Naogaon Paunti Rajgadi Motor Road Work Completed
Project: UEAP-RB UID: 5012 Sanction Cost: 625.00  lakh Length: 24.000 KM.
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1057        Package Name:  UEAP/PWD/C54        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 25-05-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C54      Contractor Name: R K Gupta Contractor
Start Date:  15-06-2015      Intended Completion Date:  31-05-2017      Original End Date:  14-12-2016
Total Bond Cost: 61166275.95 (611.66 lakh)        Variation Cost: 7370825.78 (73.71 lakh)    Hence Total Bond Cost is   68537101.73 (685.37 lakh) 
Sub Project Cost: 583.72  lakh        Variation Cost of Sub Project: 5522022.25  (55.22 lakh)       Total Sub Project Cost:   638.94 lakh
LD Analysis for Milestone1: calculated LD is Rs 1682065 for 55 days        LD Analysis for Milestone2: calculated LD is Rs 672826 for 22 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence12.00 KM0.5501-10-201531-05-201712.00 KM12.00 KM0.090.55
2.R/Wall, B/ Wall Type Protection works785.00 m127.1801-10-201531-05-2017785.00 m785.00 m21.12127.18
3.G-21.00 KM15.7515-01-201631-08-20161.00 KM1.00 KM2.6215.75
4.G-31.00 KM7.9815-01-201631-08-20161.00 KM1.00 KM1.337.98
5.BM i/c Prime Coat, Tack Coat4.00 KM83.8401-03-201631-05-20174.00 KM4.00 KM13.9283.84
6.SDBC i/c Tackcoat4.00 KM64.6910-03-201631-05-20174.00 KM4.00 KM10.7464.69
7.Cause Way13.00 No61.6601-10-201531-05-201713.00 No13.00 No10.2461.66
8.Culverts/Scupper 4.00 No34.7001-10-201514-11-20164.00 No4.00 No5.7634.70
9.longitudinal Drain9610.00 m124.7215-10-201530-04-20179610.00 m9610.00 m20.71124.72
10.Crash Barrier350.00 m10.4101-06-201617-12-2016350.00 m350.00 m1.7310.41
11.Parapet115.00 No11.9001-06-201614-11-2016115.00 No115.00 No1.9811.90
12.Road Furniture2521.00 No19.6101-06-201631-05-20172521.00 No2521.00 No3.2619.61
13.Other Allied Works & Finishing Work 1.00 Job39.1715-06-201631-05-20171.00 Job1.00 Job6.5139.17
Total Amount: 602.16 100   602.16
Remarks: Kuchha Drain (Km) = 6.00/6.00       Work Program Made On: 14-10-2015        Updation of work program on: 24-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201518.31  lakh
2.15-December-201540.29  lakh
3.31-January-201628.41  lakh
4.29-February-201633.62  lakh
5.31-March-201649.89  lakh
6.29-April-201615.16  lakh
7.28-May-201652.83  lakh
8.18-June-201624.13  lakh
9.09-September-201662.11  lakh
10.26-October-201618.49  lakh
11.23-February-201735.97  lakh
12.06-April-201717.74  lakh
13.27-June-201747.31  lakh
Total 444.26  lakh
% Payment69.53 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1570   No. of Test Done : 1571    No. of Test Passed : 1570   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.03
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 13
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.26-01-201619+900R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
2.26-01-201618+100R/wall with plum in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
3.26-01-201618.00R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
4.21-12-20150+700Drain work in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
5.21-12-20150+890CausewayBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
6.21-12-20150+900R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
7.21-12-20150+850R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
8.07-11-20150.800Runing r/wallAjeet SinghAEUEAP R&B Uttarkashi See Pic
9.04-11-201594.020Bm laying in progressAjeet SinghAEUEAP R&B Uttarkashi See Pic
10.04-11-201594.060Cleaning surface before b.m.Ajeet SinghAEUEAP R&B Uttarkashi See Pic
11.14-09-20153+00Construction of causewayBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
12.14-09-20150+175R/wall in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
13.29-08-2015Km 19Slip boulder clearanceAshutosh KumarEEDEA ADB Uttarkashi See Pic