Nandprayag- Ghat
Agreement signed
|
Project: |
UEAP-RB |
UID: |
5101 |
Sanction Cost: |
330.00 lakh |
Length:
|
14.000 KM. |
District: |
Chamoli |
Block: |
Ghat |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 1009
Package Name: 
UEAP/PWD/C7
Tender Date: 08-02-2014
Current Status: Agreement signed
Achieved on Date: 18-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C7
Contractor Name: Bharat Construction
|
Start Date: 08-08-2014
Intended Completion Date: 05-04-2016
Original End Date: 07-11-2015 |
Total Bond Cost: 34799370 (347.99 lakh)
Variation Cost: 8478614.26 (84.79 lakh) Hence Total Bond Cost is 43277984.26 (432.78 lakh)
|
Sub Project Cost: 211.00 lakh
Variation Cost of Sub Project: 8901873.00 (89.02 lakh)
Total Sub Project Cost:
300.02 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2644800 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 2470800 for 142 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.25 KM | 7.40 | 08-08-2014 | 08-10-2015 | 0.47 KM | 0.35 KM | 1.51 | 5.51 | 2. | R/Wall, B/ Wall Type Protection works | 607.00 m | 43.32 | 08-08-2014 | 08-08-2015 | 1210.00 m | 607.00 m | 5.95 | 21.73 | 3. | GSB/RBI/G-1 | 0.30 KM | 0.83 | 26-01-2015 | 26-05-2015 | 0.20 KM | 0.20 KM | 0.23 | 0.83 | 4. | G-2 | 0.43 KM | 0.99 | 10-02-2015 | 28-05-2015 | 0.59 KM | 0.43 KM | 0.2 | 0.72 | 5. | G-3 | 0.90 KM | 2.14 | 24-03-2015 | 31-05-2015 | 1.03 KM | 0.90 KM | 0.51 | 1.87 | 6. | BM i/c Prime Coat, Tack Coat | 4.70 KM | 134.74 | 15-05-2015 | 25-09-2015 | 1.50 KM | 1.50 KM | 36.89 | 134.74 | 7. | SDBC i/c Tackcoat | 9.10 KM | 110.57 | 20-05-2015 | 25-10-2015 | 6.58 KM | 6.58 KM | 30.27 | 110.57 | 8. | Cause Way | 7.00 No | 22.57 | 10-05-2015 | 25-03-2016 | 10.00 No | 7.00 No | 4.32 | 15.80 | 9. | Culverts/Scupper | 0.00 No | 0.00 | 15-05-2015 | 25-06-2015 | 0.00 No | 0.00 No | 0 | 0.00 | 10. | longitudinal Drain | 8648.00 m | 18.67 | 15-05-2015 | 20-06-2015 | 18500.00 m | 7850.00 m | 2.17 | 7.19 | 11. | Crash Barrier | 604.00 m | 20.54 | 20-05-2015 | 25-03-2016 | 600.00 m | 600.00 m | 5.62 | 20.54 | 12. | Parapet | 95.00 No | 2.28 | 18-05-2015 | 25-03-2016 | 190.00 No | 90.00 No | 0.3 | 1.02 | 13. | Road Furniture | 64.00 No | 1.24 | 25-05-2015 | 30-03-2016 | 209.00 No | 74.00 No | 0.12 | 0.44 |
Total Amount: |
365.29 |
|
88.08 |
320.96 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015 } ?>
Updation of work program on:
25-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-January-2015 | 12.81 lakh | 2. | 16-May-2015 | 8.92 lakh | 3. | 25-June-2015 | 37.15 lakh | 4. | 19-October-2015 | 62.23 lakh | 5. | 09-November-2015 | 67.43 lakh | 6. | 19-June-2016 | 181.71 lakh |
Total |
370.25 lakh |
% Payment | 123.41 % |
|
Advance Amount: 34.80 lakh
Recovered Amount: 34.80 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
labour licence, workmen Insurance
Environment & Social Compliances(Sub Project level):
No Pending Issue |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 2 No. of Test Done : 41 No. of Test Passed : 41 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 276 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-08-2016 | C7(Sera)ghat/13+960to14++080 | PRoad washout125mtr length | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
2. | 14-05-2016 | Bharat HMP / Chamoli | BM mix material production for Nandprayag -ghat road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
3. | 07-03-2016 | C7 Thirpak/6+700 | Public consultation by DrBhattachary Social ExpertDsc2 | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
4. | 07-03-2016 | C7(Ghat)/18+420 | CC Road in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
5. | 29-02-2016 | Ch. 18.275, Nandprayag Ghat motor road. | CC road under construction. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
6. | 16-02-2016 | C7 Ghat /18+410 | CC Road M15 Work in progress. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
7. | 16-02-2016 | N.p.that(Ganes nagar)/ch15+980 | Parapet work in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
8. | 06-02-2016 | C7(saintuli)N.P.that/17+110 | Parapet work in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
9. | 06-02-2016 | Km. 9, Nandprayag Ghat motor road. | Constructed parapit. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
10. | 27-01-2016 | C7 kameda (N.p.g)9+620 | Parapet work ln progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
11. | 15-01-2016 | C-7 N.P.G. Gwala/3+250 | Parapet work in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
12. | 15-01-2016 | C7 Tephna N.P.Chat/2+760 | Line drain ln progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
13. | 19-12-2015 | 10+050 | KC Drain in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
14. | 07-11-2015 | Km 5.200, Nandprayag Ghat motor road | Rolling of SDBC. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
15. | 03-11-2015 | Km 5.175, Nandprayag Ghat motor road. | Laying of SDBC. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
16. | 27-10-2015 | 5.900 | SDBC IN PROGRESS | Akhilesh Sharma | RE | DSC2 R&B ADB Chamoli | See Pic |
17. | 27-10-2015 | Km. 14.680, Nandprayag Ghat motor road. | Bended breast wall work completed. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
18. | 26-10-2015 | Gwala C7 N.P.ghat/3+875 | Reconstruction of damage R/wall | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
19. | 26-10-2015 | Gwala N.p.ghat C7/4+200 | Reconstruction of damage R/wall | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
20. | 26-10-2015 | C7 N.p.ghat/4+500 | Causeway kharanga work in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
|
|