Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Damta Kandari Motor Raod Work Completed
Project: UEAP-RB UID: 5013 Sanction Cost: 100.00  lakh Length: 6.000 KM.
District: Uttarkashi Block: Naugaon Constituency: Purola Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1057        Package Name:  UEAP/PWD/C54        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 25-05-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C54      Contractor Name: R K Gupta Contractor
Start Date:  15-06-2015      Intended Completion Date:  31-05-2017      Original End Date:  14-12-2016
Total Bond Cost: 61166275.95 (611.66 lakh)        Variation Cost: 7370825.78 (73.71 lakh)    Hence Total Bond Cost is   68537101.73 (685.37 lakh) 
Sub Project Cost: 101.65  lakh        Variation Cost of Sub Project: 1848803.53  (18.49 lakh)       Total Sub Project Cost:   120.14 lakh
LD Analysis for Milestone1: calculated LD is Rs 1682065 for 55 days        LD Analysis for Milestone2: calculated LD is Rs 672826 for 22 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.32 KM0.0801-10-201524-12-20160.32 KM0.32 KM0.080.08
2.R/Wall, B/ Wall Type Protection works565.00 m29.9401-10-201525-10-2016565.00 m565.00 m31.7129.94
3.Cause Way2.00 No3.1501-10-201530-09-20162.00 No2.00 No3.343.15
4.longitudinal Drain810.00 m34.7901-10-201531-05-2017806.00 m806.00 m36.8534.79
5.Crash Barrier100.00 m2.9801-06-201617-12-2016100.00 m100.00 m3.152.98
6.Road Furniture631.00 No4.2701-06-201631-05-2017631.00 No631.00 No4.524.27
7.Other Allied Works & Finishing Work 2.00 Job19.2215-06-201531-05-20172.00 Job2.00 Job20.3619.22
Total Amount: 94.43 100   94.43
Remarks: Kuchha Drain (Km) = 2.00/2.00 No Bituminous Work in this Road       Work Program Made On: 14-10-2015        Updation of work program on: 24-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201522.41  lakh
2.15-December-20156.00  lakh
3.31-January-20168.41  lakh
4.29-April-20163.37  lakh
5.18-June-20165.53  lakh
6.09-September-201624.81  lakh
7.26-October-20161.93  lakh
8.23-February-20176.62  lakh
Total 79.08  lakh
% Payment65.82 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1570   No. of Test Done : 1571    No. of Test Passed : 1570   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.03
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 12
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-09-20169.600Parapet work done at c 48Pooja GargJEUEAP R&B Almora See Pic
2.10-09-20169.800Parapet work done c48 jalikhan nobaraPooja GargJEUEAP R&B Almora See Pic
3.10-09-201610.050Parapet completed at c 48 jalikhan nobaraPooja GargJEUEAP R&B Almora See Pic
4.10-09-201610.200Parapet work done at package c 48 jalikhan nobaraPooja GargJEUEAP R&B Almora See Pic
5.10-09-201611.000PC work at c 48Pooja GargJEUEAP R&B Almora See Pic
6.17-02-2016Ch 6.300Excavation for KC DrainChetan BhattJEUEAP R&B Almora See Pic
7.17-02-2016Ch 0.800KC drain completeChetan BhattJEUEAP R&B Almora See Pic
8.17-02-2016Chainage 18.350B C laying in progressChetan BhattJEUEAP R&B Almora See Pic
9.29-08-2015Km 16.150Retaining WallAshutosh KumarEEDEA ADB Uttarkashi See Pic
10.29-08-2015Km 18.125CulvertAshutosh KumarEEDEA ADB Uttarkashi See Pic
11.29-08-2015Km 21Slip cleaningAshutosh KumarEEDEA ADB Uttarkashi See Pic
12.29-08-201518+125R/wall in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic