Reconstruction of Internal Roads of Nagarpalika Gopeshwar
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5109 |
Sanction Cost: |
234.00 lakh |
Length:
|
4.800 KM. |
District: |
Chamoli |
Block: |
Dasholi |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
Urban |
|
Procurement: |
Package No.: 1037
Package Name: 
UEAP/PWD/C34
Tender Date: 07-04-2014
Current Status: Agreement signed
Achieved on Date: 01-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C34
Contractor Name: Rami Construction
|
Start Date: 10-12-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-03-2016 |
Total Bond Cost: 23869139.5 (238.69 lakh)
Variation Cost: 11554617.80 (115.55 lakh) Hence Total Bond Cost is 35423757.3 (354.24 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1802185 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 2184105 for 183 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | G-3 | 1.05 KM | 7.08 | 28-02-2015 | 06-03-2016 | 1.05 KM | 0.04 KM | 0.08 | 0.27 | 2. | BM i/c Prime Coat, Tack Coat | 4.80 KM | 126.21 | 28-03-2015 | 09-03-2016 | 4.80 KM | 4.20 KM | 31.91 | 110.43 | 3. | SDBC i/c Tackcoat | 4.80 KM | 81.94 | 20-04-2015 | 09-03-2016 | 4.80 KM | 4.20 KM | 20.71 | 71.70 | 4. | Culverts/Scupper | 2.00 No | 1.27 | 28-02-2015 | 01-12-2016 | 2.00 No | 0.00 No | 0 | 0.00 | 5. | longitudinal Drain | 1210.00 m | 12.10 | 28-02-2015 | 01-12-2016 | 0.40 m | 0.38 m | 3.32 | 11.50 | 6. | Parapet | 65.00 No | 1.81 | 28-02-2015 | 01-12-2016 | 65.00 No | 65.00 No | 0.52 | 1.81 | 7. | Road Furniture | 1000.00 No | 8.26 | 20-02-2015 | 05-12-2016 | 1000.00 No | 880.00 No | 2.1 | 7.27 | 8. | Other Allied Works & Finishing Work | 3.00 Job | 107.45 | 20-04-2016 | 03-01-2017 | 3.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
346.12 |
|
58.64 |
202.98 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2017 } ?>
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 17-October-2015 | 5.17 lakh | 2. | 08-November-2015 | 38.18 lakh | 3. | 03-December-2015 | 36.43 lakh | 4. | 30-March-2016 | 33.73 lakh | 5. | 20-April-2016 | 12.66 lakh | 6. | 20-May-2016 | 12.24 lakh | 7. | 22-June-2016 | 15.19 lakh | 8. | 04-August-2016 | 57.70 lakh | 9. | 16-October-2016 | 24.99 lakh | 10. | 26-October-2016 | 15.42 lakh | 11. | 12-December-2016 | 19.32 lakh | 12. | 10-March-2017 | 18.69 lakh |
Total |
289.72 lakh |
% Payment |
81.78 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 105 No. of Test Done : 185 No. of Test Passed : 185 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.82 |
Number of Notice(s) issued: 69 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 131 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-12-2016 | Infront of kedarnath wildlife /0+840 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
2. | 01-12-2016 | Infront of government library /0+830 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
3. | 30-11-2016 | Gov't liberary /0+820 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
4. | 30-11-2016 | Kedar nath wildlife office /0+880 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
5. | 29-11-2016 | DM Quarter /1+000 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
6. | 27-11-2016 | DM Quarter /1+010 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
7. | 21-10-2016 | Badrinath forest office /1+020 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
8. | 21-10-2016 | Kund colony /1+240 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
9. | 17-10-2016 | Forest office/ 1+070 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
10. | 17-10-2016 | Rami plant / gigran road | Interlocking tiles face makings work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
11. | 15-10-2016 | Kund colony / 1+350 | Slopes checked for interlocking tiles fixing and laying. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
12. | 15-10-2016 | Rami plant / gigran road | Interlocking tiles casting work in progress. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
13. | 15-10-2016 | Kund colony /1+360 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
14. | 14-10-2016 | Kund colony /1+370 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
15. | 12-10-2016 | Kund colony /1+400 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
16. | 08-10-2016 | Kund colony /1+590 | Water curing on cc for interlocking tiles fixing in gap | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
17. | 05-10-2016 | Kund colony /1+700 | Pcc fill between road edge & interlocking tiles work progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
18. | 29-09-2016 | Kund colony 1+ 780 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
19. | 29-09-2016 | Kund colony /1+670 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
20. | 29-09-2016 | Kund colony /1+630 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
|
|