Bridge over Ramganga River on Gagas Udee Mahadev to Selapani Bhikiyasain Marchula MR at KM-37
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4133 |
Sanction Cost: |
830.16 lakh |
Span:
|
84.000 M |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 659
Package Name: 
UDRP/AF/BR/92
Tender Date: 02-12-2019
Current Status: Agreement signed
Achieved on Date: 10-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/92
Contractor Name: Gaurav Builder
|
Start Date: 02-10-2020
Intended Completion Date: 12-06-2023
Original End Date: 01-04-2022 |
Total Bond Cost: 83269832.13 (832.7 lakh)
Variation Cost: 3638853.62 (36.39 lakh) Hence Total Bond Cost is 86908685.75 (869.09 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 40760665 for 979 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 5.51 | 02-10-2020 | 20-10-2022 | 1.00 Job | 1.00 Job | 0.66 | 5.51 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 4.91 | 01-09-2021 | 20-10-2022 | 1.00 Job | 1.00 Job | 0.59 | 4.91 | 3. | Foundation RHS | 1.00 Job | 38.18 | 15-01-2021 | 05-01-2022 | 1.00 Job | 1.00 Job | 4.59 | 38.18 | 4. | Foundation LHS | 1.00 Job | 38.18 | 01-02-2021 | 25-10-2021 | 1.00 Job | 1.00 Job | 4.59 | 38.18 | 5. | Abutment Superstructure RHS | 1.00 Job | 0.12 | 01-07-2022 | 31-07-2022 | 1.00 Job | 1.00 Job | 0.01 | 0.12 | 6. | Abutment Superstructure LHS | 1.00 Job | 0.12 | 10-09-2022 | 15-09-2022 | 1.00 Job | 1.00 Job | 0.01 | 0.12 | 7. | Fixing of chequered Plate/RCC Deck | 462.00 sqm | 50.93 | 15-11-2022 | 15-12-2022 | 462.00 sqm | 462.00 sqm | 6.12 | 50.93 | 8. | Steel Railing/crush barrier | 135.00 m | 9.77 | 15-12-2022 | 30-12-2022 | 135.00 m | 135.00 m | 1.17 | 9.77 | 9. | Approach Ramp /path | 300.00 m | 53.64 | 15-12-2021 | 30-11-2022 | 300.00 m | 300.00 m | 6.44 | 53.64 | 10. | Protection Work | 1.00 Job | 16.07 | 01-12-2021 | 30-11-2022 | 1.00 Job | 1.00 Job | 1.93 | 16.07 | 11. | Errection Work | 1.00 Job | 141.28 | 16-09-2022 | 15-11-2022 | 1.00 Job | 1.00 Job | 16.97 | 141.28 | 12. | Fabrication Work | 1.00 job | 305.68 | 01-06-2022 | 15-09-2022 | 1.00 job | 1.00 job | 36.71 | 305.68 | 13. | Abutment Substructure RHS | 1.00 Job | 84.16 | 01-11-2021 | 30-06-2022 | 1.00 Job | 1.00 Job | 10.11 | 84.16 | 14. | Abutment Substructure LHS | 1.00 Job | 84.16 | 26-10-2021 | 10-09-2022 | 1.00 Job | 1.00 Job | 10.11 | 84.16 |
Total Amount: |
832.71 |
|
100 |
832.71 |
|
Remarks:
No Remarks
Work Program Made On:
16-10-2020 } ?>
Updation of work program on:
24-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2021 | 11.36 lakh | 2. | 30-October-2021 | 56.20 lakh | 3. | 16-February-2022 | 75.31 lakh | 4. | 31-May-2022 | 17.55 lakh | 5. | 21-October-2022 | 30.16 lakh | 6. | 27-December-2022 | 18.11 lakh | 7. | 28-January-2023 | 101.29 lakh | 8. | 31-January-2023 | 22.85 lakh | 9. | 04-March-2023 | 17.08 lakh | 10. | 13-March-2023 | 24.83 lakh |
Total |
374.74 lakh |
% Payment |
44.98 % |
|
Advance Amount: 205.21 lakh
Recovered Amount: 53.69 lakh
Balance to be Recovered 151.52 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
EMP Land Owner Consent |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 199 No. of Test Done : 199 No. of Test Passed : 199 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 56 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-06-2022 | A1 | Caution tape | Azhar (J.E) | ` | ` | See Pic |
2. | 03-06-2022 | A1 | Caution tape | Azhar | ` | ` | See Pic |
3. | 03-06-2022 | A1 | BR-92 | Azhar | ` | ` | See Pic |
4. | 03-06-2022 | A1 | BR-92 | Azhar | ` | ` | See Pic |
5. | 03-06-2022 | A1 | Reinforcement steel | Azhar | ` | ` | See Pic |
6. | 27-05-2022 | BR92 | Abutment LHS and RHS | Rajesh sharma | ` | ` | See Pic |
7. | 26-05-2022 | A2 | Reinforcement work | Azhar | ` | ` | See Pic |
8. | 26-05-2022 | A2 | A2 | Azhar | ` | ` | See Pic |
9. | 26-05-2022 | A1 | Reinforcement steel | Azhar | ` | ` | See Pic |
10. | 26-05-2022 | Km 37 | Abutment A-2 | Govind kumar | ` | ` | See Pic |
11. | 09-05-2022 | Bridge BR92 | Concrete pouring in progress for 2nd lift of RHS Abutment. | Rajesh sharma | ` | ` | See Pic |
12. | 09-05-2022 | BR-92 (84m span) | Pouring of 2nd lift of abutment A-2 | Govind kumar | ` | ` | See Pic |
13. | 31-01-2022 | BR-92 | A-2 | Govind kumar | ` | ` | See Pic |
14. | 31-01-2022 | BR-92 | A-2 1st lift | Govind kumar | ` | ` | See Pic |
15. | 17-12-2021 | Bridge BR92 | LHS abutment | Rajesh sharma | ` | ` | See Pic |
16. | 17-12-2021 | Bridge BR92 | RHS Abutment raft preparation in progress. | Rajesh sharma | ` | ` | See Pic |
17. | 17-12-2021 | Bridge BR92 | Information Board | Rajesh sharma | ` | ` | See Pic |
18. | 17-12-2021 | bridge package BR92 | Information board | Rajesh sharma | ` | ` | See Pic |
19. | 27-11-2021 | Km -37 BR-92 | Curing of abutment A-1 's 1st lift | Govind kumar ss | ` | ` | See Pic |
20. | 27-11-2021 | Km 36 BR 92 | Abutment A-1 | Govind kumar ss | ` | ` | See Pic |
|
|