Bridge over Ramganga River on Hinaula Kaney Khalpati MR at KM-14
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4135 |
Sanction Cost: |
640.49 lakh |
Span:
|
70.000 M |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 637
Package Name: 
UDRP/AF/BR/94
Tender Date: 02-12-2019
Current Status: Agreement signed
Achieved on Date: 10-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/94
Contractor Name: Gaurav Builder
|
Start Date: 10-09-2020
Intended Completion Date: 26-03-2023
Original End Date: 09-03-2022 |
Total Bond Cost: 65956234.96 (659.56 lakh)
Variation Cost: -369844.58 (-3.7 lakh) Hence Total Bond Cost is 65586390.38 (655.86 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 28525970 for 865 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 5.40 | 10-09-2020 | 01-08-2022 | 1.00 Job | 1.00 Job | 0.82 | 5.40 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 5.26 | 15-01-2021 | 25-07-2022 | 1.00 Job | 1.00 Job | 0.8 | 5.26 | 3. | Foundation RHS | 1.00 Job | 27.12 | 01-11-2020 | 30-06-2021 | 1.00 Job | 1.00 Job | 4.12 | 27.12 | 4. | Foundation LHS | 1.00 Job | 27.42 | 01-12-2020 | 10-07-2021 | 1.00 Job | 1.00 Job | 4.16 | 27.42 | 5. | Abutment Superstructure LHS | 1.00 Job | 0.20 | 16-06-2021 | 20-06-2022 | 1.00 Job | 1.00 Job | 0.03 | 0.20 | 6. | Fixing of chequered Plate/RCC Deck | 367.50 sqm | 30.98 | 15-07-2022 | 30-07-2022 | 367.50 sqm | 367.50 sqm | 4.7 | 30.98 | 7. | Steel Railing/crush barrier | 140.00 m | 9.49 | 20-07-2022 | 30-07-2022 | 140.00 m | 140.00 m | 1.44 | 9.49 | 8. | Approach Ramp /path | 2.00 m | 104.79 | 01-01-2021 | 20-07-2022 | 2.00 m | 2.00 m | 15.9 | 104.79 | 9. | Protection Work | 1.00 Job | 27.04 | 01-12-2021 | 20-07-2022 | 1.00 Job | 1.00 Job | 4.1 | 27.04 | 10. | Errection Work | 1.00 Job | 111.15 | 06-06-2022 | 15-07-2022 | 1.00 Job | 1.00 Job | 16.87 | 111.15 | 11. | Fabrication Work | 1.00 job | 211.67 | 10-04-2021 | 30-06-2022 | 1.00 job | 1.00 job | 32.12 | 211.67 | 12. | Abutment Substructure RHS | 1.00 Job | 49.21 | 01-05-2021 | 31-05-2022 | 1.00 Job | 1.00 Job | 7.47 | 49.21 | 13. | Abutment Substructure LHS | 1.00 Job | 49.21 | 11-07-2021 | 25-06-2022 | 1.00 Job | 1.00 Job | 7.47 | 49.21 |
Total Amount: |
658.94 |
|
100 |
658.94 |
|
Remarks:
No Remarks
Work Program Made On:
02-01-2021 } ?>
Updation of work program on:
23-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-February-2021 | 26.24 lakh | 2. | 30-March-2021 | 15.33 lakh | 3. | 05-August-2021 | 96.92 lakh | 4. | 23-September-2021 | 19.85 lakh | 5. | 30-October-2021 | 13.76 lakh | 6. | 26-May-2022 | 24.34 lakh | 7. | 22-November-2022 | 160.22 lakh | 8. | 30-November-2022 | 42.13 lakh | 9. | 30-December-2022 | 88.82 lakh | 10. | 31-December-2022 | 10.84 lakh | 11. | 25-January-2023 | 15.83 lakh | 12. | 24-February-2023 | 33.61 lakh |
Total |
547.89 lakh |
% Payment |
83.12 % |
|
Advance Amount: 49.70 lakh
Recovered Amount: 39.40 lakh
Balance to be Recovered 10.30 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 493 No. of Test Done : 498 No. of Test Passed : 495 No. of Test Failed : 3 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 93.94 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 159 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-06-2022 | Bridge BR94 | Abutment RHS | Rajesh sharma | ` | ` | See Pic |
2. | 10-06-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS abutment 6th lift RCC work in progress | Roop | ` | ` | See Pic |
3. | 09-06-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS abutment 6th lift Shuttering work in progress | Roop | ` | ` | See Pic |
4. | 17-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS Abutment 6th lift Shuttering work | Roop | ` | ` | See Pic |
5. | 17-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS Abutment 6th lift Shuttering work in progress | Roop | ` | ` | See Pic |
6. | 12-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS Abutment 6th lift Shuttering work in progress | Roop | ` | ` | See Pic |
7. | 11-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS Abutment 6th lift Shuttering work in progress | Roop | ` | ` | See Pic |
8. | 09-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RHS abutment cap Shuttering work | Roop | ` | ` | See Pic |
9. | 06-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RHS Abutment cap reinforcement & Shuttering work in progress | Roop | ` | ` | See Pic |
10. | 06-05-2022 | BR-94 hinaula kane khalpati motor road KM-7 | Steel binding and shuttring of cap at A2 is in progress | Anurag Rawat | ` | ` | See Pic |
11. | 05-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RHS abutment cap reinforcement & Shuttering work in progress | Roop | ` | ` | See Pic |
12. | 05-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | Hill cutting near LHS Abutment side approach road | Roop | ` | ` | See Pic |
13. | 04-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RRM work in progress towards RHS approach road | Roop | ` | ` | See Pic |
14. | 01-05-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RRM work in progress towards RHS approach road | Roop | ` | ` | See Pic |
15. | 30-04-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RRM work in progress towards RHS approach road | Roop | ` | ` | See Pic |
16. | 30-04-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS Abutment 6th lift Reinforcement work is in progress | Roop | ` | ` | See Pic |
17. | 30-04-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS abutment 6th lift Reinforcement work in progress | Roop | ` | ` | See Pic |
18. | 30-04-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RRM work in progress to LHS approach road | Roop | ` | ` | See Pic |
19. | 25-04-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | LHS Abutment 6th lift Reinforcement work in progress | Roop | ` | ` | See Pic |
20. | 25-04-2022 | Hinola Kaney khalpati motor road at Km-14 in distt-Almora | RRM work is in progress to LHS approach road | Roop | ` | ` | See Pic |
|
|