Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge on Bailkana Gadera on Pipna Manhaith Dangula MR at KM-7 Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4134 Sanction Cost: 435.09  lakh Span: 48.000 M
District: Almora Block: Sult Constituency: Salt Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 660        Package Name:  UDRP/AF/BR/93        Tender Date: 02-12-2019        Current Status: Agreement signed        Achieved on Date: 06-07-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/93      Contractor Name: Gaurav Builder
Start Date:  27-08-2020      Intended Completion Date:  13-08-2022      Original End Date:  26-11-2021
Total Bond Cost: 46814331.2 (468.14 lakh)        Variation Cost: 2357712.63 (23.58 lakh)    Hence Total Bond Cost is   49172043.83 (491.72 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11867349 for 507 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job4.5627-08-202030-05-20221.00 Job1.00 Job0.974.56
2.Other Allied Works & Finishing Work 1.00 Job5.0227-08-202031-05-20221.00 Job1.00 Job1.075.02
3.Foundation RHS1.00 Job9.2615-09-202031-01-20211.00 Job1.00 Job1.979.26
4.Foundation LHS1.00 Job10.3615-09-202031-01-20211.00 Job1.00 Job2.2110.36
5.Abutment Superstructure RHS1.00 Job0.2204-05-202123-05-20221.00 Job1.00 Job0.050.22
6.Abutment Superstructure LHS1.00 Job0.2221-05-202223-05-20221.00 Job1.00 Job0.050.22
7.Fixing of chequered Plate/RCC Deck257.25 sqm20.5710-05-202221-05-2022257.25 sqm257.25 sqm4.3820.57
8.Steel Railing/crush barrier1.00 m6.2121-05-202228-05-20221.00 m1.00 m1.326.21
9.Approach Ramp /path 2.00 m43.6320-02-202220-05-20222.00 m2.00 m9.343.63
10.Protection Work1.00 Job11.7920-02-202220-05-20221.00 Job1.00 Job2.5111.79
11.Errection Work1.00 Job96.2815-10-202105-05-20221.00 Job1.00 Job20.5196.28
12.Fabrication Work1.00 job222.8215-04-202130-11-20211.00 job1.00 job47.47222.82
13.Abutment Substructure RHS1.00 Job19.2301-02-202130-04-20211.00 Job1.00 Job4.119.23
14.Abutment Substructure LHS1.00 Job19.2301-04-202130-06-20211.00 Job1.00 Job4.119.23
Total Amount: 469.4 100   469.4
Remarks: No Remarks       Work Program Made On: 14-10-2020        Updation of work program on: 06-05-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-December-20207.96  lakh
2.27-February-202128.46  lakh
3.04-September-202192.41  lakh
4.13-October-202152.35  lakh
5.02-November-202131.06  lakh
6.16-December-202141.25  lakh
7.14-March-202212.45  lakh
8.14-April-202289.86  lakh
9.30-April-202238.86  lakh
10.13-July-202235.65  lakh
11.17-August-202211.35  lakh
12.23-September-202220.27  lakh
13.21-October-20227.52  lakh
14.28-December-202224.92  lakh
Total 494.37  lakh
% Payment 98.82 %
Advance Amount:  17.33  lakh        Recovered Amount:  15.34  lakh        Balance to be Recovered  1.99  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): Land Owner Consent, Signs
Detailed report of this subproject
Quality
No. of Test Required : 261   No. of Test Done : 267    No. of Test Passed : 267   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.08
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 145
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic
2.23-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraGabion fillingRoop ` ` See Pic
3.23-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraCube moulding for RCC of pedestal at RHS abutmentRoop ` ` See Pic
4.23-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraRCC of pedestal at RHS abutmentRoop ` ` See Pic
5.23-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraRCC of pedestal at RHS abutmentRoop ` ` See Pic
6.21-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraLHS approach road RRM work in progressRoop ` ` See Pic
7.21-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic
8.19-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraLHS approach road RRM work in progresRoop ` ` See Pic
9.17-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraLHS approach road RRM work in progressRoop ` ` See Pic
10.17-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic
11.15-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraLHS approach road RRM workRoop ` ` See Pic
12.15-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraLHS approach road RRM work in progressRoop ` ` See Pic
13.09-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic
14.09-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraLHS approach road RRM work in progressRoop ` ` See Pic
15.08-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic
16.08-06-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraLHS approach road RRM work in progressRoop ` ` See Pic
17.27-05-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic
18.17-05-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening workRoop ` ` See Pic
19.12-05-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic
20.11-05-2022Pipna Manhaith Dangula Motor road at Km-7 in distt-AlmoraBolt tightening work in progressRoop ` ` See Pic