Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge Over Gandak River at KM-2 of Champawat to Manch Tamali MR Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4136 Sanction Cost: 269.39  lakh Span: 30.000 M
District: Champawat Block: Champawat Constituency: Champawat Circle:
DEA: DEA Champawat DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 610        Package Name:  UDRP/AF/BR/96        Tender Date: 30-12-2019        Current Status: Agreement signed        Achieved on Date: 14-07-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/96      Contractor Name: M/s Laxmi Datt Binwal
Start Date:  21-08-2020      Intended Completion Date:  13-02-2022      Original End Date:  20-11-2021
Total Bond Cost: 25133492.44 (251.33 lakh)        Variation Cost: -1429314.77 (-14.29 lakh)    Hence Total Bond Cost is   23704177.67 (237.04 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 6094995 for 485 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job21.6920-12-202012-03-20221.00 Job1.00 Job8.6321.69
2.Foundation RHS1.00 Job9.9120-12-202025-04-20211.00 Job1.00 Job3.949.91
3.Foundation LHS1.00 Job14.5415-02-202115-04-20211.00 Job1.00 Job5.7914.54
4.Abutment Superstructure RHS1.00 Job26.8716-03-202115-08-20211.00 Job1.00 Job10.6926.87
5.Abutment Superstructure LHS1.00 Job26.8717-04-202120-08-20211.00 Job1.00 Job10.6926.87
6.Fixing of chequered Plate/RCC Deck62.10 sqm6.4001-01-202231-01-202262.10 sqm62.10 sqm2.556.40
7.Steel Railing/crush barrier64.00 m3.4301-02-202210-03-202264.00 m64.00 m1.373.43
8.Approach Ramp /path 110.00 m45.1001-10-202110-03-2022110.00 m110.00 m17.9445.10
9.Protection Work1.00 Job22.8115-09-202130-12-20211.00 Job1.00 Job9.0822.81
10.Errection Work1.00 Job21.1901-09-202101-10-20211.00 Job1.00 Job8.4321.19
11.Fabrication Work1.00 job52.5215-03-202115-07-20211.00 job1.00 job20.952.52
Total Amount: 251.33 100   251.33
Remarks: No Remarks       Work Program Made On: 16-12-2020        Updation of work program on: 23-05-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-202118.45  lakh
2.06-May-202120.48  lakh
3.13-July-202152.20  lakh
4.28-August-20215.68  lakh
5.09-November-202123.10  lakh
6.30-November-202153.39  lakh
7.31-December-202111.03  lakh
8.16-February-202220.35  lakh
9.13-May-202220.23  lakh
10.31-May-202212.14  lakh
Total 237.05  lakh
% Payment 96.43 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 298   No. of Test Done : 320    No. of Test Passed : 320   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 91.35
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 185
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-03-2022BR-96Curing of deck slab is in progressAbhay Singh ` ` See Pic
2.23-03-2022BR-96Painting of crash barrier is in progressAbhay singh ` ` See Pic
3.23-03-2022BR-96Concrete work of bearing coat is in progressAbhay singh ` ` See Pic
4.23-03-2022BR-96Casting of Perapet is in progressAbhay singh ` ` See Pic
5.23-03-2022BR-96Concrete work of crash barrier is completedAbhay singh ` ` See Pic
6.23-03-2022BR-96Concrete work of crash barrier is in progress M40 gradeAbhay singh ` ` See Pic
7.23-03-2022BR-96Curing of crash barrier is in progressAbhay singh ` ` See Pic
8.23-03-2022BR-96Casting of bearing coat is in progress of approach slab in A2 sideAbhay Singh ` ` See Pic
9.23-03-2022BR-96Concrete work of approach slab is in progress in A1 sideAbhay singh ` ` See Pic
10.23-03-2022BR-96Curing of deck slab is in progressAbhay singh ` ` See Pic
11.23-03-2022BR-96Rcc crash barrier concrete M40 is in progressAbhay singh ` ` See Pic
12.23-03-2022BR-96Laying pcc in approach road in A2 sideAbhay singh ` ` See Pic
13.04-03-2022BR-96Concrete work of crash barrier is completedAbhay Singh ` ` See Pic
14.04-03-2022BR-96Concrete work of crash barrier is in progress M40 gradeAbhay singh ` ` See Pic
15.03-03-2022BR-96Curing of crash barrier is in progressAbhay singh ` ` See Pic
16.03-03-2022BR-96Curing work is progress of deck slabAbhay singh ` ` See Pic
17.02-03-2022BR-96Concrete work of crash barrier is completed in U/SAbhay singh ` ` See Pic
18.02-03-2022BR-96Casting of crash barrier M40 grade is in progressAbhay singh ` ` See Pic
19.01-03-2022BR-96Shuttering work of crash barrier is in progressAbhay singh ` ` See Pic
20.01-03-2022BR-96Curing of deck slab is in progressAbhay singh ` ` See Pic