Reconstruction of Narshing Mandir Approach road under Nagar Palika Joshimath
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5105 |
Sanction Cost: |
381.00 lakh |
Length:
|
3.900 KM. |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
Type: |
Urban |
|
Procurement: |
Package No.: 1024
Package Name: 
UEAP/PWD/C21
Tender Date: 07-03-2014
Current Status: Agreement signed
Achieved on Date: 17-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C21
Contractor Name: R.G. Buildwell.
|
Start Date: 09-12-2014
Intended Completion Date: 08-06-2016
|
Total Bond Cost: 36798809.52 (367.99 lakh)
Variation Cost: 180267.35 (1.8 lakh) Hence Total Bond Cost is 36979076.87 (369.79 lakh)
|
Sub Project Cost: 381.00 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.00 KM | 0.00 | 01-06-2015 | 01-06-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 60.00 m | 5.10 | 01-04-2015 | 28-05-2016 | 260.00 m | 70.00 m | 0.75 | 1.37 | 3. | GSB/RBI/G-1 | 0.04 KM | 0.63 | 20-05-2015 | 20-02-2016 | 0.04 KM | 0.04 KM | 0.35 | 0.63 | 4. | G-2 | 0.06 KM | 0.50 | 20-05-2015 | 20-02-2016 | 0.06 KM | 0.06 KM | 0.27 | 0.50 | 5. | G-3 | 0.10 KM | 0.54 | 20-05-2015 | 20-02-2016 | 0.10 KM | 0.10 KM | 0.29 | 0.54 | 6. | BM i/c Prime Coat, Tack Coat | 3.45 KM | 82.61 | 01-06-2015 | 01-06-2016 | 3.90 KM | 3.90 KM | 44.89 | 82.61 | 7. | SDBC i/c Tackcoat | 3.45 KM | 48.33 | 01-06-2015 | 01-06-2016 | 3.90 KM | 3.90 KM | 26.27 | 48.33 | 8. | Cause Way | 0.00 No | 0.00 | 15-05-2015 | 15-05-2015 | 0.00 No | 0.00 No | 0 | 0.00 | 9. | Culverts/Scupper | 1.00 No | 1.26 | 15-05-2015 | 27-05-2016 | 3.00 No | 1.00 No | 0.23 | 0.42 | 10. | longitudinal Drain | 1095.00 m | 9.87 | 15-05-2015 | 30-06-2015 | 1095.00 m | 350.00 m | 1.71 | 3.15 | 11. | Crash Barrier | 384.00 m | 11.14 | 01-09-2015 | 24-05-2016 | 1120.00 m | 1000.00 m | 5.4 | 9.94 | 12. | Parapet | 60.00 No | 3.28 | 01-09-2015 | 30-05-2016 | 150.00 No | 40.00 No | 0.48 | 0.58 | 13. | Road Furniture | 40.00 No | 3.28 | 01-09-2015 | 16-05-2016 | 40.00 No | 0.00 No | 0 | 0.00 | 14. | Other Allied Works & Finishing Work | 2.00 Job | 17.48 | 02-06-2016 | 08-06-2016 | 2.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
184.02 |
|
80.64 |
148.07 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015 } ?>
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-August-2015 | 2.86 lakh | 2. | 07-November-2015 | 89.88 lakh | 3. | 25-January-2016 | 8.70 lakh | 4. | 30-March-2016 | 8.13 lakh | 5. | 07-June-2016 | 46.45 lakh | 6. | 27-August-2016 | 30.15 lakh | 7. | 17-June-2017 | 25.97 lakh |
Total |
212.14 lakh |
% Payment | 55.68 % |
|
Advance Amount: 36.80 lakh
Recovered Amount: 36.37 lakh
Balance to be Recovered 0.43 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
Borrow pits, DG set |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 0 No. of Test Done : 52 No. of Test Passed : 52 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 37 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-05-2016 | RGB HMP / Nandprayag | SDBC temperature checked at HMP Nandprayag for narsing Mandir road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
2. | 27-05-2016 | RGB HMP / Nandprayag | SDBC mix material production for narsing Mandir road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
3. | 22-05-2016 | RGB HMP / Nandprayag | SDBC temperature checked at HMP Nandprayag for narsing Mandir road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
4. | 22-05-2016 | RGB HMP / Nandprayag | SDBC mix material production for narsing Mandir road . | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
5. | 21-05-2016 | RGB HMP / Nandprayag | BM mix material temperatures checked at HMP Nandprayag for narsing Mandir road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
6. | 21-05-2016 | RGB HMP / Nandprayag | BM mix material production for narsing Mandir road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
7. | 06-02-2016 | Ch. 1.650, Joshimath Narsingh Mandir motor road. | Retaining wall under construction. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
8. | 05-02-2016 | 1+600 | R/wall | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
9. | 23-01-2016 | 1+630 | R/W in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
10. | 20-12-2015 | Narsing Mandir road/1+100 | Visit at site Social experts.Dr.Debasish Bhattacharya | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
11. | 04-11-2015 | Narsing Mandir road/ 1+650 | R/wall masonry work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
12. | 27-10-2015 | 1.600 | HIV camp by CREDA | Akhilesh Sharma | RE | DSC2 R&B ADB Chamoli | See Pic |
13. | 27-10-2015 | 1.600 | Retaining wall in progress | Akhilesh Sharma | RE | DSC2 R&B ADB Chamoli | See Pic |
14. | 27-10-2015 | 0.400 | Construction of Scupper in progress | Akhilesh Sharma | RE | DSC2 R&B ADB Chamoli | See Pic |
15. | 27-10-2015 | Km 1.900, Joshimath Narsingh Mandir motor road. | Laying of BM | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
16. | 19-10-2015 | Narshing mandir / 1+160 | BM IN PROGRESS | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
17. | 19-10-2015 | RGB PLANT / NANDPRYAG GHAT | BITUMEN EXTRACTION TEST ON THE PLANT | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
18. | 19-10-2015 | RGB PLANT / NANDPRYAG GHAT | SDBC TEMP ON PLANT | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
19. | 19-10-2015 | RGB PLANT / NANDPRYAG GHAT | SDBC MATERIAL PREPARING FOR NARSHING MANDIR | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
20. | 17-10-2015 | 1+520 | BM work in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
|
|