Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Tyuni-Mori-Purola-Naugaon Work Completed
Project: UEAP-RB UID: 5003 Sanction Cost: 845.00  lakh Length: 32.000 KM.
District: Uttarkashi Block: Puraula Constituency: Purola Circle:
DEA: DEA UEAP Uttarkashi DSC: Royal Haskoning DHV DSC Scope: Design & Supervision Type: MDR
Procurement:
Package No.: 1040        Package Name:  UEAP/PWD/C37        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 16-03-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C37      Contractor Name: SS Infratech
Start Date:  06-04-2015      Intended Completion Date:  26-05-2017      Original End Date:  05-10-2016
Total Bond Cost: 83662453.21 (836.62 lakh)        Variation Cost: 602840.20 (6.03 lakh)    Hence Total Bond Cost is   84265293.41 (842.65 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 7613242 for +182 days        LD Analysis for Milestone2: calculated LD is Rs 8826341 for 211 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.45 KM0.9915-05-201520-12-20160.45 KM0.45 KM0.120.99
2.R/Wall, B/ Wall Type Protection works600.00 m55.0208-04-201505-03-2017600.00 m600.00 m6.5355.02
3.GSB/RBI/G-10.13 KM0.4720-09-201530-09-20160.13 KM0.13 KM0.060.47
4.G-20.75 KM0.8025-09-201530-09-20160.75 KM0.75 KM0.10.80
5.G-30.75 KM0.6428-09-201530-09-20160.75 KM0.75 KM0.080.64
6.BM i/c Prime Coat, Tack Coat1.50 KM2.8226-10-201526-05-20171.50 KM1.50 KM0.332.82
7.SDBC i/c Tackcoat32.00 KM474.8801-11-201526-05-201732.00 KM32.00 KM56.37474.88
8.longitudinal Drain3250.00 m33.1501-07-201526-05-20173250.00 m3250.00 m3.9433.15
9.Crash Barrier500.00 m13.1915-11-201526-05-2017500.00 m500.00 m1.5713.19
10.Parapet1250.00 No163.8410-04-201530-08-20161250.00 No1250.00 No19.45163.84
11.Road Furniture4020.00 No74.3015-01-201626-05-20174020.00 No4020.00 No8.8274.30
12.Other Allied Works & Finishing Work 1.00 Job22.4106-04-201526-05-20171.00 Job1.00 Job2.6622.41
Total Amount: 842.51 100   842.51
Remarks: EOT Applied       Work Program Made On: 13-06-2015        Updation of work program on: 25-07-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-June-201524.55  lakh
2.28-October-201523.10  lakh
3.30-November-201536.65  lakh
4.22-January-201612.03  lakh
5.31-March-201619.23  lakh
6.29-April-20168.72  lakh
7.17-May-2016116.25  lakh
8.17-June-201676.76  lakh
9.20-October-201648.68  lakh
10.28-October-201641.93  lakh
11.07-December-201675.94  lakh
12.27-February-201722.19  lakh
13.16-May-201755.12  lakh
14.09-June-2017111.18  lakh
15.27-June-201753.78  lakh
Total 726.11  lakh
% Payment 86.16 %
Advance Amount:  38.66  lakh        Recovered Amount:  38.66  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1768   No. of Test Done : 1755    No. of Test Passed : 1754   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.07
Number of Notice(s) issued: 69

Mobile Pic Upload

Number of Pics Available on Web Repository: 13
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-06-201521+415R/wall completedBheem Singh MeharJEDEA ADB Uttarkashi See Pic
2.18-06-201522+740RR dry with two plum completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
3.18-06-201524+635 to 645R/wall with plum completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
4.18-06-201530+225R/W completed with plumBheem Singh MeharJEDEA ADB Uttarkashi See Pic
5.18-06-201526+925 to 944RR dry completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
6.17-06-201522+825RR dry with 4 no plum completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
7.02-05-201523+260Construction of plum concrete.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
8.02-05-201520+400Plum concrete in progressBheem Singh MeharJEDEA ADB Uttarkashi See Pic
9.02-05-201524+780R/wall in complete.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
10.02-05-201530+910Protection work in complete.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
11.20-04-201523+340Excavation of R/wallBheem Singh MeharJEDEA ADB Uttarkashi See Pic
12.20-04-201530+110R/wall in progressBheem Singh MeharJEDEA ADB Uttarkashi See Pic
13.14-04-201523+24Construction of R/wallBheem Singh MeharJEDEA ADB Uttarkashi See Pic