Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge over Ramganga River on Hinaula Kaney Khalpati MR at KM-14 Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4135 Sanction Cost: 640.49  lakh Span: 70.000 M
District: Almora Block: Sult Constituency: Salt Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 637        Package Name:  UDRP/AF/BR/94        Tender Date: 02-12-2019        Current Status: Agreement signed        Achieved on Date: 10-06-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/94      Contractor Name: Gaurav Builder
Start Date:  10-09-2020      Intended Completion Date:  26-03-2023      Original End Date:  09-03-2022
Total Bond Cost: 65956234.96 (659.56 lakh)        Variation Cost: -369844.58 (-3.7 lakh)    Hence Total Bond Cost is   65586390.38 (655.86 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 28525970 for 865 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job5.4010-09-202001-08-20221.00 Job1.00 Job0.825.40
2.Other Allied Works & Finishing Work 1.00 Job5.2615-01-202125-07-20221.00 Job1.00 Job0.85.26
3.Foundation RHS1.00 Job27.1201-11-202030-06-20211.00 Job1.00 Job4.1227.12
4.Foundation LHS1.00 Job27.4201-12-202010-07-20211.00 Job1.00 Job4.1627.42
5.Abutment Superstructure LHS1.00 Job0.2016-06-202120-06-20221.00 Job1.00 Job0.030.20
6.Fixing of chequered Plate/RCC Deck367.50 sqm30.9815-07-202230-07-2022367.50 sqm367.50 sqm4.730.98
7.Steel Railing/crush barrier140.00 m9.4920-07-202230-07-2022140.00 m140.00 m1.449.49
8.Approach Ramp /path 2.00 m104.7901-01-202120-07-20222.00 m2.00 m15.9104.79
9.Protection Work1.00 Job27.0401-12-202120-07-20221.00 Job1.00 Job4.127.04
10.Errection Work1.00 Job111.1506-06-202215-07-20221.00 Job1.00 Job16.87111.15
11.Fabrication Work1.00 job211.6710-04-202130-06-20221.00 job1.00 job32.12211.67
12.Abutment Substructure RHS1.00 Job49.2101-05-202131-05-20221.00 Job1.00 Job7.4749.21
13.Abutment Substructure LHS1.00 Job49.2111-07-202125-06-20221.00 Job1.00 Job7.4749.21
Total Amount: 658.94 100   658.94
Remarks: No Remarks       Work Program Made On: 02-01-2021        Updation of work program on: 23-05-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-February-202126.24  lakh
2.30-March-202115.33  lakh
3.05-August-202196.92  lakh
4.23-September-202119.85  lakh
5.30-October-202113.76  lakh
6.26-May-202224.34  lakh
7.22-November-2022160.22  lakh
8.30-November-202242.13  lakh
9.30-December-202288.82  lakh
10.31-December-202210.84  lakh
11.25-January-202315.83  lakh
12.24-February-202333.61  lakh
Total 547.89  lakh
% Payment 83.12 %
Advance Amount:  49.70  lakh        Recovered Amount:  39.40  lakh        Balance to be Recovered  10.30  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): EMP
Detailed report of this subproject
Quality
No. of Test Required : 493   No. of Test Done : 498    No. of Test Passed : 495   No. of Test Failed : 3   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.94
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 159
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-06-2022Bridge BR94Abutment RHSRajesh sharma ` ` See Pic
2.10-06-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS abutment 6th lift RCC work in progressRoop ` ` See Pic
3.09-06-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS abutment 6th lift Shuttering work in progressRoop ` ` See Pic
4.17-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS Abutment 6th lift Shuttering workRoop ` ` See Pic
5.17-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS Abutment 6th lift Shuttering work in progressRoop ` ` See Pic
6.12-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS Abutment 6th lift Shuttering work in progressRoop ` ` See Pic
7.11-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS Abutment 6th lift Shuttering work in progressRoop ` ` See Pic
8.09-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRHS abutment cap Shuttering workRoop ` ` See Pic
9.06-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRHS Abutment cap reinforcement & Shuttering work in progressRoop ` ` See Pic
10.06-05-2022BR-94 hinaula kane khalpati motor road KM-7Steel binding and shuttring of cap at A2 is in progressAnurag Rawat ` ` See Pic
11.05-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRHS abutment cap reinforcement & Shuttering work in progressRoop ` ` See Pic
12.05-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraHill cutting near LHS Abutment side approach roadRoop ` ` See Pic
13.04-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRRM work in progress towards RHS approach roadRoop ` ` See Pic
14.01-05-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRRM work in progress towards RHS approach roadRoop ` ` See Pic
15.30-04-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRRM work in progress towards RHS approach roadRoop ` ` See Pic
16.30-04-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS Abutment 6th lift Reinforcement work is in progressRoop ` ` See Pic
17.30-04-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS abutment 6th lift Reinforcement work in progressRoop ` ` See Pic
18.30-04-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRRM work in progress to LHS approach roadRoop ` ` See Pic
19.25-04-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraLHS Abutment 6th lift Reinforcement work in progressRoop ` ` See Pic
20.25-04-2022Hinola Kaney khalpati motor road at Km-14 in distt-AlmoraRRM work is in progress to LHS approach roadRoop ` ` See Pic