Damta Kandari Motor Raod
Work Completed
|
Project: |
UEAP-RB |
UID: |
5013 |
Sanction Cost: |
100.00 lakh |
Length:
|
6.000 KM. |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1057
Package Name: 
UEAP/PWD/C54
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 25-05-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C54
Contractor Name: R K Gupta Contractor
|
Start Date: 15-06-2015
Intended Completion Date: 31-05-2017
Original End Date: 14-12-2016 |
Total Bond Cost: 61166275.95 (611.66 lakh)
Variation Cost: 7370825.78 (73.71 lakh) Hence Total Bond Cost is 68537101.73 (685.37 lakh)
|
Sub Project Cost: 101.65 lakh
Variation Cost of Sub Project: 1848803.53 (18.49 lakh)
Total Sub Project Cost:
120.14 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1682065 for 55 days
LD Analysis for Milestone2: calculated LD is Rs 672826 for 22 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.32 KM | 0.08 | 01-10-2015 | 24-12-2016 | 0.32 KM | 0.32 KM | 0.08 | 0.08 | 2. | R/Wall, B/ Wall Type Protection works | 565.00 m | 29.94 | 01-10-2015 | 25-10-2016 | 565.00 m | 565.00 m | 31.71 | 29.94 | 3. | Cause Way | 2.00 No | 3.15 | 01-10-2015 | 30-09-2016 | 2.00 No | 2.00 No | 3.34 | 3.15 | 4. | longitudinal Drain | 810.00 m | 34.79 | 01-10-2015 | 31-05-2017 | 806.00 m | 806.00 m | 36.85 | 34.79 | 5. | Crash Barrier | 100.00 m | 2.98 | 01-06-2016 | 17-12-2016 | 100.00 m | 100.00 m | 3.15 | 2.98 | 6. | Road Furniture | 631.00 No | 4.27 | 01-06-2016 | 31-05-2017 | 631.00 No | 631.00 No | 4.52 | 4.27 | 7. | Other Allied Works & Finishing Work | 2.00 Job | 19.22 | 15-06-2015 | 31-05-2017 | 2.00 Job | 2.00 Job | 20.36 | 19.22 |
Total Amount: |
94.43 |
|
100 |
94.43 |
|
Remarks:
Kuchha Drain (Km) = 2.00/2.00 No Bituminous Work in this Road
Work Program Made On:
14-10-2015 } ?>
Updation of work program on:
24-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-October-2015 | 22.41 lakh | 2. | 15-December-2015 | 6.00 lakh | 3. | 31-January-2016 | 8.41 lakh | 4. | 29-April-2016 | 3.37 lakh | 5. | 18-June-2016 | 5.53 lakh | 6. | 09-September-2016 | 24.81 lakh | 7. | 26-October-2016 | 1.93 lakh | 8. | 23-February-2017 | 6.62 lakh |
Total |
79.08 lakh |
% Payment | 65.82 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1570 No. of Test Done : 1571 No. of Test Passed : 1570 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.03 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 12 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-09-2016 | 9.600 | Parapet work done at c 48 | Pooja Garg | JE | UEAP R&B Almora | See Pic |
2. | 10-09-2016 | 9.800 | Parapet work done c48 jalikhan nobara | Pooja Garg | JE | UEAP R&B Almora | See Pic |
3. | 10-09-2016 | 10.050 | Parapet completed at c 48 jalikhan nobara | Pooja Garg | JE | UEAP R&B Almora | See Pic |
4. | 10-09-2016 | 10.200 | Parapet work done at package c 48 jalikhan nobara | Pooja Garg | JE | UEAP R&B Almora | See Pic |
5. | 10-09-2016 | 11.000 | PC work at c 48 | Pooja Garg | JE | UEAP R&B Almora | See Pic |
6. | 17-02-2016 | Ch 6.300 | Excavation for KC Drain | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
7. | 17-02-2016 | Ch 0.800 | KC drain complete | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
8. | 17-02-2016 | Chainage 18.350 | B C laying in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
9. | 29-08-2015 | Km 16.150 | Retaining Wall | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
10. | 29-08-2015 | Km 18.125 | Culvert | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
11. | 29-08-2015 | Km 21 | Slip cleaning | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
12. | 29-08-2015 | 18+125 | R/wall in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
|
|