Rudraprayag-pokhari-Karanprayag
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5102 |
Sanction Cost: |
112.00 lakh |
Length:
|
14.510 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 1009
Package Name: 
UEAP/PWD/C7
Tender Date: 08-02-2014
Current Status: Agreement signed
Achieved on Date: 18-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C7
Contractor Name: Bharat Construction
|
Start Date: 08-08-2014
Intended Completion Date: 05-04-2016
Original End Date: 07-11-2015 |
Total Bond Cost: 34799370 (347.99 lakh)
Variation Cost: 8478614.26 (84.79 lakh) Hence Total Bond Cost is 43277984.26 (432.78 lakh)
|
Sub Project Cost: 112.00 lakh
Variation Cost of Sub Project: 417767.00 (4.18 lakh)
Total Sub Project Cost:
116.18 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2644800 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 2470800 for 142 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.00 KM | 0.00 | 15-05-2015 | 15-05-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 110.00 m | 5.36 | 20-11-2014 | 10-12-2015 | 281.00 m | 130.00 m | 3.56 | 2.48 | 3. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 25-02-2015 | 25-02-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | G-2 | 0.00 KM | 0.00 | 20-03-2015 | 20-03-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-3 | 0.11 KM | 0.24 | 24-03-2015 | 15-05-2015 | 0.32 KM | 0.11 KM | 0.12 | 0.08 | 6. | BM i/c Prime Coat, Tack Coat | 0.48 KM | 10.90 | 20-05-2015 | 25-10-2015 | 0.48 KM | 0.43 KM | 14.02 | 9.76 | 7. | SDBC i/c Tackcoat | 2.79 KM | 32.64 | 27-05-2015 | 25-10-2015 | 2.79 KM | 2.79 KM | 46.89 | 32.64 | 8. | Cause Way | 0.00 No | 0.00 | 25-05-2015 | 25-05-2015 | 0.00 No | 0.00 No | 0 | 0.00 | 9. | Culverts/Scupper | 0.00 No | 0.00 | 28-05-2015 | 28-05-2015 | 0.00 No | 0.00 No | 0 | 0.00 | 10. | longitudinal Drain | 1750.00 m | 5.68 | 15-01-2015 | 25-03-2015 | 1750.00 m | 0.00 m | 0 | 0.00 | 11. | Crash Barrier | 400.00 m | 13.60 | 30-05-2015 | 25-03-2016 | 400.00 m | 400.00 m | 19.54 | 13.60 | 12. | Parapet | 0.00 No | 0.00 | 25-05-2015 | 25-05-2015 | 0.00 No | 0.00 No | 0 | 0.00 | 13. | Road Furniture | 95.00 No | 1.20 | 15-01-2016 | 25-03-2016 | 95.00 No | 0.00 No | 0 | 0.00 |
Total Amount: |
69.62 |
|
84.13 |
58.56 |
|
Remarks:
No Remarks
Work Program Made On:
27-02-2015 } ?>
Updation of work program on:
25-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 09-November-2015 | 59.73 lakh |
Total |
59.73 lakh |
% Payment | 51.41 % |
|
Advance Amount: 34.80 lakh
Recovered Amount: 34.80 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
labour licence, workmen Insurance
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 2 No. of Test Done : 41 No. of Test Passed : 41 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 27 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-11-2015 | Rudr.pokhri.karnapryag /C7 ch45+450 | Odbc laying&rolling in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
2. | 02-11-2015 | C7 R.p.k.(Bhardwar)/ch45+100 | Laying Sdbc work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
3. | 02-11-2015 | Bhardwaj R.P.K./45+435 | B.M. patch work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
4. | 02-11-2015 | 45+020 bhaurawan dhar | Sdbc work in progress . | Anurag Rawat | JE | UEAP R&B Chamoli | See Pic |
5. | 01-11-2015 | C7 R.P.K.(Bhairv dhar)/ch44+720 | Sdbc work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
6. | 01-11-2015 | Rudr P. Pokhri K./C7 ch44+580 | Sdbc patchwork in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
7. | 01-11-2015 | C7 R.P.K.(Mahankal)/44+160 | M.B.Crashbarrier work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
8. | 30-10-2015 | C7 R.P.K/44+170 | BMwork in patch work | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
9. | 23-02-2015 | 53+300/R.P.k vill-Devar | Foundation for R/wall | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
10. | 22-02-2015 | Devagan R.p.k. C7/53+300 | Excavation in foundation | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
11. | 22-02-2015 | Devarghat/53+100 | R/Wal in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
12. | 21-02-2015 | Dewar village 53+100 Rudraprayag-pokhari-karanprayag | R/Wall Masonary work Completed | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
13. | 15-02-2015 | Vill-Dewar,KM-53+100,RUDR-POKH-KARN Rd | RWall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
14. | 14-02-2015 | R.p.k/53+100 C-7 | RR masonary inprogress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
15. | 12-02-2015 | Devalghat/53+100R.P.K. C-7 | RR masonry in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
16. | 09-02-2015 | Vill-Dewar,KM-53+100,R-P-K | R/Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
17. | 08-02-2015 | Vill-Kunkuli,KM21+900,CHAMOLI-Kund Rd | Foundatoin of R/Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
18. | 08-02-2015 | Vill-Dewar,KM-53+100,Rudr-pokh-karn Rd | Retaining wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
19. | 07-02-2015 | Devar village 53+100 Rudraprayag-pokhari-karanprayag | R/Wall Masonary work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
20. | 22-01-2015 | Vill-Dewar,KM-53+100,Rudra-Pokh-Karn Rd | R/Wall in progress | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
|
|