Construction of 210m span Arch Steel Truss Bridle Bridge Between Village Amel and Village Khairali Gaon over Kosi River Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4142 Sanction Cost: 1074.38  lakh Span: M
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nainital DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 664        Package Name:  UDRP/AF/BR/100        Tender Date: 11-06-2020        Current Status: Agreement signed        Achieved on Date: 11-11-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/100      Contractor Name: M/S.KGL Infrastructure
Start Date:  28-11-2020      Intended Completion Date:  28-02-2023      Original End Date:  
Total Bond Cost: 109437900.32 (1094.38 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job87.5501-09-202231-12-20220.00 Job0.00 Job00.00
2.Group of Pile4.00 No90.8314-01-202219-06-20224.00 No4.00 No8.390.83
3.Foundation RHS1.00 Job22.7109-05-202215-06-20221.00 Job1.00 Job2.0822.71
4.Foundation LHS1.00 Job22.7114-01-202214-05-20221.00 Job1.00 Job2.0822.71
5.Steel Railing/crush barrier420.00 m0.0001-09-202231-12-20220.00 m0.00 m00.00
6.Approach Ramp /path 300.00 m98.4901-05-202231-12-2022300.00 m225.00 m6.7573.87
7.Protection Work1.00 Job0.0001-07-202225-12-20220.00 Job0.00 Job00.00
8.Errection Work5.00 Job270.6816-08-202231-12-20220.00 Job0.00 Job00.00
9.Fabrication Work5.00 job392.4001-02-202231-07-20225.00 job5.00 job0392.40
10.Abutment Substructure RHS1.00 Job18.1715-06-202223-08-20221.00 Job1.00 Job1.6618.17
11.Abutment Substructure LHS1.00 Job18.1718-05-202206-08-20221.00 Job1.00 Job1.6618.17
12.Well-Abutments/Pier/Shafts/Caps4.00 job72.6705-02-202205-09-20224.00 job4.00 job6.6472.67
Total Amount: 1094.38 73.99   711.53
Remarks: No Remarks       Work Program Made On: 26-03-2021        Updation of work program on: 20-12-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.27-January-20223.00  lakh
2.06-April-202243.56  lakh
3.30-May-202285.36  lakh
4.31-May-2022235.44  lakh
5.15-June-2022175.13  lakh
6.27-July-202240.88  lakh
7.31-August-202254.50  lakh
8.22-September-202254.50  lakh
9.22-December-20225.84  lakh
10.27-January-202346.29  lakh
11.13-February-2023110.25  lakh
12.27-February-2023165.37  lakh
13.17-April-2023104.00  lakh
Total 1124.12  lakh
% Payment 102.7 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1337   No. of Test Done : 1337    No. of Test Passed : 1337   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.04
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 242
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-06-2022Amel-Khairali BetalghatCube casting work in progress for Pier-4 first lift at Amel Betalghat Haldwani District-NainitalMadhav Singh ` ` See Pic
2.24-06-20224142Slump test for Pier-4 first lift at BR-100 Amel-Khairali Betalghat Haldwani District-NainitalMadhav Singh ` ` See Pic
3.24-06-2022Amel-Khairali BetalghatPoring of M35 grade of concrete work is in progress for Pier-4 first lift at BR-100 Amel Betalghat Haldwani District-NainitalMadhav singh ` ` See Pic
4.24-06-2022BR/100Concrete work is in progress for pier-4 of Ist lift.Sanjeev Sharma ` ` See Pic
5.23-06-2022BR/100Cube casting for Pier-3 of Ist liftSanjeev Sharma ` ` See Pic
6.23-06-2022BR/100Slump test for pier-3 of Ist liftSanjeev Sharma ` ` See Pic
7.23-06-2022BR/100Concrete work started for Ist lift of pier-3Sanjeev Sharma ` ` See Pic
8.23-06-2022BR-100Pier no-03 1st lift concreting work is in progress...Jaspal rawat ` ` See Pic
9.22-06-2022BR 100At Ramnagar yard Ground ErectionSantosh Shukla ` ` See Pic
10.22-06-2022BR 100At Ramnagar yard inspection graund ErectionSantosh Shukla ` ` See Pic
11.22-06-2022BR 100At Ramnagar yard Inspection ground ErectionSantosh Shukla ` ` See Pic
12.21-06-2022BR/100Concrete work completed for pile cap of Pier-3Sanjeev Sharma ` ` See Pic
13.21-06-2022BR/100Cube casting for pile cap concrete of pier-3Sanjeev Sharma ` ` See Pic
14.21-06-2022BR/100Slump test for pile cap concrete of pier-3Sanjeev Sharma ` ` See Pic
15.21-06-2022BR-100Pier no-03 pile cap concreting work is in progress....Jaspal rawat ` ` See Pic
16.21-06-2022BR/100Pile cap concrete work started of pier-3Sanjeev Sharma ` ` See Pic
17.21-06-2022BR/100Pile cap reinforcement & Shuttering work is in progress of pier-3Sanjeev Sharma ` ` See Pic
18.20-06-2022BR/100Dewatering work is in progress for pile cap of Pier-3Sanjeev Sharma ` ` See Pic
19.19-06-2022BR/100Pile cap concreting work completed of pier-4Sanjeev Sharma ` ` See Pic
20.19-06-2022BR/100Cube casting for pile cap of Pier-4Sanjeev Sharma ` ` See Pic