Naugaon-purola
Bond Terminated.
|
Project: |
UEAP-RB |
UID: |
5001 |
Sanction Cost: |
197.00 lakh |
Length:
|
11.000 KM. |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
Type: |
MDR |
|
Procurement: |
Package No.: 1013
Package Name: 
UEAP/PWD/C11
Tender Date: 03-02-2014
Current Status: Agreement signed
Achieved on Date: 09-06-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C11
Contractor Name: Mathiyan Construction Pvt Ltd
|
Start Date: 30-06-2014
Intended Completion Date: 26-09-2015
|
Total Bond Cost: 53436503.32 (534.37 lakh)
Variation Cost: -44798837.32 (-447.99 lakh) Hence Total Bond Cost is 8637666 (86.38 lakh)
|
Sub Project Cost: 197.00 lakh
Variation Cost of Sub Project: -16129225.78 (-161.29 lakh)
Total Sub Project Cost:
35.71 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4034418 for 151 days
LD Analysis for Milestone2: calculated LD is Rs 4034418 for 151 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.90 KM | 3.80 | 01-12-2014 | 31-12-2014 | 0.56 KM | 0.56 KM | 2.9 | 3.80 | 2. | R/Wall, B/ Wall Type Protection works | 550.00 m | 31.14 | 01-12-2014 | 31-05-2015 | 260.00 m | 260.00 m | 23.82 | 31.14 | 3. | G-3 | 0.76 KM | 1.23 | 01-04-2015 | 31-05-2015 | 0.76 KM | 0.00 KM | 0 | 0.00 | 4. | PC/CC i/c Prime Coat, Tack Coat | 340.00 KM | 27.26 | 01-07-2015 | 15-09-2015 | 340.00 KM | 0.00 KM | 0 | 0.00 | 5. | BM i/c Prime Coat, Tack Coat | 1.17 KM | 19.29 | 01-06-2015 | 15-06-2015 | 1.17 KM | 0.00 KM | 0 | 0.00 | 6. | longitudinal Drain | 2000.00 m | 27.83 | 01-08-2015 | 15-09-2015 | 350.00 m | 350.00 m | 21.29 | 27.83 | 7. | Crash Barrier | 500.00 m | 14.00 | 01-07-2015 | 31-07-2015 | 500.00 m | 0.00 m | 0 | 0.00 | 8. | Road Furniture | 1020.00 No | 6.20 | 01-07-2015 | 31-07-2015 | 1020.00 No | 0.00 No | 0 | 0.00 |
Total Amount: |
130.75 |
|
48.01 |
62.77 |
|
Remarks:
Contract Agreement Terminated due to comprehensive sanction under State Sector.
Work Program Made On:
25-02-2015 } ?>
Updation of work program on:
22-07-2016
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 05-November-2015 | 23.35 lakh |
Previous Package Expenditure Total |
23.35 lakh |
SNo. |
Date |
Payment |
1. | 05-November-2015 | 23.35 lakh |
Total |
23.35 lakh |
% Payment | 65.39 % |
|
Advance Amount: 53.44 lakh
Recovered Amount: 6.50 lakh
Balance to be Recovered 46.94 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 36 No. of Test Done : 36 No. of Test Passed : 36 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.26 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 5 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-03-2015 | 3+625 | Very dangerous points for working, .. Plz suggestions for construction of wall etc. | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
2. | 18-03-2015 | 13+800 | Construction of K C Drain | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
3. | 18-03-2015 | 12+954 | Plum concrete | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
4. | 18-03-2015 | 5+818 | R/wall& wire create complete | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
5. | 21-02-2015 | 2/30 | B/wall with wire crate | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
|
|