Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Chamoli - Kund Agreement signed
Project: UEAP-RB UID: 5103 Sanction Cost: 1094.00  lakh Length: 41.000 KM.
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1010        Package Name:  UEAP/PWD/C8        Tender Date: 08-02-2014        Current Status: Agreement signed        Achieved on Date: 18-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C8      Contractor Name: Bharat Construction
Start Date:  08-08-2014      Intended Completion Date:  07-05-2016      Original End Date:  07-02-2016
Total Bond Cost: 76899400 (768.99 lakh)        Variation Cost: -20378.89 (-0.2 lakh)    Hence Total Bond Cost is   76879021.11 (768.79 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 6997900 for +182 days        LD Analysis for Milestone2: calculated LD is Rs 9766300 for 254 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works270.00 m11.6208-08-201408-10-2015356.00 m270.00 m1.18.82
2.GSB/RBI/G-10.00 KM0.0025-02-201525-02-20150.46 KM0.20 KM00.00
3.G-20.00 KM0.0028-02-201528-02-20150.77 KM0.50 KM00.00
4.G-30.08 KM0.1102-03-201515-04-20151.05 KM0.75 KM0.010.08
5.BM i/c Prime Coat, Tack Coat9.20 KM280.1525-03-201510-04-20169.20 KM9.20 KM35.01280.15
6.SDBC i/c Tackcoat16.20 KM262.3401-04-201511-04-201616.20 KM16.20 KM32.79262.34
7.Cause Way2.00 No1.6018-02-201525-03-20163.00 No2.00 No0.131.07
8.Culverts/Scupper 2.00 No3.8911-02-201525-03-20154.00 No2.00 No0.241.94
9.longitudinal Drain5281.00 m52.6520-04-201420-06-20155281.00 m5281.00 m6.5852.65
10.Crash Barrier2380.00 m80.5125-05-201525-06-20152380.00 m2380.00 m10.0680.51
11.Parapet150.00 No4.2501-06-201515-07-2015252.00 No150.00 No0.322.53
12.Road Furniture877.00 No10.5810-02-201630-04-2016877.00 No0.00 No00.00
13.Other Allied Works & Finishing Work 2.00 Job92.4112-04-201603-05-20162.00 Job0.00 Job00.00
Total Amount: 800.11 86.25   690.09
Remarks: No Remarks       Work Program Made On: 27-02-2015        Updation of work program on: 26-02-2017       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-December-20146.11  lakh
2.29-May-201541.83  lakh
3.24-August-201562.61  lakh
4.08-November-201533.18  lakh
5.25-January-201648.22  lakh
6.30-March-201655.14  lakh
7.06-May-2016270.09  lakh
8.02-July-2016174.64  lakh
9.25-October-201646.73  lakh
10.10-May-201730.23  lakh
Total 768.78  lakh
% Payment 99.99 %
Advance Amount:  76.90  lakh        Recovered Amount:  76.90  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 155   No. of Test Done : 211    No. of Test Passed : 211   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.11
Number of Notice(s) issued: 78

Mobile Pic Upload

Number of Pics Available on Web Repository: 282
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-06-20161+727Metal beam Crash barrier work in progressRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
2.17-05-2016Ch. 36.190, Chamoli Kund motor road.Parapits under construction.Atul ShandilyaAEUEAP R&B Chamoli See Pic
3.23-04-2016C8/40+350BM work in progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
4.23-04-2016C8/40+410BM work in progress.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
5.23-04-2016C8/36+170Sdbc work in progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
6.20-04-2016Chopta road / 37+400BM laying in progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
7.20-04-2016Chopta road / 37+450BM laying & rolling work progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
8.20-04-2016Bharat HMP / ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
9.19-04-2016Bharat HMP /ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
10.19-04-2016Bharat HMP / ChamoliSDBC mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
11.18-04-2016Bharat HMP / ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
12.18-04-2016Bharat HMP /ChamoliSDBC mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
13.14-04-2016Chopta road / 38+570BM laying & rolling work progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
14.14-04-2016Chopta road / 38+850BM laying & rolling work progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
15.14-04-2016Bharat HMP / ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
16.13-04-2016C8 CH kind/39+050Sdbc Rolling work in progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
17.13-04-2016C8 CH kund/39+160Sdbc work&Rolling work in prpgressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
18.13-04-2016Bharat HMP / ChamoliSDBC mix material for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
19.12-04-2016Chopta road /39+050AE sir checked BM thickness during laying Chamoli kund road.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
20.12-04-2016Chopta road /39+150BM laying & rolling work in progress at Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic