Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tharali-Dewal-Mundoli Agreement signed
Project: UEAP-RB UID: 5108 Sanction Cost: 1840.00  lakh Length: 20.870 KM.
District: Chamoli Block: Tharali Constituency: Tharali Circle:
DEA: DEA UEAP Chamoli DSC: DSC Scope: Design & Supervision Type: SH
Procurement:
Package No.: 1036        Package Name:  UEAP/PWD/C33        Tender Date: 07-04-2014        Current Status: Agreement signed        Achieved on Date: 14-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C33      Contractor Name: Bharat Construction
Start Date:  21-10-2014      Intended Completion Date:  20-04-2016     
Total Bond Cost: 192586507 (1925.87 lakh)        Variation Cost: 27750958.00 (277.51 lakh)    Hence Total Bond Cost is   220337465 (2203.37 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 18391963 for 191 days        LD Analysis for Milestone2: calculated LD is Rs 17525326 for +182 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works4790.00 m1000.0022-10-201420-12-20164610.00 m4600.00 m62.12997.83
2.GSB/RBI/G-10.79 KM6.2215-05-201520-02-20162.37 KM2.15 KM0.355.64
3.G-22.28 KM14.1220-05-201520-02-20162.37 KM2.15 KM0.812.08
4.G-33.11 KM20.1422-05-201520-02-20162.37 KM2.15 KM1.1418.27
5.PC/CC i/c Prime Coat, Tack Coat5.95 KM97.0205-08-201525-05-20166.60 KM5.95 KM5.4587.47
6.Culverts/Scupper 5.00 No14.7825-05-201520-02-201626.00 No18.00 No0.6410.23
7.longitudinal Drain22250.00 m22.6015-06-201530-01-201637695.00 m22000.00 m0.8213.04
8.Crash Barrier6880.00 m261.7405-05-201520-12-20166000.00 m6000.00 m16.3261.74
9.Parapet495.00 No9.6001-06-201525-12-20163700.00 No120.00 No0.020.08
10.Road Furniture1382.00 No34.3220-08-201515-12-20161382.00 No900.00 No1.3922.35
11.Other Allied Works & Finishing Work 8.00 Job125.7809-04-201620-12-20168.00 Job0.00 Job00.00
Total Amount: 1606.32 89.01   1428.73
Remarks: No Remarks       Work Program Made On: 27-02-2015        Updation of work program on: 26-02-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.27-April-201521.82  lakh
2.27-June-2015103.82  lakh
3.20-October-2015227.70  lakh
4.10-November-201573.26  lakh
5.25-January-2016133.88  lakh
6.20-February-2016122.40  lakh
7.31-March-2016151.58  lakh
8.23-April-2016109.81  lakh
9.10-May-201697.38  lakh
10.10-June-201668.79  lakh
11.15-July-2016130.39  lakh
12.07-September-201682.41  lakh
13.24-September-2016157.53  lakh
14.25-October-2016121.51  lakh
15.07-December-201679.21  lakh
16.21-January-201738.73  lakh
17.12-May-2017158.48  lakh
18.15-June-201784.29  lakh
19.20-July-201759.35  lakh
Total 2022.34  lakh
% Payment 91.77 %
Advance Amount:  192.59  lakh        Recovered Amount:  153.25  lakh        Balance to be Recovered  39.33  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 213   No. of Test Done : 284    No. of Test Passed : 284   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.13
Number of Notice(s) issued: 82

Mobile Pic Upload

Number of Pics Available on Web Repository: 120
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-12-2016Km 1 (Ch. 0+620), Tharali Dewal Mundoli motor road.Retaining wall construction work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
2.04-11-2016Km 2 (Ch. 1+700), Tharali Dewal Mundoli motor road.PC work laid surface.Atul ShandilyaAEUEAP R&B Chamoli See Pic
3.08-10-2016Km 2.060, Tharali Dewal Mundoli motor road.WBM (G1) work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
4.22-09-2016Km 1, Steel girder bridge approach site. Tharali Dewal Mundoli motor road (C-33).Reinforcement and shuttering work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
5.12-09-2016Km 1, Steel girder bridge approach site, Tharali Dewal Mundoli motor road.Mixing of concrete M15 work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
6.12-09-2016Km 1, Steel girder bridge approach site, Tharali Dewal Mundoli motor road.Reinforcement and shuttering work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
7.21-08-20160+750 belly bridge at tharali market c33Pcc at belly bridgeNaresh KumarTechnical OfficerDSC2 R&B ADB Chamoli See Pic
8.16-08-2016Km 1, Steel Girder Bridge approach site (Tharali Dewal Mundoli motor road).Reinforcement work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
9.27-07-201621+00/vill-kandaiTL,RE,CONTRACTOR SITE VISIT & DISCUSS WITH VILLAGE PEOPLEShubham ShandilyaTechnical AssistantDSC2 ADB See Pic
10.25-07-2016Km. 1.710, Tharali Dewal Mundoli motor roadRetaining wall protection work completed between Km. 1.560 to Km. 1.800.Atul ShandilyaAEUEAP R&B Chamoli See Pic
11.25-07-2016Km 2.070, Tharali Dewal Mundoli motor road.Retaining wall work completed.Atul ShandilyaAEUEAP R&B Chamoli See Pic
12.25-07-2016Km 21.235, Tharali Dewal Mundoli motor road.Retaining wall damaged due to heavy rain.Atul ShandilyaAEUEAP R&B Chamoli See Pic
13.25-07-2016Km 21.250, Tharal Dewal Mundoli motor road.Dry scupper damaged due heavy rainfall.Atul ShandilyaAEUEAP R&B Chamoli See Pic
14.04-07-2016Km. 2.140, Tharali Dewal Mundoli motor road.Retaining wall protection work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
15.19-05-2016Km 1, Steel girder bridge approach site, Tharali Dewal Mundoli motor road.Site visit of Project Manager & TL (SMEC (India) Pvt. Ltd. DSC-2)Atul ShandilyaAEUEAP R&B Chamoli See Pic
16.19-05-2016Km 1, Steel girder bridge site Tharali Dewal Mundoli motor road.Site visit of SE ADB (UEAP) Circle SrinagarAtul ShandilyaAEUEAP R&B Chamoli See Pic
17.19-05-2016Km.1, Steel girder bridge approach site,Tharali Dewal Mundoli motor road.Reinforcement and shuttering work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
18.19-05-2016Ch. 1.050, Tharali Dewal Mundoli motor road.Slip clearence in progress after cloud burst in Tharali.Atul ShandilyaAEUEAP R&B Chamoli See Pic
19.17-05-2016Km 1, Steel Girder Bridge Approach site.Reinforcement for raft foundation and vertical side walls.Atul ShandilyaAEUEAP R&B Chamoli See Pic
20.17-05-2016Steel Girder Bridge site Km. 1Plum concrete protection work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic