Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Silkyara Bangaon-Chapda saroth Motor Raod Work Completed
Project: UEAP-RB UID: 5010 Sanction Cost: 1480.00  lakh Length: 38.000 KM.
District: Uttarkashi Block: Dunda Constituency: Yamunotri Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: MDR
Procurement:
Package No.: 1055        Package Name:  UEAP/PWD/C52        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 12-01-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C52      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  03-02-2015      Intended Completion Date:  23-10-2016      Original End Date:  11-07-2016
Total Bond Cost: 121422697.9 (1214.23 lakh)        Variation Cost: 17948286.80 (179.48 lakh)    Hence Total Bond Cost is   139370984.7 (1393.71 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 2914128 for 48 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.47 KM5.6715-03-201531-05-20151.47 KM1.47 KM0.435.67
2.R/Wall, B/ Wall Type Protection works2660.00 m369.8815-03-201506-09-20162660.00 m2660.00 m28.12369.88
3.G-21.87 KM21.1825-05-201530-08-20161.87 KM1.87 KM1.6121.18
4.G-31.87 KM21.6425-05-201530-08-20161.87 KM1.87 KM1.6521.64
5.BM i/c Prime Coat, Tack Coat14.02 KM180.7405-06-201530-08-201614.02 KM14.02 KM13.74180.74
6.SDBC i/c Tackcoat22.77 KM137.2501-11-201530-08-201622.77 KM22.77 KM10.43137.25
7.Cause Way16.00 No48.5001-06-201515-07-201616.00 No16.00 No3.6948.50
8.Culverts/Scupper 6.00 No22.7901-06-201530-08-20166.00 No6.00 No1.7322.79
9.longitudinal Drain7725.00 m277.5415-05-201520-04-20167725.00 m7725.00 m21.1277.54
10.Crash Barrier850.00 m25.5001-01-201623-10-2016850.00 m850.00 m1.9425.50
11.Parapet529.00 No25.1101-10-201530-08-2016529.00 No529.00 No1.9125.11
12.Road Furniture4696.00 No54.4120-03-201623-10-20164696.00 No4696.00 No4.1454.41
13.Other Allied Works & Finishing Work 2.00 Job125.3003-02-201523-10-20162.00 Job2.00 Job9.53125.30
Total Amount: 1315.51 100   1315.51
Remarks: Bituminous work completed Kuchha Drain (Km)= 25.00/25.00        Work Program Made On: 31-05-2015        Updation of work program on: 17-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-June-201545.78  lakh
2.26-June-201532.58  lakh
3.07-September-2015144.92  lakh
4.03-October-201569.50  lakh
5.23-October-201595.12  lakh
6.09-November-2015122.64  lakh
7.08-January-2016163.66  lakh
8.10-February-201619.67  lakh
9.25-February-201641.69  lakh
10.25-March-201626.92  lakh
11.12-May-2016216.87  lakh
12.21-June-2016153.86  lakh
13.03-August-201630.46  lakh
14.01-October-201652.33  lakh
15.28-October-201617.18  lakh
16.15-June-201748.40  lakh
Total 1281.58  lakh
% Payment 91.94 %
Advance Amount:  121.00  lakh        Recovered Amount:  121.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 887   No. of Test Done : 938    No. of Test Passed : 937   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.89
Number of Notice(s) issued: 74

Mobile Pic Upload

Number of Pics Available on Web Repository: 77
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-05-2016Ch-96+160Slab casting (1m span culvert ) in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
2.08-05-2016Ch-5+760B.C work in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
3.08-05-2016Ch-3+045B.C work in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
4.08-05-2016Ch- 4+320R/wall in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
5.08-05-2016Ch-5+755B.M laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
6.01-05-2016Ch-7+900B.C Laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
7.10-04-2016Ch-90+980Parapet work in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
8.08-04-2016Ch-15+430B.C laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
9.07-04-2016Ch-15+945B.C laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
10.07-04-2016Ch-16+220B.C laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
11.04-04-2016Ch-16+620B.C laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
12.04-04-2016Ch-16+880B.C laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
13.04-04-2016Ch-9+730B.C laying in progressDeepak BahugunaJEUEAP R&B Uttarkashi See Pic
14.04-04-2016Km 10BC Work in ProgressAshutosh KumarEEDEA ADB Uttarkashi See Pic
15.03-04-2016Km 10BC WORK IN PROGRESSAshutosh KumarEEDEA ADB Uttarkashi See Pic
16.31-10-201592.640Bm thickness checkingAjeet SinghAEUEAP R&B Uttarkashi See Pic
17.31-10-201592.830Bm laying in progressAjeet SinghAEUEAP R&B Uttarkashi See Pic
18.29-10-201598.220Bm.thickness CheckingAjeet SinghAEUEAP R&B Uttarkashi See Pic
19.29-10-201592.300B.m.laying in progressAjeet SinghAEUEAP R&B Uttarkashi See Pic
20.18-09-201516.310S.E. Sir visit in c52Ajeet SinghAEUEAP R&B Uttarkashi See Pic