Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Karanprayag- Nauti- Paithani Motor Road Agreement signed
Project: UEAP-RB UID: 5115 Sanction Cost: 492.00  lakh Length: KM.
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision Type: SH
Procurement:
Package No.: 1052        Package Name:  UEAP/PWD/C49        Tender Date: 26-09-2014        Current Status: Agreement signed        Achieved on Date: 22-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C49      Contractor Name: R.G. Buildwell.
Start Date:  01-05-2015      Intended Completion Date:  15-03-2017      Original End Date:  31-10-2016
Total Bond Cost: 160361906 (1603.62 lakh)        Variation Cost: 42216626.00 (422.17 lakh)    Hence Total Bond Cost is   202578532 (2025.79 lakh) 
Sub Project Cost: 478.80  lakh       
LD Analysis for Milestone1: calculated LD is Rs 7216290 for 90 days        LD Analysis for Milestone2: calculated LD is Rs 320724 for 4 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.31 KM1.6017-08-201502-02-20170.31 KM0.25 KM0.271.29
2.R/Wall, B/ Wall Type Protection works207.00 m38.2515-08-201515-02-2017414.00 m375.00 m7.3334.65
3.GSB/RBI/G-10.39 KM3.6415-10-201530-07-20160.39 KM0.39 KM0.773.64
4.G-21.19 KM7.3215-10-201530-07-20161.19 KM1.19 KM1.557.32
5.G-33.42 KM23.2115-10-201530-07-20163.42 KM3.42 KM4.9123.21
6.BM i/c Prime Coat, Tack Coat7.61 KM133.6701-03-201610-10-20164.66 KM4.60 KM27.9131.95
7.SDBC i/c Tackcoat7.61 KM150.7001-03-201611-10-20167.61 KM7.61 KM31.87150.70
8.Cause Way7.00 No19.7415-08-201505-02-20177.00 No7.00 No4.1819.74
9.Culverts/Scupper 22.00 No2.6115-08-201505-02-201722.00 No21.00 No0.532.49
10.longitudinal Drain7900.00 m19.6715-08-201501-01-20177900.00 m7340.00 m3.8718.28
11.Crash Barrier1035.00 m33.1215-05-201628-02-20171035.00 m1035.00 m733.12
12.Road Furniture499.00 No24.3815-05-201628-02-2017499.00 No450.00 No4.6521.98
13.Other Allied Works & Finishing Work 2.00 Job14.9901-12-201615-03-20172.00 Job0.00 Job00.00
Total Amount: 472.9 94.81   448.37
Remarks: No Remarks       Work Program Made On: 11-02-2017        Updation of work program on: 26-02-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.18-October-201552.49  lakh
2.08-November-201535.45  lakh
3.08-January-201618.28  lakh
4.09-June-2016105.40  lakh
5.08-July-20169.55  lakh
6.22-November-201646.40  lakh
7.07-February-201741.42  lakh
8.29-April-201760.06  lakh
Total 369.05  lakh
% Payment77.08 %
Advance Amount:  41.65  lakh        Recovered Amount:  115.73  lakh        Balance to be Recovered  -74.08  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, workmen Insurance
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 493   No. of Test Done : 652    No. of Test Passed : 652   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.41
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 15
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-11-201639+750Bush cutting work is on progressPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
2.11-11-201639+610Thermoplastic has been completedPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
3.20-10-201640+400Take measurement of bmPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
4.16-10-2016Km 41.100, Karnprayag Nauti Paithani motor road.BC work in progress freshly laid surface.Atul ShandilyaAEUEAP R&B Chamoli See Pic
5.16-10-2016Km 41.020, Karnprayag Nauti Paithani motor road.BC work laid surface thickness checking by SE UEAP Srinagar.Atul ShandilyaAEUEAP R&B Chamoli See Pic
6.16-10-2016Km 40.950, Karnprayag Nauti Paithani motor road.BM work laid surface thickness checking by SE UEAP Srinagar.Atul ShandilyaAEUEAP R&B Chamoli See Pic
7.16-10-201641+025Site visit of cp singh se sirPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
8.16-10-201641+000Site vistit of se sir and BC work is on progress....!Prabhansh SrivastavaJEUEAP R&B Chamoli See Pic
9.15-10-201641+500Bc work at curvePrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
10.07-10-2016C49 K.N.P./41+150B.M. work in progress.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
11.07-10-2016C49 K.N.P.(Visoana)/41+260B.M.Rolling work in progress.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
12.07-10-2016C49 k.N.P.(Visona)/41+290B.M. work in progress.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
13.05-10-201641+800Bm work is on progressPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
14.03-10-2016Km 44.390, Karnprayag Nauti Paithani mtor road.BC work laid surface.Atul ShandilyaAEUEAP R&B Chamoli See Pic
15.03-10-2016Km 47.050, Karnprayag Nauti Paithani motor road.Old retaining wall damaged due to rain.Atul ShandilyaAEUEAP R&B Chamoli See Pic