Badethi Banchora Badrigarh Motor Road (Included Tehri Part)
Work Completed
|
Project: |
UEAP-RB |
UID: |
5011 |
Sanction Cost: |
1700.00 lakh |
Length:
|
29.000 KM. |
District: |
Uttarkashi |
Block: |
Chinyalisaur |
Constituency: |
Yamunotri |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1056
Package Name: 
UEAP/PWD/C53
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 16-03-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C53
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 06-04-2015
Intended Completion Date: 31-01-2017
Original End Date: 05-10-2016 |
Total Bond Cost: 148799811.3 (1488 lakh)
Variation Cost: 18064613.72 (180.65 lakh) Hence Total Bond Cost is 166864425.02 (1668.64 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1785600 for 24 days
LD Analysis for Milestone2: calculated LD is Rs 5431200 for 73 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.25 KM | 3.28 | 01-06-2015 | 31-01-2017 | 1.25 KM | 1.25 KM | 0.24 | 3.28 | 2. | R/Wall, B/ Wall Type Protection works | 3368.00 m | 326.76 | 06-04-2015 | 30-09-2016 | 3368.00 m | 3368.00 m | 23.49 | 326.76 | 3. | GSB/RBI/G-1 | 0.60 KM | 6.89 | 01-06-2015 | 20-12-2016 | 0.60 KM | 0.60 KM | 0.5 | 6.89 | 4. | G-2 | 2.50 KM | 16.90 | 01-06-2015 | 20-12-2016 | 2.50 KM | 2.50 KM | 1.22 | 16.90 | 5. | G-3 | 2.50 KM | 17.28 | 10-06-2015 | 20-12-2016 | 2.50 KM | 2.50 KM | 1.24 | 17.28 | 6. | BM i/c Prime Coat, Tack Coat | 9.77 KM | 208.13 | 26-06-2015 | 25-12-2016 | 9.77 KM | 9.77 KM | 14.96 | 208.13 | 7. | SDBC i/c Tackcoat | 29.00 KM | 408.92 | 01-09-2015 | 26-12-2016 | 29.00 KM | 29.00 KM | 29.4 | 408.92 | 8. | Cause Way | 8.00 No | 24.97 | 01-06-2015 | 31-01-2017 | 8.00 No | 8.00 No | 1.8 | 24.97 | 9. | Culverts/Scupper | 5.00 No | 45.82 | 01-06-2015 | 30-09-2016 | 5.00 No | 5.00 No | 3.29 | 45.82 | 10. | longitudinal Drain | 7000.00 m | 222.82 | 01-06-2015 | 31-01-2017 | 7000.00 m | 7000.00 m | 16.02 | 222.82 | 11. | Crash Barrier | 300.00 m | 9.30 | 01-04-2016 | 31-01-2017 | 300.00 m | 300.00 m | 0.67 | 9.30 | 12. | Parapet | 500.00 No | 62.42 | 01-04-2016 | 31-01-2017 | 500.00 No | 500.00 No | 4.49 | 62.42 | 13. | Road Furniture | 1812.00 No | 23.52 | 01-04-2016 | 31-01-2017 | 1812.00 No | 1812.00 No | 1.69 | 23.52 | 14. | Other Allied Works & Finishing Work | 4.00 Job | 13.84 | 06-04-2015 | 31-01-2017 | 4.00 Job | 4.00 Job | 1 | 13.84 |
Total Amount: |
1390.85 |
|
100 |
1390.85 |
|
Remarks:
EOT Applied
Work Program Made On:
31-05-2015 } ?>
Updation of work program on:
17-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 03-June-2015 | 47.53 lakh | 2. | 26-June-2015 | 21.17 lakh | 3. | 21-August-2015 | 45.75 lakh | 4. | 03-October-2015 | 87.72 lakh | 5. | 23-October-2015 | 65.25 lakh | 6. | 09-November-2015 | 69.16 lakh | 7. | 08-January-2016 | 117.25 lakh | 8. | 10-February-2016 | 77.11 lakh | 9. | 25-March-2016 | 50.15 lakh | 10. | 12-May-2016 | 55.85 lakh | 11. | 21-June-2016 | 120.23 lakh | 12. | 03-August-2016 | 277.54 lakh | 13. | 01-October-2016 | 21.47 lakh | 14. | 28-October-2016 | 31.93 lakh | 15. | 23-December-2016 | 116.42 lakh | 16. | 15-June-2017 | 119.99 lakh |
Total |
1324.52 lakh |
% Payment |
79.39 % |
|
Advance Amount: 198.00 lakh
Recovered Amount: 198.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 872 No. of Test Done : 888 No. of Test Passed : 887 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.64 |
Number of Notice(s) issued: 74 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 79 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-06-2016 | Ch-3+460 | B.M laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
2. | 29-06-2016 | Ch-5+480 | B.c laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
3. | 06-06-2016 | Ch-9+960 | B.C Laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
4. | 06-06-2016 | Ch-10+220 | B.M laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
5. | 31-05-2016 | Ch+69+210 | B.m work in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
6. | 12-04-2016 | Ch-78+060 | R/wall in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
7. | 04-04-2016 | Ch-1+940 | Drain work in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
8. | 29-12-2015 | 72+800 | Drain work in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
9. | 29-12-2015 | 74+830 | R/wall, B/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
10. | 29-12-2015 | 77+200 | Completed drain work | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
11. | 02-11-2015 | 13.040 | B.c laying in progress | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
12. | 30-10-2015 | 71.250 | Bc laying | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
13. | 30-10-2015 | 71.400 | Bc thickness checking | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
14. | 30-10-2015 | 71.220 | Bc laying | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
15. | 25-09-2015 | Km 95 | BC laying | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
16. | 25-09-2015 | Km 2.15 | Retaining Wall | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
17. | 25-09-2015 | Km 1.14 | Sinking zone | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
18. | 25-09-2015 | Km 0.94 | Sinking zone | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
19. | 25-09-2015 | Km 0.74 | Sinking zone | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
20. | 22-09-2015 | 0+740 | SE sir visit | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
|
|