Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Reconstruction of Internal Roads of Nagarpalika Gopeshwar Agreement signed
Project: UEAP-RB UID: 5109 Sanction Cost: 234.00  lakh Length: 4.800 KM.
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: DSC Scope: Design & Supervision Type: Urban
Procurement:
Package No.: 1037        Package Name:  UEAP/PWD/C34        Tender Date: 07-04-2014        Current Status: Agreement signed        Achieved on Date: 01-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C34      Contractor Name: Rami Construction
Start Date:  10-12-2014      Intended Completion Date:  30-06-2017      Original End Date:  09-03-2016
Total Bond Cost: 23869139.5 (238.69 lakh)        Variation Cost: 11554617.80 (115.55 lakh)    Hence Total Bond Cost is   35423757.3 (354.24 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1802185 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 2184105 for 183 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.G-31.05 KM7.0828-02-201506-03-20161.05 KM0.04 KM0.080.27
2.BM i/c Prime Coat, Tack Coat4.80 KM126.2128-03-201509-03-20164.80 KM4.20 KM31.91110.43
3.SDBC i/c Tackcoat4.80 KM81.9420-04-201509-03-20164.80 KM4.20 KM20.7171.70
4.Culverts/Scupper 2.00 No1.2728-02-201501-12-20162.00 No0.00 No00.00
5.longitudinal Drain1210.00 m12.1028-02-201501-12-20160.40 m0.38 m3.3211.50
6.Parapet65.00 No1.8128-02-201501-12-201665.00 No65.00 No0.521.81
7.Road Furniture1000.00 No8.2620-02-201505-12-20161000.00 No880.00 No2.17.27
8.Other Allied Works & Finishing Work 3.00 Job107.4520-04-201603-01-20173.00 Job0.00 Job00.00
Total Amount: 346.12 58.64   202.98
Remarks: No Remarks       Work Program Made On: 11-02-2017        Updation of work program on: 26-02-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.17-October-20155.17  lakh
2.08-November-201538.18  lakh
3.03-December-201536.43  lakh
4.30-March-201633.73  lakh
5.20-April-201612.66  lakh
6.20-May-201612.24  lakh
7.22-June-201615.19  lakh
8.04-August-201657.70  lakh
9.16-October-201624.99  lakh
10.26-October-201615.42  lakh
11.12-December-201619.32  lakh
12.10-March-201718.69  lakh
Total 289.72  lakh
% Payment 81.78 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 105   No. of Test Done : 185    No. of Test Passed : 185   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.82
Number of Notice(s) issued: 69

Mobile Pic Upload

Number of Pics Available on Web Repository: 131
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-12-2016Infront of kedarnath wildlife /0+840Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
2.01-12-2016Infront of government library /0+830Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
3.30-11-2016Gov't liberary /0+820Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
4.30-11-2016Kedar nath wildlife office /0+880Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
5.29-11-2016DM Quarter /1+000Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
6.27-11-2016DM Quarter /1+010Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
7.21-10-2016Badrinath forest office /1+020Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
8.21-10-2016Kund colony /1+240Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
9.17-10-2016Forest office/ 1+070Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
10.17-10-2016Rami plant / gigran roadInterlocking tiles face makings work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
11.15-10-2016Kund colony / 1+350Slopes checked for interlocking tiles fixing and laying.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
12.15-10-2016Rami plant / gigran roadInterlocking tiles casting work in progress.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
13.15-10-2016Kund colony /1+360Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
14.14-10-2016Kund colony /1+370Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
15.12-10-2016Kund colony /1+400Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
16.08-10-2016Kund colony /1+590Water curing on cc for interlocking tiles fixing in gapSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
17.05-10-2016Kund colony /1+700Pcc fill between road edge & interlocking tiles work progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
18.29-09-2016Kund colony 1+ 780Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
19.29-09-2016Kund colony /1+670Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
20.29-09-2016Kund colony /1+630Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic