Bridge Over Gandak River at KM-2 of Champawat to Manch Tamali MR
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4136 |
Sanction Cost: |
269.39 lakh |
Span:
|
30.000 M |
District: |
Champawat |
Block: |
Champawat |
Constituency: |
Champawat |
Circle: |
|
DEA: |
DEA Champawat |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 610
Package Name: 
UDRP/AF/BR/96
Tender Date: 30-12-2019
Current Status: Agreement signed
Achieved on Date: 14-07-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/96
Contractor Name: M/s Laxmi Datt Binwal
|
Start Date: 21-08-2020
Intended Completion Date: 13-02-2022
Original End Date: 20-11-2021 |
Total Bond Cost: 25133492.44 (251.33 lakh)
Variation Cost: -1429314.77 (-14.29 lakh) Hence Total Bond Cost is 23704177.67 (237.04 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 6094995 for 485 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 21.69 | 20-12-2020 | 12-03-2022 | 1.00 Job | 1.00 Job | 8.63 | 21.69 | 2. | Foundation RHS | 1.00 Job | 9.91 | 20-12-2020 | 25-04-2021 | 1.00 Job | 1.00 Job | 3.94 | 9.91 | 3. | Foundation LHS | 1.00 Job | 14.54 | 15-02-2021 | 15-04-2021 | 1.00 Job | 1.00 Job | 5.79 | 14.54 | 4. | Abutment Superstructure RHS | 1.00 Job | 26.87 | 16-03-2021 | 15-08-2021 | 1.00 Job | 1.00 Job | 10.69 | 26.87 | 5. | Abutment Superstructure LHS | 1.00 Job | 26.87 | 17-04-2021 | 20-08-2021 | 1.00 Job | 1.00 Job | 10.69 | 26.87 | 6. | Fixing of chequered Plate/RCC Deck | 62.10 sqm | 6.40 | 01-01-2022 | 31-01-2022 | 62.10 sqm | 62.10 sqm | 2.55 | 6.40 | 7. | Steel Railing/crush barrier | 64.00 m | 3.43 | 01-02-2022 | 10-03-2022 | 64.00 m | 64.00 m | 1.37 | 3.43 | 8. | Approach Ramp /path | 110.00 m | 45.10 | 01-10-2021 | 10-03-2022 | 110.00 m | 110.00 m | 17.94 | 45.10 | 9. | Protection Work | 1.00 Job | 22.81 | 15-09-2021 | 30-12-2021 | 1.00 Job | 1.00 Job | 9.08 | 22.81 | 10. | Errection Work | 1.00 Job | 21.19 | 01-09-2021 | 01-10-2021 | 1.00 Job | 1.00 Job | 8.43 | 21.19 | 11. | Fabrication Work | 1.00 job | 52.52 | 15-03-2021 | 15-07-2021 | 1.00 job | 1.00 job | 20.9 | 52.52 |
Total Amount: |
251.33 |
|
100 |
251.33 |
|
Remarks:
No Remarks
Work Program Made On:
16-12-2020 } ?>
Updation of work program on:
23-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2021 | 18.45 lakh | 2. | 06-May-2021 | 20.48 lakh | 3. | 13-July-2021 | 52.20 lakh | 4. | 28-August-2021 | 5.68 lakh | 5. | 09-November-2021 | 23.10 lakh | 6. | 30-November-2021 | 53.39 lakh | 7. | 31-December-2021 | 11.03 lakh | 8. | 16-February-2022 | 20.35 lakh | 9. | 13-May-2022 | 20.23 lakh | 10. | 31-May-2022 | 12.14 lakh |
Total |
237.05 lakh |
% Payment |
96.43 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 298 No. of Test Done : 320 No. of Test Passed : 320 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.35 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 185 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-03-2022 | BR-96 | Curing of deck slab is in progress | Abhay Singh | ` | ` | See Pic |
2. | 23-03-2022 | BR-96 | Painting of crash barrier is in progress | Abhay singh | ` | ` | See Pic |
3. | 23-03-2022 | BR-96 | Concrete work of bearing coat is in progress | Abhay singh | ` | ` | See Pic |
4. | 23-03-2022 | BR-96 | Casting of Perapet is in progress | Abhay singh | ` | ` | See Pic |
5. | 23-03-2022 | BR-96 | Concrete work of crash barrier is completed | Abhay singh | ` | ` | See Pic |
6. | 23-03-2022 | BR-96 | Concrete work of crash barrier is in progress M40 grade | Abhay singh | ` | ` | See Pic |
7. | 23-03-2022 | BR-96 | Curing of crash barrier is in progress | Abhay singh | ` | ` | See Pic |
8. | 23-03-2022 | BR-96 | Casting of bearing coat is in progress of approach slab in A2 side | Abhay Singh | ` | ` | See Pic |
9. | 23-03-2022 | BR-96 | Concrete work of approach slab is in progress in A1 side | Abhay singh | ` | ` | See Pic |
10. | 23-03-2022 | BR-96 | Curing of deck slab is in progress | Abhay singh | ` | ` | See Pic |
11. | 23-03-2022 | BR-96 | Rcc crash barrier concrete M40 is in progress | Abhay singh | ` | ` | See Pic |
12. | 23-03-2022 | BR-96 | Laying pcc in approach road in A2 side | Abhay singh | ` | ` | See Pic |
13. | 04-03-2022 | BR-96 | Concrete work of crash barrier is completed | Abhay Singh | ` | ` | See Pic |
14. | 04-03-2022 | BR-96 | Concrete work of crash barrier is in progress M40 grade | Abhay singh | ` | ` | See Pic |
15. | 03-03-2022 | BR-96 | Curing of crash barrier is in progress | Abhay singh | ` | ` | See Pic |
16. | 03-03-2022 | BR-96 | Curing work is progress of deck slab | Abhay singh | ` | ` | See Pic |
17. | 02-03-2022 | BR-96 | Concrete work of crash barrier is completed in U/S | Abhay singh | ` | ` | See Pic |
18. | 02-03-2022 | BR-96 | Casting of crash barrier M40 grade is in progress | Abhay singh | ` | ` | See Pic |
19. | 01-03-2022 | BR-96 | Shuttering work of crash barrier is in progress | Abhay singh | ` | ` | See Pic |
20. | 01-03-2022 | BR-96 | Curing of deck slab is in progress | Abhay singh | ` | ` | See Pic |
|
|