Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Gauchar-Sidoli Motor Raod Agreement signed
Project: UEAP-RB UID: 5116 Sanction Cost: 1154.00  lakh Length: 23.400 KM.
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1052        Package Name:  UEAP/PWD/C49        Tender Date: 26-09-2014        Current Status: Agreement signed        Achieved on Date: 22-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C49      Contractor Name: R.G. Buildwell.
Start Date:  01-05-2015      Intended Completion Date:  15-03-2017      Original End Date:  31-10-2016
Total Bond Cost: 160361906 (1603.62 lakh)        Variation Cost: 42216626.00 (422.17 lakh)    Hence Total Bond Cost is   202578532 (2025.79 lakh) 
Sub Project Cost: 1124.80  lakh        Variation Cost of Sub Project: 42216626.00  (422.17 lakh)       Total Sub Project Cost:   1546.97 lakh
LD Analysis for Milestone1: calculated LD is Rs 7216290 for 90 days        LD Analysis for Milestone2: calculated LD is Rs 320724 for 4 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.25 KM13.9115-08-201502-02-20171.25 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works1408.00 m206.5920-07-201515-02-20171408.00 m1250.00 m12.11183.41
3.GSB/RBI/G-11.62 KM14.9201-01-201625-09-20161.62 KM1.50 KM0.9113.82
4.G-24.07 KM24.9310-01-201625-09-20164.07 KM3.90 KM1.5823.89
5.G-37.53 KM51.0310-01-201628-09-20167.53 KM6.80 KM3.0446.08
6.BM i/c Prime Coat, Tack Coat23.15 KM566.8015-03-201605-10-201623.15 KM21.20 KM34.27519.06
7.SDBC i/c Tackcoat23.15 KM409.8215-03-201610-10-201623.15 KM20.60 KM24.08364.68
8.Cause Way4.00 No74.7615-08-201505-02-20174.00 No4.00 No4.9474.76
9.Culverts/Scupper 82.00 No10.7415-08-201505-02-201780.00 No60.00 No0.538.05
10.longitudinal Drain24860.00 m53.7720-07-201501-01-201724860.00 m20850.00 m2.9845.10
11.Crash Barrier1040.00 m33.2820-05-201628-02-20171040.00 m1040.00 m2.233.28
12.Road Furniture1379.00 No52.1701-01-201628-02-20171379.00 No800.00 No230.26
13.Other Allied Works & Finishing Work 2.00 Job1.9601-12-201628-02-20172.00 Job0.00 Job00.00
Total Amount: 1514.68 88.63   1342.39
Remarks: No Remarks       Work Program Made On: 11-02-2017        Updation of work program on: 26-02-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.18-October-201552.49  lakh
2.09-November-201598.60  lakh
3.05-December-201542.68  lakh
4.20-February-201641.80  lakh
5.11-March-2016175.04  lakh
6.21-March-201678.93  lakh
7.28-April-2016106.31  lakh
8.09-May-2016155.66  lakh
9.08-July-201679.52  lakh
10.23-October-2016199.65  lakh
11.22-November-201629.41  lakh
12.17-January-201794.32  lakh
13.07-March-201736.49  lakh
14.24-March-2017113.27  lakh
15.29-April-201716.52  lakh
16.06-June-201797.45  lakh
17.17-June-201710.51  lakh
Total 1428.65  lakh
% Payment92.35 %
Advance Amount:  41.65  lakh        Recovered Amount:  115.73  lakh        Balance to be Recovered  -74.08  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, workmen Insurance
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 493   No. of Test Done : 652    No. of Test Passed : 652   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.77
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 17
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-12-2016C49 (Gauchar Sidoli)/13+00 v/sPCC M15 work in progress in cc Road.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
2.05-12-2016Km 13 ( Ch. 12+720), Gauchar Sidoli motor road.Concrete work in CC road.Atul ShandilyaAEUEAP R&B Chamoli See Pic
3.02-12-2016C49 (gauchar siddoliR.c.c. M15 work in progress in cc road at chainage12+730.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
4.18-11-201615+500Excavation work is on progressPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
5.16-11-2016C49/15+500Excavation work in progressGovind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
6.09-11-2016C49 Gauchar Sidoli/6+100Crash barrier work in progress above chainage.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
7.09-11-201612+500Tree guard fixed at sitePrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
8.05-11-2016C49 Gauchar Sidoli (Gwad)/22+560Road cutting work in progress Hillside.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
9.04-11-2016Km 23 (CH. 22+500 approx.), Gauchar Sidoli motor road.Hill side cutting work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
10.08-10-2016Km 1.550, Gauchar Sidoli motor road.Breast wall under construction.Atul ShandilyaAEUEAP R&B Chamoli See Pic
11.24-04-201615+450BC LayingRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
12.17-11-2015Gauchar Sidholi road/ 6+700BC Laying under progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
13.17-11-2015Gauchar Sidholi road/ 6+750BC laying under progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
14.16-11-20156.100BM LayingSubhash ChandraQCDSC2 R&B WB Tehri See Pic
15.15-11-20156+500BM RollingRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
16.15-11-20156+570BM LayingRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
17.15-11-20156+600BM Tack CoatRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic