Silkyara Bangaon-Chapda saroth Motor Raod
Work Completed
|
Project: |
UEAP-RB |
UID: |
5010 |
Sanction Cost: |
1480.00 lakh |
Length:
|
38.000 KM. |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Yamunotri |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1055
Package Name: 
UEAP/PWD/C52
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 12-01-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C52
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 03-02-2015
Intended Completion Date: 23-10-2016
Original End Date: 11-07-2016 |
Total Bond Cost: 121422697.9 (1214.23 lakh)
Variation Cost: 17948286.80 (179.48 lakh) Hence Total Bond Cost is 139370984.7 (1393.71 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 2914128 for 48 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.47 KM | 5.67 | 15-03-2015 | 31-05-2015 | 1.47 KM | 1.47 KM | 0.43 | 5.67 | 2. | R/Wall, B/ Wall Type Protection works | 2660.00 m | 369.88 | 15-03-2015 | 06-09-2016 | 2660.00 m | 2660.00 m | 28.12 | 369.88 | 3. | G-2 | 1.87 KM | 21.18 | 25-05-2015 | 30-08-2016 | 1.87 KM | 1.87 KM | 1.61 | 21.18 | 4. | G-3 | 1.87 KM | 21.64 | 25-05-2015 | 30-08-2016 | 1.87 KM | 1.87 KM | 1.65 | 21.64 | 5. | BM i/c Prime Coat, Tack Coat | 14.02 KM | 180.74 | 05-06-2015 | 30-08-2016 | 14.02 KM | 14.02 KM | 13.74 | 180.74 | 6. | SDBC i/c Tackcoat | 22.77 KM | 137.25 | 01-11-2015 | 30-08-2016 | 22.77 KM | 22.77 KM | 10.43 | 137.25 | 7. | Cause Way | 16.00 No | 48.50 | 01-06-2015 | 15-07-2016 | 16.00 No | 16.00 No | 3.69 | 48.50 | 8. | Culverts/Scupper | 6.00 No | 22.79 | 01-06-2015 | 30-08-2016 | 6.00 No | 6.00 No | 1.73 | 22.79 | 9. | longitudinal Drain | 7725.00 m | 277.54 | 15-05-2015 | 20-04-2016 | 7725.00 m | 7725.00 m | 21.1 | 277.54 | 10. | Crash Barrier | 850.00 m | 25.50 | 01-01-2016 | 23-10-2016 | 850.00 m | 850.00 m | 1.94 | 25.50 | 11. | Parapet | 529.00 No | 25.11 | 01-10-2015 | 30-08-2016 | 529.00 No | 529.00 No | 1.91 | 25.11 | 12. | Road Furniture | 4696.00 No | 54.41 | 20-03-2016 | 23-10-2016 | 4696.00 No | 4696.00 No | 4.14 | 54.41 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 125.30 | 03-02-2015 | 23-10-2016 | 2.00 Job | 2.00 Job | 9.53 | 125.30 |
Total Amount: |
1315.51 |
|
100 |
1315.51 |
|
Remarks:
Bituminous work completed Kuchha Drain (Km)= 25.00/25.00
Work Program Made On:
31-05-2015 } ?>
Updation of work program on:
17-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-June-2015 | 45.78 lakh | 2. | 26-June-2015 | 32.58 lakh | 3. | 07-September-2015 | 144.92 lakh | 4. | 03-October-2015 | 69.50 lakh | 5. | 23-October-2015 | 95.12 lakh | 6. | 09-November-2015 | 122.64 lakh | 7. | 08-January-2016 | 163.66 lakh | 8. | 10-February-2016 | 19.67 lakh | 9. | 25-February-2016 | 41.69 lakh | 10. | 25-March-2016 | 26.92 lakh | 11. | 12-May-2016 | 216.87 lakh | 12. | 21-June-2016 | 153.86 lakh | 13. | 03-August-2016 | 30.46 lakh | 14. | 01-October-2016 | 52.33 lakh | 15. | 28-October-2016 | 17.18 lakh | 16. | 15-June-2017 | 48.40 lakh |
Total |
1281.58 lakh |
% Payment |
91.94 % |
|
Advance Amount: 121.00 lakh
Recovered Amount: 121.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 887 No. of Test Done : 938 No. of Test Passed : 937 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.89 |
Number of Notice(s) issued: 74 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 77 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-05-2016 | Ch-96+160 | Slab casting (1m span culvert ) in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
2. | 08-05-2016 | Ch-5+760 | B.C work in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
3. | 08-05-2016 | Ch-3+045 | B.C work in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
4. | 08-05-2016 | Ch- 4+320 | R/wall in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
5. | 08-05-2016 | Ch-5+755 | B.M laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
6. | 01-05-2016 | Ch-7+900 | B.C Laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
7. | 10-04-2016 | Ch-90+980 | Parapet work in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
8. | 08-04-2016 | Ch-15+430 | B.C laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
9. | 07-04-2016 | Ch-15+945 | B.C laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
10. | 07-04-2016 | Ch-16+220 | B.C laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
11. | 04-04-2016 | Ch-16+620 | B.C laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
12. | 04-04-2016 | Ch-16+880 | B.C laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
13. | 04-04-2016 | Ch-9+730 | B.C laying in progress | Deepak Bahuguna | JE | UEAP R&B Uttarkashi | See Pic |
14. | 04-04-2016 | Km 10 | BC Work in Progress | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
15. | 03-04-2016 | Km 10 | BC WORK IN PROGRESS | Ashutosh Kumar | EE | DEA ADB Uttarkashi | See Pic |
16. | 31-10-2015 | 92.640 | Bm thickness checking | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
17. | 31-10-2015 | 92.830 | Bm laying in progress | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
18. | 29-10-2015 | 98.220 | Bm.thickness Checking | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
19. | 29-10-2015 | 92.300 | B.m.laying in progress | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
20. | 18-09-2015 | 16.310 | S.E. Sir visit in c52 | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
|
|