Tharali-Dewal-Mundoli
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5108 |
Sanction Cost: |
1840.00 lakh |
Length:
|
20.870 KM. |
District: |
Chamoli |
Block: |
Tharali |
Constituency: |
Tharali |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
Type: |
SH |
|
Procurement: |
Package No.: 1036
Package Name: 
UEAP/PWD/C33
Tender Date: 07-04-2014
Current Status: Agreement signed
Achieved on Date: 14-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C33
Contractor Name: Bharat Construction
|
Start Date: 21-10-2014
Intended Completion Date: 20-04-2016
|
Total Bond Cost: 192586507 (1925.87 lakh)
Variation Cost: 27750958.00 (277.51 lakh) Hence Total Bond Cost is 220337465 (2203.37 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 18391963 for 191 days
LD Analysis for Milestone2: calculated LD is Rs 17525326 for +182 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 4790.00 m | 1000.00 | 22-10-2014 | 20-12-2016 | 4610.00 m | 4600.00 m | 62.12 | 997.83 | 2. | GSB/RBI/G-1 | 0.79 KM | 6.22 | 15-05-2015 | 20-02-2016 | 2.37 KM | 2.15 KM | 0.35 | 5.64 | 3. | G-2 | 2.28 KM | 14.12 | 20-05-2015 | 20-02-2016 | 2.37 KM | 2.15 KM | 0.8 | 12.08 | 4. | G-3 | 3.11 KM | 20.14 | 22-05-2015 | 20-02-2016 | 2.37 KM | 2.15 KM | 1.14 | 18.27 | 5. | PC/CC i/c Prime Coat, Tack Coat | 5.95 KM | 97.02 | 05-08-2015 | 25-05-2016 | 6.60 KM | 5.95 KM | 5.45 | 87.47 | 6. | Culverts/Scupper | 5.00 No | 14.78 | 25-05-2015 | 20-02-2016 | 26.00 No | 18.00 No | 0.64 | 10.23 | 7. | longitudinal Drain | 22250.00 m | 22.60 | 15-06-2015 | 30-01-2016 | 37695.00 m | 22000.00 m | 0.82 | 13.04 | 8. | Crash Barrier | 6880.00 m | 261.74 | 05-05-2015 | 20-12-2016 | 6000.00 m | 6000.00 m | 16.3 | 261.74 | 9. | Parapet | 495.00 No | 9.60 | 01-06-2015 | 25-12-2016 | 3700.00 No | 120.00 No | 0.02 | 0.08 | 10. | Road Furniture | 1382.00 No | 34.32 | 20-08-2015 | 15-12-2016 | 1382.00 No | 900.00 No | 1.39 | 22.35 | 11. | Other Allied Works & Finishing Work | 8.00 Job | 125.78 | 09-04-2016 | 20-12-2016 | 8.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
1606.32 |
|
89.01 |
1428.73 |
|
Remarks:
No Remarks
Work Program Made On:
27-02-2015 } ?>
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-April-2015 | 21.82 lakh | 2. | 27-June-2015 | 103.82 lakh | 3. | 20-October-2015 | 227.70 lakh | 4. | 10-November-2015 | 73.26 lakh | 5. | 25-January-2016 | 133.88 lakh | 6. | 20-February-2016 | 122.40 lakh | 7. | 31-March-2016 | 151.58 lakh | 8. | 23-April-2016 | 109.81 lakh | 9. | 10-May-2016 | 97.38 lakh | 10. | 10-June-2016 | 68.79 lakh | 11. | 15-July-2016 | 130.39 lakh | 12. | 07-September-2016 | 82.41 lakh | 13. | 24-September-2016 | 157.53 lakh | 14. | 25-October-2016 | 121.51 lakh | 15. | 07-December-2016 | 79.21 lakh | 16. | 21-January-2017 | 38.73 lakh | 17. | 12-May-2017 | 158.48 lakh | 18. | 15-June-2017 | 84.29 lakh | 19. | 20-July-2017 | 59.35 lakh |
Total |
2022.34 lakh |
% Payment |
91.77 % |
|
Advance Amount: 192.59 lakh
Recovered Amount: 153.25 lakh
Balance to be Recovered 39.33 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 213 No. of Test Done : 284 No. of Test Passed : 284 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.13 |
Number of Notice(s) issued: 82 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 120 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-12-2016 | Km 1 (Ch. 0+620), Tharali Dewal Mundoli motor road. | Retaining wall construction work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
2. | 04-11-2016 | Km 2 (Ch. 1+700), Tharali Dewal Mundoli motor road. | PC work laid surface. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
3. | 08-10-2016 | Km 2.060, Tharali Dewal Mundoli motor road. | WBM (G1) work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
4. | 22-09-2016 | Km 1, Steel girder bridge approach site. Tharali Dewal Mundoli motor road (C-33). | Reinforcement and shuttering work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
5. | 12-09-2016 | Km 1, Steel girder bridge approach site, Tharali Dewal Mundoli motor road. | Mixing of concrete M15 work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
6. | 12-09-2016 | Km 1, Steel girder bridge approach site, Tharali Dewal Mundoli motor road. | Reinforcement and shuttering work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
7. | 21-08-2016 | 0+750 belly bridge at tharali market c33 | Pcc at belly bridge | Naresh Kumar | Technical Officer | DSC2 R&B ADB Chamoli | See Pic |
8. | 16-08-2016 | Km 1, Steel Girder Bridge approach site (Tharali Dewal Mundoli motor road). | Reinforcement work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
9. | 27-07-2016 | 21+00/vill-kandai | TL,RE,CONTRACTOR SITE VISIT & DISCUSS WITH VILLAGE PEOPLE | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
10. | 25-07-2016 | Km. 1.710, Tharali Dewal Mundoli motor road | Retaining wall protection work completed between Km. 1.560 to Km. 1.800. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
11. | 25-07-2016 | Km 2.070, Tharali Dewal Mundoli motor road. | Retaining wall work completed. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
12. | 25-07-2016 | Km 21.235, Tharali Dewal Mundoli motor road. | Retaining wall damaged due to heavy rain. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
13. | 25-07-2016 | Km 21.250, Tharal Dewal Mundoli motor road. | Dry scupper damaged due heavy rainfall. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
14. | 04-07-2016 | Km. 2.140, Tharali Dewal Mundoli motor road. | Retaining wall protection work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
15. | 19-05-2016 | Km 1, Steel girder bridge approach site, Tharali Dewal Mundoli motor road. | Site visit of Project Manager & TL (SMEC (India) Pvt. Ltd. DSC-2) | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
16. | 19-05-2016 | Km 1, Steel girder bridge site Tharali Dewal Mundoli motor road. | Site visit of SE ADB (UEAP) Circle Srinagar | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
17. | 19-05-2016 | Km.1, Steel girder bridge approach site,Tharali Dewal Mundoli motor road. | Reinforcement and shuttering work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
18. | 19-05-2016 | Ch. 1.050, Tharali Dewal Mundoli motor road. | Slip clearence in progress after cloud burst in Tharali. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
19. | 17-05-2016 | Km 1, Steel Girder Bridge Approach site. | Reinforcement for raft foundation and vertical side walls. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
20. | 17-05-2016 | Steel Girder Bridge site Km. 1 | Plum concrete protection work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
|
|