Gauchar-Sidoli Motor Raod
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5116 |
Sanction Cost: |
1154.00 lakh |
Length:
|
23.400 KM. |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1052
Package Name: 
UEAP/PWD/C49
Tender Date: 26-09-2014
Current Status: Agreement signed
Achieved on Date: 22-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C49
Contractor Name: R.G. Buildwell.
|
Start Date: 01-05-2015
Intended Completion Date: 15-03-2017
Original End Date: 31-10-2016 |
Total Bond Cost: 160361906 (1603.62 lakh)
Variation Cost: 42216626.00 (422.17 lakh) Hence Total Bond Cost is 202578532 (2025.79 lakh)
|
Sub Project Cost: 1124.80 lakh
Variation Cost of Sub Project: 42216626.00 (422.17 lakh)
Total Sub Project Cost:
1546.97 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 7216290 for 90 days
LD Analysis for Milestone2: calculated LD is Rs 320724 for 4 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.25 KM | 13.91 | 15-08-2015 | 02-02-2017 | 1.25 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 1408.00 m | 206.59 | 20-07-2015 | 15-02-2017 | 1408.00 m | 1250.00 m | 12.11 | 183.41 | 3. | GSB/RBI/G-1 | 1.62 KM | 14.92 | 01-01-2016 | 25-09-2016 | 1.62 KM | 1.50 KM | 0.91 | 13.82 | 4. | G-2 | 4.07 KM | 24.93 | 10-01-2016 | 25-09-2016 | 4.07 KM | 3.90 KM | 1.58 | 23.89 | 5. | G-3 | 7.53 KM | 51.03 | 10-01-2016 | 28-09-2016 | 7.53 KM | 6.80 KM | 3.04 | 46.08 | 6. | BM i/c Prime Coat, Tack Coat | 23.15 KM | 566.80 | 15-03-2016 | 05-10-2016 | 23.15 KM | 21.20 KM | 34.27 | 519.06 | 7. | SDBC i/c Tackcoat | 23.15 KM | 409.82 | 15-03-2016 | 10-10-2016 | 23.15 KM | 20.60 KM | 24.08 | 364.68 | 8. | Cause Way | 4.00 No | 74.76 | 15-08-2015 | 05-02-2017 | 4.00 No | 4.00 No | 4.94 | 74.76 | 9. | Culverts/Scupper | 82.00 No | 10.74 | 15-08-2015 | 05-02-2017 | 80.00 No | 60.00 No | 0.53 | 8.05 | 10. | longitudinal Drain | 24860.00 m | 53.77 | 20-07-2015 | 01-01-2017 | 24860.00 m | 20850.00 m | 2.98 | 45.10 | 11. | Crash Barrier | 1040.00 m | 33.28 | 20-05-2016 | 28-02-2017 | 1040.00 m | 1040.00 m | 2.2 | 33.28 | 12. | Road Furniture | 1379.00 No | 52.17 | 01-01-2016 | 28-02-2017 | 1379.00 No | 800.00 No | 2 | 30.26 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 1.96 | 01-12-2016 | 28-02-2017 | 2.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
1514.68 |
|
88.63 |
1342.39 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2017 } ?>
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-October-2015 | 52.49 lakh | 2. | 09-November-2015 | 98.60 lakh | 3. | 05-December-2015 | 42.68 lakh | 4. | 20-February-2016 | 41.80 lakh | 5. | 11-March-2016 | 175.04 lakh | 6. | 21-March-2016 | 78.93 lakh | 7. | 28-April-2016 | 106.31 lakh | 8. | 09-May-2016 | 155.66 lakh | 9. | 08-July-2016 | 79.52 lakh | 10. | 23-October-2016 | 199.65 lakh | 11. | 22-November-2016 | 29.41 lakh | 12. | 17-January-2017 | 94.32 lakh | 13. | 07-March-2017 | 36.49 lakh | 14. | 24-March-2017 | 113.27 lakh | 15. | 29-April-2017 | 16.52 lakh | 16. | 06-June-2017 | 97.45 lakh | 17. | 17-June-2017 | 10.51 lakh |
Total |
1428.65 lakh |
% Payment | 92.35 % |
|
Advance Amount: 41.65 lakh
Recovered Amount: 115.73 lakh
Balance to be Recovered -74.08 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles, workmen Insurance
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 493 No. of Test Done : 652 No. of Test Passed : 652 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.77 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 17 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-12-2016 | C49 (Gauchar Sidoli)/13+00 v/s | PCC M15 work in progress in cc Road. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
2. | 05-12-2016 | Km 13 ( Ch. 12+720), Gauchar Sidoli motor road. | Concrete work in CC road. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
3. | 02-12-2016 | C49 (gauchar siddoli | R.c.c. M15 work in progress in cc road at chainage12+730. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
4. | 18-11-2016 | 15+500 | Excavation work is on progress | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
5. | 16-11-2016 | C49/15+500 | Excavation work in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
6. | 09-11-2016 | C49 Gauchar Sidoli/6+100 | Crash barrier work in progress above chainage. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
7. | 09-11-2016 | 12+500 | Tree guard fixed at site | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
8. | 05-11-2016 | C49 Gauchar Sidoli (Gwad)/22+560 | Road cutting work in progress Hillside. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
9. | 04-11-2016 | Km 23 (CH. 22+500 approx.), Gauchar Sidoli motor road. | Hill side cutting work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
10. | 08-10-2016 | Km 1.550, Gauchar Sidoli motor road. | Breast wall under construction. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
11. | 24-04-2016 | 15+450 | BC Laying | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
12. | 17-11-2015 | Gauchar Sidholi road/ 6+700 | BC Laying under progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
13. | 17-11-2015 | Gauchar Sidholi road/ 6+750 | BC laying under progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
14. | 16-11-2015 | 6.100 | BM Laying | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
15. | 15-11-2015 | 6+500 | BM Rolling | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
16. | 15-11-2015 | 6+570 | BM Laying | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
17. | 15-11-2015 | 6+600 | BM Tack Coat | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
|
|