Naogaon Paunti Rajgadi Motor Road
Work Completed
|
Project: |
UEAP-RB |
UID: |
5012 |
Sanction Cost: |
625.00 lakh |
Length:
|
24.000 KM. |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Yamunotri |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1057
Package Name: 
UEAP/PWD/C54
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 25-05-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C54
Contractor Name: R K Gupta Contractor
|
Start Date: 15-06-2015
Intended Completion Date: 31-05-2017
Original End Date: 14-12-2016 |
Total Bond Cost: 61166275.95 (611.66 lakh)
Variation Cost: 7370825.78 (73.71 lakh) Hence Total Bond Cost is 68537101.73 (685.37 lakh)
|
Sub Project Cost: 583.72 lakh
Variation Cost of Sub Project: 5522022.25 (55.22 lakh)
Total Sub Project Cost:
638.94 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 1682065 for 55 days
LD Analysis for Milestone2: calculated LD is Rs 672826 for 22 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 12.00 KM | 0.55 | 01-10-2015 | 31-05-2017 | 12.00 KM | 12.00 KM | 0.09 | 0.55 | 2. | R/Wall, B/ Wall Type Protection works | 785.00 m | 127.18 | 01-10-2015 | 31-05-2017 | 785.00 m | 785.00 m | 21.12 | 127.18 | 3. | G-2 | 1.00 KM | 15.75 | 15-01-2016 | 31-08-2016 | 1.00 KM | 1.00 KM | 2.62 | 15.75 | 4. | G-3 | 1.00 KM | 7.98 | 15-01-2016 | 31-08-2016 | 1.00 KM | 1.00 KM | 1.33 | 7.98 | 5. | BM i/c Prime Coat, Tack Coat | 4.00 KM | 83.84 | 01-03-2016 | 31-05-2017 | 4.00 KM | 4.00 KM | 13.92 | 83.84 | 6. | SDBC i/c Tackcoat | 4.00 KM | 64.69 | 10-03-2016 | 31-05-2017 | 4.00 KM | 4.00 KM | 10.74 | 64.69 | 7. | Cause Way | 13.00 No | 61.66 | 01-10-2015 | 31-05-2017 | 13.00 No | 13.00 No | 10.24 | 61.66 | 8. | Culverts/Scupper | 4.00 No | 34.70 | 01-10-2015 | 14-11-2016 | 4.00 No | 4.00 No | 5.76 | 34.70 | 9. | longitudinal Drain | 9610.00 m | 124.72 | 15-10-2015 | 30-04-2017 | 9610.00 m | 9610.00 m | 20.71 | 124.72 | 10. | Crash Barrier | 350.00 m | 10.41 | 01-06-2016 | 17-12-2016 | 350.00 m | 350.00 m | 1.73 | 10.41 | 11. | Parapet | 115.00 No | 11.90 | 01-06-2016 | 14-11-2016 | 115.00 No | 115.00 No | 1.98 | 11.90 | 12. | Road Furniture | 2521.00 No | 19.61 | 01-06-2016 | 31-05-2017 | 2521.00 No | 2521.00 No | 3.26 | 19.61 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 39.17 | 15-06-2016 | 31-05-2017 | 1.00 Job | 1.00 Job | 6.51 | 39.17 |
Total Amount: |
602.16 |
|
100 |
602.16 |
|
Remarks:
Kuchha Drain (Km) = 6.00/6.00
Work Program Made On:
14-10-2015 } ?>
Updation of work program on:
24-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-October-2015 | 18.31 lakh | 2. | 15-December-2015 | 40.29 lakh | 3. | 31-January-2016 | 28.41 lakh | 4. | 29-February-2016 | 33.62 lakh | 5. | 31-March-2016 | 49.89 lakh | 6. | 29-April-2016 | 15.16 lakh | 7. | 28-May-2016 | 52.83 lakh | 8. | 18-June-2016 | 24.13 lakh | 9. | 09-September-2016 | 62.11 lakh | 10. | 26-October-2016 | 18.49 lakh | 11. | 23-February-2017 | 35.97 lakh | 12. | 06-April-2017 | 17.74 lakh | 13. | 27-June-2017 | 47.31 lakh |
Total |
444.26 lakh |
% Payment | 69.53 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1570 No. of Test Done : 1571 No. of Test Passed : 1570 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.03 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 13 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 26-01-2016 | 19+900 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
2. | 26-01-2016 | 18+100 | R/wall with plum in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
3. | 26-01-2016 | 18.00 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
4. | 21-12-2015 | 0+700 | Drain work in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
5. | 21-12-2015 | 0+890 | Causeway | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
6. | 21-12-2015 | 0+900 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
7. | 21-12-2015 | 0+850 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
8. | 07-11-2015 | 0.800 | Runing r/wall | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
9. | 04-11-2015 | 94.020 | Bm laying in progress | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
10. | 04-11-2015 | 94.060 | Cleaning surface before b.m. | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
11. | 14-09-2015 | 3+00 | Construction of causeway | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
12. | 14-09-2015 | 0+175 | R/wall in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
13. | 29-08-2015 | Km 19 | Slip boulder clearance | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
|
|