Karanprayag- Nauti- Paithani Motor Road
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5115 |
Sanction Cost: |
492.00 lakh |
Length:
|
KM. |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1052
Package Name: 
UEAP/PWD/C49
Tender Date: 26-09-2014
Current Status: Agreement signed
Achieved on Date: 22-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C49
Contractor Name: R.G. Buildwell.
|
Start Date: 01-05-2015
Intended Completion Date: 15-03-2017
Original End Date: 31-10-2016 |
Total Bond Cost: 160361906 (1603.62 lakh)
Variation Cost: 42216626.00 (422.17 lakh) Hence Total Bond Cost is 202578532 (2025.79 lakh)
|
Sub Project Cost: 478.80 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 7216290 for 90 days
LD Analysis for Milestone2: calculated LD is Rs 320724 for 4 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.31 KM | 1.60 | 17-08-2015 | 02-02-2017 | 0.31 KM | 0.25 KM | 0.27 | 1.29 | 2. | R/Wall, B/ Wall Type Protection works | 207.00 m | 38.25 | 15-08-2015 | 15-02-2017 | 414.00 m | 375.00 m | 7.33 | 34.65 | 3. | GSB/RBI/G-1 | 0.39 KM | 3.64 | 15-10-2015 | 30-07-2016 | 0.39 KM | 0.39 KM | 0.77 | 3.64 | 4. | G-2 | 1.19 KM | 7.32 | 15-10-2015 | 30-07-2016 | 1.19 KM | 1.19 KM | 1.55 | 7.32 | 5. | G-3 | 3.42 KM | 23.21 | 15-10-2015 | 30-07-2016 | 3.42 KM | 3.42 KM | 4.91 | 23.21 | 6. | BM i/c Prime Coat, Tack Coat | 7.61 KM | 133.67 | 01-03-2016 | 10-10-2016 | 4.66 KM | 4.60 KM | 27.9 | 131.95 | 7. | SDBC i/c Tackcoat | 7.61 KM | 150.70 | 01-03-2016 | 11-10-2016 | 7.61 KM | 7.61 KM | 31.87 | 150.70 | 8. | Cause Way | 7.00 No | 19.74 | 15-08-2015 | 05-02-2017 | 7.00 No | 7.00 No | 4.18 | 19.74 | 9. | Culverts/Scupper | 22.00 No | 2.61 | 15-08-2015 | 05-02-2017 | 22.00 No | 21.00 No | 0.53 | 2.49 | 10. | longitudinal Drain | 7900.00 m | 19.67 | 15-08-2015 | 01-01-2017 | 7900.00 m | 7340.00 m | 3.87 | 18.28 | 11. | Crash Barrier | 1035.00 m | 33.12 | 15-05-2016 | 28-02-2017 | 1035.00 m | 1035.00 m | 7 | 33.12 | 12. | Road Furniture | 499.00 No | 24.38 | 15-05-2016 | 28-02-2017 | 499.00 No | 450.00 No | 4.65 | 21.98 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 14.99 | 01-12-2016 | 15-03-2017 | 2.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
472.9 |
|
94.81 |
448.37 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2017 } ?>
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-October-2015 | 52.49 lakh | 2. | 08-November-2015 | 35.45 lakh | 3. | 08-January-2016 | 18.28 lakh | 4. | 09-June-2016 | 105.40 lakh | 5. | 08-July-2016 | 9.55 lakh | 6. | 22-November-2016 | 46.40 lakh | 7. | 07-February-2017 | 41.42 lakh | 8. | 29-April-2017 | 60.06 lakh |
Total |
369.05 lakh |
% Payment | 77.08 % |
|
Advance Amount: 41.65 lakh
Recovered Amount: 115.73 lakh
Balance to be Recovered -74.08 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
PUC vehicles, workmen Insurance
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 493 No. of Test Done : 652 No. of Test Passed : 652 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.41 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 15 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 11-11-2016 | 39+750 | Bush cutting work is on progress | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
2. | 11-11-2016 | 39+610 | Thermoplastic has been completed | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
3. | 20-10-2016 | 40+400 | Take measurement of bm | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
4. | 16-10-2016 | Km 41.100, Karnprayag Nauti Paithani motor road. | BC work in progress freshly laid surface. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
5. | 16-10-2016 | Km 41.020, Karnprayag Nauti Paithani motor road. | BC work laid surface thickness checking by SE UEAP Srinagar. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
6. | 16-10-2016 | Km 40.950, Karnprayag Nauti Paithani motor road. | BM work laid surface thickness checking by SE UEAP Srinagar. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
7. | 16-10-2016 | 41+025 | Site visit of cp singh se sir | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
8. | 16-10-2016 | 41+000 | Site vistit of se sir and BC work is on progress....! | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
9. | 15-10-2016 | 41+500 | Bc work at curve | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
10. | 07-10-2016 | C49 K.N.P./41+150 | B.M. work in progress. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
11. | 07-10-2016 | C49 K.N.P.(Visoana)/41+260 | B.M.Rolling work in progress. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
12. | 07-10-2016 | C49 k.N.P.(Visona)/41+290 | B.M. work in progress. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
13. | 05-10-2016 | 41+800 | Bm work is on progress | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
14. | 03-10-2016 | Km 44.390, Karnprayag Nauti Paithani mtor road. | BC work laid surface. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
15. | 03-10-2016 | Km 47.050, Karnprayag Nauti Paithani motor road. | Old retaining wall damaged due to rain. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
|
|