Phoolchatti Jankichatti Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5016 |
Sanction Cost: |
856.00 lakh |
Length:
|
3.450 KM. |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Yamunotri |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 1082
Package Name: 
UEAP/PWD/C-78
Tender Date: 14-08-2015
Current Status: Agreement signed
Achieved on Date: 17-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-78
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 06-01-2016
Intended Completion Date: 05-04-2017
|
Total Bond Cost: 79104645 (791.05 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1898496 for 48 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.40 KM | 5.13 | 01-03-2016 | 03-08-2016 | 3.40 KM | 3.40 KM | 0.62 | 5.13 | 2. | R/Wall, B/ Wall Type Protection works | 550.00 m | 175.85 | 01-03-2016 | 31-12-2016 | 550.00 m | 550.00 m | 21.18 | 175.85 | 3. | G-2 | 3.45 KM | 17.82 | 11-03-2016 | 05-04-2017 | 3.45 KM | 3.45 KM | 2.15 | 17.82 | 4. | G-3 | 3.45 KM | 18.40 | 11-03-2016 | 05-04-2017 | 3.45 KM | 3.45 KM | 2.22 | 18.40 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.45 KM | 468.82 | 01-03-2016 | 10-04-2017 | 3.45 KM | 3.45 KM | 56.48 | 468.82 | 6. | longitudinal Drain | 2380.00 m | 33.73 | 01-03-2016 | 15-04-2017 | 2380.00 m | 2380.00 m | 4.06 | 33.73 | 7. | Parapet | 237.00 No | 8.50 | 01-03-2016 | 15-04-2017 | 237.00 No | 237.00 No | 1.03 | 8.50 | 8. | Road Furniture | 2096.00 No | 61.19 | 01-01-2017 | 15-04-2017 | 2096.00 No | 2096.00 No | 7.37 | 61.19 | 9. | Other Allied Works & Finishing Work | 2.00 Job | 40.67 | 21-01-2016 | 15-04-2017 | 2.00 Job | 2.00 Job | 4.9 | 40.67 |
Total Amount: |
830.11 |
|
100 |
830.11 |
|
Remarks:
work completed
Work Program Made On:
06-03-2016 } ?>
Updation of work program on:
25-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-April-2016 | 45.24 lakh | 2. | 04-June-2016 | 57.36 lakh | 3. | 01-August-2016 | 64.26 lakh | 4. | 15-September-2016 | 52.11 lakh | 5. | 04-October-2016 | 51.06 lakh | 6. | 26-October-2016 | 130.31 lakh | 7. | 28-November-2016 | 115.79 lakh | 8. | 22-December-2016 | 78.60 lakh | 9. | 10-January-2017 | 45.76 lakh | 10. | 28-February-2017 | 75.55 lakh | 11. | 06-April-2017 | 16.57 lakh | 12. | 16-May-2017 | 55.56 lakh | 13. | 27-June-2017 | 31.46 lakh |
Total |
819.63 lakh |
% Payment |
103.6 % |
|
Advance Amount: 99.70 lakh
Recovered Amount: 99.70 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 642 No. of Test Done : 642 No. of Test Passed : 642 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.17 |
Number of Notice(s) issued: 53 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 4 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-04-2016 | 1+07 | B/wall in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
2. | 07-04-2016 | 1+200 | B/wall in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
3. | 07-04-2016 | 2+850 | Excavation in B/wall | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
4. | 07-04-2016 | 0+00 | Starting point | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
|
|