Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Phoolchatti Jankichatti Motor Road Work Completed
Project: UEAP-RB UID: 5016 Sanction Cost: 856.00  lakh Length: 3.450 KM.
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 1082        Package Name:  UEAP/PWD/C-78        Tender Date: 14-08-2015        Current Status: Agreement signed        Achieved on Date: 17-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-78      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  06-01-2016      Intended Completion Date:  05-04-2017     
Total Bond Cost: 79104645 (791.05 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 1898496 for 48 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.40 KM5.1301-03-201603-08-20163.40 KM3.40 KM0.625.13
2.R/Wall, B/ Wall Type Protection works550.00 m175.8501-03-201631-12-2016550.00 m550.00 m21.18175.85
3.G-23.45 KM17.8211-03-201605-04-20173.45 KM3.45 KM2.1517.82
4.G-33.45 KM18.4011-03-201605-04-20173.45 KM3.45 KM2.2218.40
5.PC/CC i/c Prime Coat, Tack Coat3.45 KM468.8201-03-201610-04-20173.45 KM3.45 KM56.48468.82
6.longitudinal Drain2380.00 m33.7301-03-201615-04-20172380.00 m2380.00 m4.0633.73
7.Parapet237.00 No8.5001-03-201615-04-2017237.00 No237.00 No1.038.50
8.Road Furniture2096.00 No61.1901-01-201715-04-20172096.00 No2096.00 No7.3761.19
9.Other Allied Works & Finishing Work 2.00 Job40.6721-01-201615-04-20172.00 Job2.00 Job4.940.67
Total Amount: 830.11 100   830.11
Remarks: work completed       Work Program Made On: 06-03-2016        Updation of work program on: 25-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-April-201645.24  lakh
2.04-June-201657.36  lakh
3.01-August-201664.26  lakh
4.15-September-201652.11  lakh
5.04-October-201651.06  lakh
6.26-October-2016130.31  lakh
7.28-November-2016115.79  lakh
8.22-December-201678.60  lakh
9.10-January-201745.76  lakh
10.28-February-201775.55  lakh
11.06-April-201716.57  lakh
12.16-May-201755.56  lakh
13.27-June-201731.46  lakh
Total 819.63  lakh
% Payment 103.6 %
Advance Amount:  99.70  lakh        Recovered Amount:  99.70  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 642   No. of Test Done : 642    No. of Test Passed : 642   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.17
Number of Notice(s) issued: 53

Mobile Pic Upload

Number of Pics Available on Web Repository: 4
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-04-20161+07B/wall in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
2.07-04-20161+200B/wall in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
3.07-04-20162+850Excavation in B/wallBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
4.07-04-20160+00Starting pointBheem Singh MeharJEUEAP R&B Uttarkashi See Pic