabbion toe Dam in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
18.26-04-2017Chronic slip zone km 12Excavation for 30m gabbion stopper in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
19.13-04-2017Chronic slip zoneExcavation for Gabbion toe Dam in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
20.24-03-2017Chronic slip zone near village SalnaExcavation for RCC wallRachna BahugunaJEUEAP R&B Chamoli See Pic