70 Mtr span motor bridge at Km-166 of Munsyari motor road at hardiya nala.
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4139 |
Sanction Cost: |
987.07 lakh |
Span:
|
70.000 M |
District: |
Pithoragarh |
Block: |
0049 |
Constituency: |
42 |
Circle: |
|
DEA: |
DEA Munsyari |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 620
Package Name: 
UDRP/AF/BR/47
Tender Date: 21-09-2019
Current Status: Agreement signed
Achieved on Date: 20-01-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/47
Contractor Name: M/S.G.S.Matiyani and sons
|
Start Date: 27-01-2020
Intended Completion Date: 06-08-2022
Original End Date: 26-07-2021 |
Total Bond Cost: 86310066.23 (863.1 lakh)
Variation Cost: 16325553.40 (163.26 lakh) Hence Total Bond Cost is 102635619.63 (1026.36 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 25893000 for 600 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 152.94 | 27-01-2020 | 04-08-2022 | 1.00 Job | 1.00 Job | 17.72 | 152.94 | 2. | Foundation RHS | 1.00 Job | 0.48 | 27-01-2020 | 15-10-2020 | 1.00 Job | 1.00 Job | 0.06 | 0.48 | 3. | Foundation LHS | 1.00 Job | 2.19 | 30-01-2020 | 17-01-2021 | 1.00 Job | 1.00 Job | 0.25 | 2.19 | 4. | Fixing of chequered Plate/RCC Deck | 616.62 sqm | 24.89 | 21-04-2022 | 22-05-2022 | 616.62 sqm | 616.62 sqm | 2.88 | 24.89 | 5. | Steel Railing/crush barrier | 143.40 m | 9.15 | 01-06-2022 | 30-06-2022 | 143.40 m | 143.40 m | 1.06 | 9.15 | 6. | Approach Ramp /path | 100.00 m | 53.15 | 28-01-2020 | 10-07-2022 | 100.00 m | 100.00 m | 6.16 | 53.15 | 7. | Protection Work | 1.00 Job | 24.40 | 10-02-2020 | 12-05-2022 | 1.00 Job | 1.00 Job | 2.83 | 24.40 | 8. | Errection Work | 1.00 Job | 119.34 | 15-09-2021 | 29-03-2022 | 1.00 Job | 1.00 Job | 13.83 | 119.34 | 9. | Fabrication Work | 1.00 job | 387.85 | 19-02-2020 | 15-08-2021 | 1.00 job | 1.00 job | 44.94 | 387.85 | 10. | Abutment Substructure RHS | 1.00 Job | 18.03 | 16-10-2020 | 20-08-2021 | 1.00 Job | 1.00 Job | 2.09 | 18.03 | 11. | Abutment Substructure LHS | 1.00 Job | 70.68 | 17-12-2020 | 25-08-2021 | 1.00 Job | 1.00 Job | 8.19 | 70.68 |
Total Amount: |
863.1 |
|
100 |
863.1 |
|
Remarks:
No Remarks
Work Program Made On:
06-05-2020 } ?>
Updation of work program on:
27-02-2023
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2020 | 61.17 lakh | 2. | 08-December-2020 | 23.68 lakh | 3. | 30-January-2021 | 29.80 lakh | 4. | 31-March-2021 | 27.57 lakh | 5. | 06-May-2021 | 40.44 lakh | 6. | 27-July-2021 | 25.04 lakh | 7. | 28-August-2021 | 22.45 lakh | 8. | 21-September-2021 | 353.40 lakh | 9. | 09-November-2021 | 60.77 lakh | 10. | 16-February-2022 | 51.90 lakh | 11. | 31-March-2022 | 210.48 lakh | 12. | 13-May-2022 | 17.94 lakh | 13. | 31-May-2022 | 35.73 lakh | 14. | 15-June-2022 | 38.14 lakh | 15. | 14-September-2022 | 14.30 lakh | 16. | 30-December-2022 | 15.05 lakh |
Total |
1027.86 lakh |
% Payment |
99.99 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 565 No. of Test Done : 670 No. of Test Passed : 670 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.45 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 531 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-06-2022 | Haradiya Nala | Expansion joint fixing work in progress | Shoyab ali | unknown | unknown | See Pic |
2. | 23-06-2022 | Haradiya Nala | Deck slab curing work in progress | Shoyab ali | unknown | unknown | See Pic |
3. | 13-06-2022 | Haradiya nala, BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
4. | 13-06-2022 | Haradiya nala, BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
5. | 11-06-2022 | Haradiya nala, BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
6. | 11-06-2022 | Haradiya nala ,BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
7. | 11-06-2022 | Haradiya nala, BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
8. | 11-06-2022 | Haradiya nala, BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
9. | 11-06-2022 | Haradiya nala, BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
10. | 09-06-2022 | Haradiya nala ,BR-47 | Reinforcement of laying deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
11. | 09-06-2022 | Haradiya nala ,BR-47 | Reinforcement of deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
12. | 09-06-2022 | Haradiya nala, BR-47 | Reinforcement of deck slab work in progress | Mukesh Mandal | ` | ` | See Pic |
13. | 09-06-2022 | Haradiya nala ,BR-47 | Painting and deck slab of reinforcement work in progress | Mukesh Mandal | ` | ` | See Pic |
14. | 09-06-2022 | Haradiya nala, BR-47 | Painting and deck slab of reinforcement work in progress | Mukesh Mandal | ` | ` | See Pic |
15. | 09-06-2022 | Haradiya nala, BR-47 | Deck slab of reinforcement work in progress | Mukesh Mandal | ` | ` | See Pic |
16. | 06-06-2022 | Haradiya nala, BR-47 | Painting and deck slab of reinforcement work in progress | Mukesh Mandal | ` | ` | See Pic |
17. | 06-06-2022 | Haradiya nala, BR-47 | Painting and deck slab of reinforcement work in progress | Mukesh Mandal | ` | ` | See Pic |
18. | 06-06-2022 | Haradiya Nala | Deck slab Reinforcement work in progress | Shoyab ali | unknown | unknown | See Pic |
19. | 06-06-2022 | Haradiya Nala | Deck slab Reinforcement work in progress | Shoyab ali | unknown | unknown | See Pic |
20. | 06-06-2022 | Haradiya Nala | Deck slab Reinforcement work in progress | Shoyab ali | unknown | unknown | See Pic |
|
|