Badethi Banchora Badrigarh Motor Road (Included Tehri Part) Work Completed
Project: UEAP-RB UID: 5011 Sanction Cost: 1700.00  lakh Length: 29.000 KM.
District: Uttarkashi Block: Chinyalisaur Constituency: Yamunotri Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1056        Package Name:  UEAP/PWD/C53        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 16-03-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C53      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  06-04-2015      Intended Completion Date:  31-01-2017      Original End Date:  05-10-2016
Total Bond Cost: 148799811.3 (1488 lakh)        Variation Cost: 18064613.72 (180.65 lakh)    Hence Total Bond Cost is   166864425.02 (1668.64 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1785600 for 24 days        LD Analysis for Milestone2: calculated LD is Rs 5431200 for 73 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.25 KM3.2801-06-201531-01-20171.25 KM1.25 KM0.243.28
2.R/Wall, B/ Wall Type Protection works3368.00 m326.7606-04-201530-09-20163368.00 m3368.00 m23.49326.76
3.GSB/RBI/G-10.60 KM6.8901-06-201520-12-20160.60 KM0.60 KM0.56.89
4.G-22.50 KM16.9001-06-201520-12-20162.50 KM2.50 KM1.2216.90
5.G-32.50 KM17.2810-06-201520-12-20162.50 KM2.50 KM1.2417.28
6.BM i/c Prime Coat, Tack Coat9.77 KM208.1326-06-201525-12-20169.77 KM9.77 KM14.96208.13
7.SDBC i/c Tackcoat29.00 KM408.9201-09-201526-12-201629.00 KM29.00 KM29.4408.92
8.Cause Way8.00 No24.9701-06-201531-01-20178.00 No8.00 No1.824.97
9.Culverts/Scupper 5.00 No45.8201-06-201530-09-20165.00 No5.00 No3.2945.82
10.longitudinal Drain7000.00 m222.8201-06-201531-01-20177000.00 m7000.00 m16.02222.82
11.Crash Barrier300.00 m9.3001-04-201631-01-2017300.00 m300.00 m0.679.30
12.Parapet500.00 No62.4201-04-201631-01-2017500.00 No500.00 No4.4962.42
13.Road Furniture1812.00 No23.5201-04-201631-01-20171812.00 No1812.00 No1.6923.52
14.Other Allied Works & Finishing Work 4.00 Job13.8406-04-201531-01-20174.00 Job4.00 Job113.84
Total Amount: 1390.85 100   1390.85
Remarks: EOT Applied       Work Program Made On: 31-05-2015        Updation of work program on: 17-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.03-June-201547.53  lakh
2.26-June-201521.17  lakh
3.21-August-201545.75  lakh
4.03-October-201587.72  lakh
5.23-October-201565.25  lakh
6.09-November-201569.16  lakh
7.08-January-2016117.25  lakh
8.10-February-201677.11  lakh
9.25-March-201650.15  lakh
10.12-May-201655.85  lakh
11.21-June-2016120.23  lakh
12.03-August-2016277.54  lakh
13.01-October-201621.47  lakh
14.28-October-201631.93  lakh
15.23-December-2016116.42  lakh
16.15-June-2017119.99  lakh
Total 1324.52  lakh
% Payment 79.39 %
Advance Amount:  198.00  lakh        Recovered Amount:  198.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 872   No. of Test Done : 888    No. of Test Passed : 887   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.64
Number of Notice(s) issued: 74

Mobile Pic Upload

Number of Pics Available on Web Repository: 79
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-06-2016Ch-3+460B.M laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
2.29-06-2016Ch-5+480B.c laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
3.06-06-2016Ch-9+960B.C Laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
4.06-06-2016Ch-10+220B.M laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
5.31-05-2016Ch+69+210B.m work in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
6.12-04-2016Ch-78+060R/wall in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
7.04-04-2016Ch-1+940Drain work in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
8.29-12-201572+800Drain work in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
9.29-12-201574+830R/wall, B/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
10.29-12-201577+200Completed drain workBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
11.02-11-201513.040B.c laying in progressAjeet SinghAEUEAP R&B Uttarkashi See Pic
12.30-10-201571.250Bc layingAjeet SinghAEUEAP R&B Uttarkashi See Pic
13.30-10-201571.400Bc thickness checkingAjeet SinghAEUEAP R&B Uttarkashi See Pic
14.30-10-201571.220Bc layingAjeet SinghAEUEAP R&B Uttarkashi See Pic
15.25-09-2015Km 95BC layingAshutosh KumarEEDEA ADB Uttarkashi See Pic
16.25-09-2015Km 2.15Retaining WallAshutosh KumarEEDEA ADB Uttarkashi See Pic
17.25-09-2015Km 1.14Sinking zoneAshutosh KumarEEDEA ADB Uttarkashi See Pic
18.25-09-2015Km 0.94Sinking zoneAshutosh KumarEEDEA ADB Uttarkashi See Pic
19.25-09-2015Km 0.74Sinking zoneAshutosh KumarEEDEA ADB Uttarkashi See Pic
20.22-09-20150+740SE sir visitBheem Singh MeharJEUEAP R&B Uttarkashi See Pic