Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Construction of 125m span Bridle Arch Steel Truss Bridge Between Village Chapad and Village Ropa over Kosi Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4141 Sanction Cost: 750.88  lakh Span: M
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA Nainital DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 662        Package Name:  UDRP/AF/BR/99        Tender Date: 11-06-2020        Current Status: Agreement signed        Achieved on Date: 26-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/99      Contractor Name: M/S.KGL Infrastructure
Start Date:  14-11-2020      Intended Completion Date:  27-11-2022      Original End Date:  31-03-2022
Total Bond Cost: 66754174.35 (667.54 lakh)        Variation Cost: -683811.80 (-6.84 lakh)    Hence Total Bond Cost is   66070362.55 (660.7 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 15787321 for 473 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan33.00 Job2.8221-02-202103-11-202233.00 Job33.00 Job0.412.82
2.Other Allied Works & Finishing Work 1.00 Job1.3501-07-202230-08-20221.00 Job0.00 Job00.00
3.Pile Cap1.00 No8.0221-02-202228-02-20221.00 No0.00 No00.00
4.Group of Pile1.00 No40.4305-12-202107-02-20221.00 No1.00 No5.8940.43
5.Foundation RHS1.00 Job14.9401-01-202116-02-20211.00 Job1.00 Job2.1814.94
6.Foundation LHS1.00 Job16.1717-02-202115-04-20211.00 Job1.00 Job2.3616.17
7.Steel Railing/crush barrier452.40 m10.3615-06-202230-06-2022452.40 m0.00 m00.00
8.Approach Ramp /path 100.00 m66.3615-09-202131-07-2022100.00 m0.00 m00.00
9.Protection Work3.00 Job42.7915-09-202131-07-20223.00 Job0.00 Job00.00
10.Errection Work1.00 Job130.4901-04-202230-06-20221.00 Job0.00 Job00.00
11.PCC in Foundation30.17 cum2.1320-12-202010-01-202130.17 cum30.17 cum0.312.13
12.Excavation in soil914.21 cum2.0115-12-202031-12-2020914.21 cum900.00 cum0.291.98
13.Fabrication Work1.00 job259.4001-02-202128-02-20221.00 job1.00 job37.78259.40
14.Abutment Substructure RHS1.00 Job35.1317-02-202130-10-20211.00 Job1.00 Job5.1235.13
15.Abutment Substructure LHS1.00 Job35.1316-04-202110-11-20211.00 Job1.00 Job5.1235.13
16.Fixing Bearing/Slab Casting8.00 job4.3815-03-202231-07-20228.00 job0.00 job00.00
17.Back Wall/ Approach slab1.00 job2.7001-07-202215-07-20221.00 job0.00 job00.00
18.Well-Abutments/Pier/Shafts/Caps1.00 job11.5001-03-202207-04-20221.00 job0.00 job00.00
19.Wearing Coat3.75 Cum0.5501-08-202210-08-20223.75 Cum0.00 Cum00.00
Total Amount: 686.66 59.44   408.13
Remarks: No Remarks       Work Program Made On: 20-02-2021        Updation of work program on: 20-12-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-May-202159.21  lakh
2.16-September-202130.86  lakh
3.21-January-2022128.91  lakh
4.22-February-2022174.97  lakh
5.31-March-20220.75  lakh
6.31-May-202272.99  lakh
7.31-August-202278.81  lakh
8.29-November-202289.33  lakh
9.22-December-20228.50  lakh
10.23-March-202326.71  lakh
Total 671.04  lakh
% Payment 101.79 %
Advance Amount:  92.27  lakh        Recovered Amount:  92.27  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): EMP, Boot, Glove, Signs, water sprinkling
Detailed report of this subproject
Quality
No. of Test Required : 817   No. of Test Done : 811    No. of Test Passed : 801   No. of Test Failed : 10   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.50
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 291
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-06-2022BR/99Top chord erection work is in progress of first spanSanjeev Sharma ` ` See Pic
2.23-06-2022BR/99Slump test for pier 2nd liftSanjeev Sharma ` ` See Pic
3.23-06-2022BR/99Concrete work is in progress of pier 2nd liftSanjeev Sharma ` ` See Pic
4.22-06-2022BR/99Bottom chord erection work is in progress for first spamSanjeev Sharma ` ` See Pic
5.20-06-2022BR/99Bottom chord erection work is in progressSanjeev Sharma ` ` See Pic
6.19-06-2022BR/99Bottom chord erection work is in progressSanjeev Sharma ` ` See Pic
7.18-06-2022BR/99Bottom chord erection work is in progressSanjeev Sharma ` ` See Pic
8.17-06-2022BR/99Erection work is in progressSanjeev Sharma ` ` See Pic
9.16-06-2022BR/99Erection work is in progressSanjeev Sharma ` ` See Pic
10.15-06-2022BR/99Curing work is in progress of pierSanjeev Sharma ` ` See Pic
11.15-06-2022BR/99Erection work is in progressSanjeev Sharma ` ` See Pic
12.14-06-2022BR/99Erection work started of RHS AbutmentSanjeev Sharma ` ` See Pic
13.13-06-2022BR/99Curing work for Pier 1st liftSanjeev Sharma ` ` See Pic
14.09-06-2022Ropa Betalghat NainitalCube casting for Pier 1st Lift Concreting workSurendra Singh Bisht ` ` See Pic
15.09-06-2022Ropa Betalghat NainitalSlump Test for Pier 1st Lift Concreting workSurendra Singh Bisht ` ` See Pic
16.09-06-2022Ropa Betalghat NainitalPier 1st Lift Concreting work startedSurendra Singh Bisht ` ` See Pic
17.09-06-2022Ropa Betalghat NainitalPier 1st Lift Shuttering Checking work is in progressSurendra Singh Bisht ` ` See Pic
18.08-06-2022BR 99Pier column concreting work is in progress...Jaspal rawat ` ` See Pic
19.08-06-2022BR -99Pier column shuttering checking work is in progress...Jaspal rawat ` ` See Pic
20.07-06-2022BR-99A1(LHS) abutment approach road (PQC) work is in progress.....Jaspal rawat ` ` See Pic