Bridge over Jalkur River on Bagi Gaun Gajna Bridle Road
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4131 |
Sanction Cost: |
207.75 lakh |
Span:
|
42.000 M |
District: |
Uttarkashi |
Block: |
Dunda |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 657
Package Name: 
UDRP/AF/BR/90
Tender Date: 02-12-2019
Current Status: Agreement signed
Achieved on Date: 24-06-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/90
Contractor Name: M/s Harpal singh Kishore singh
|
Start Date: 04-08-2020
Intended Completion Date: 17-02-2022
Original End Date: 03-11-2021 |
Total Bond Cost: 20812945.6 (208.13 lakh)
Variation Cost: -555260.73 (-5.55 lakh) Hence Total Bond Cost is 20257684.87 (202.58 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 4797166 for 461 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 4.43 | 25-09-2021 | 17-01-2022 | 1.00 Job | 1.00 Job | 2.39 | 4.43 | 2. | Foundation RHS | 1.00 Job | 27.03 | 12-09-2020 | 07-11-2020 | 1.00 Job | 1.00 Job | 14.54 | 27.03 | 3. | Foundation LHS | 1.00 Job | 27.03 | 10-10-2020 | 15-11-2020 | 1.00 Job | 1.00 Job | 14.54 | 27.03 | 4. | Abutment Superstructure RHS | 1.00 Job | 11.27 | 12-11-2020 | 12-01-2022 | 1.00 Job | 1.00 Job | 6.06 | 11.27 | 5. | Abutment Superstructure LHS | 1.00 Job | 11.27 | 20-11-2020 | 10-03-2021 | 1.00 Job | 1.00 Job | 6.06 | 11.27 | 6. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 1.36 | 10-07-2021 | 17-01-2022 | 1.00 no | 1.00 no | 0.73 | 1.36 | 7. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 1.36 | 10-07-2021 | 05-08-2021 | 1.00 sqm | 1.00 sqm | 0.73 | 1.36 | 8. | Approach Ramp /path | 1.00 m | 17.52 | 28-07-2021 | 08-01-2022 | 1.00 m | 1.00 m | 9.43 | 17.52 | 9. | Protection Work | 1.00 Job | 14.41 | 28-07-2021 | 12-01-2022 | 1.00 Job | 1.00 Job | 7.75 | 14.41 | 10. | Errection Work | 1.00 Job | 12.91 | 03-05-2021 | 14-01-2022 | 1.00 Job | 1.00 Job | 6.95 | 12.91 | 11. | Fabrication Work | 1.00 job | 45.08 | 20-11-2020 | 13-01-2022 | 1.00 job | 1.00 job | 24.25 | 45.08 | 12. | Fixing Bearing/Slab Casting | 1.00 job | 12.22 | 20-04-2021 | 15-01-2022 | 1.00 job | 1.00 job | 6.57 | 12.22 |
Total Amount: |
185.89 |
|
100 |
185.89 |
|
Remarks:
No Remarks
Work Program Made On:
24-09-2020 } ?>
Updation of work program on:
24-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2021 | 25.98 lakh | 2. | 03-April-2021 | 18.01 lakh | 3. | 10-June-2021 | 18.17 lakh | 4. | 28-June-2021 | 7.77 lakh | 5. | 22-September-2021 | 4.65 lakh | 6. | 30-September-2021 | 37.04 lakh | 7. | 02-November-2021 | 12.46 lakh | 8. | 08-December-2021 | 5.87 lakh | 9. | 25-January-2022 | 9.36 lakh | 10. | 05-March-2022 | 20.94 lakh | 11. | 31-May-2022 | 42.31 lakh |
Total |
202.56 lakh |
% Payment |
100 % |
|
Advance Amount: 16.08 lakh
Recovered Amount: 16.08 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 350 No. of Test Done : 446 No. of Test Passed : 433 No. of Test Failed : 13 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.82 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 76 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-05-2022 | 42m span Bagigaon Gajna bridle bridge | Approach road A1 side | Ajay Singh Rana | ` | ` | See Pic |
2. | 06-05-2022 | Bagigaon Gajna 42m span steel truss bridge | Painting work completed | Ajay Singh Rana | ` | ` | See Pic |
3. | 22-01-2022 | Km1 | Erection work progress at bagigaon BR/90 | Deepak | ` | ` | See Pic |
4. | 13-11-2021 | Bagigaon km1 | Approach road progress A1 side bagigaon gajna bridle bridge BR/90 | Deepak | ` | ` | See Pic |
5. | 21-09-2021 | Baghi Gajna Bridge | Abutment L.H.S side Top Cap Casting worki is in Progress at baghi Gajna Bridge District Uttarkashi | Yogesh Dobhal | ` | ` | See Pic |
6. | 11-09-2021 | Bagigaon km1 | Abutment A1 side Cap casting Bagigaon gajna bridle bridge BR/90 | Deepak saini | ` | ` | See Pic |
7. | 04-09-2021 | Baaghi bridge ground erection at Fabrication yard situated at meerut | Ground erection of baaghi bridge is in progress at Fabrication yard situated at meerut. | Abhishek tiwari | ` | ` | See Pic |
8. | 04-09-2021 | Fabrication yard situated at meerut | Ground erection of baaghi bridge is in progress at Fabrication yard situated at meerut. | Abhishek tiwari | ` | ` | See Pic |
9. | 28-08-2021 | Km1 bagigaon gajna bridle bridge | Abutment A1 side 6th lift reinforcement checking Bagigaon gajna bridle bridge BR/90 | Deepak saini | ` | ` | See Pic |
10. | 18-08-2021 | Bagigaon gajna bridle bridge BR/90 | M/35 concrete casting for Abutment A2 side 6th lift | Deepak Saini | ` | ` | See Pic |
11. | 17-07-2021 | Bagi/BR/90 | A2,protection work layout work in progress. | Niraj pathak | unknown | unknown | See Pic |
12. | 07-07-2021 | Bagigaon Gajna Bridle Bridge | T.S. survey for Abutment Cap | Ajay Singh Rana | ` | ` | See Pic |
13. | 05-07-2021 | Bagi Bridge | T.s survey is in progress at 42 M span steel Truss Bridge Bagi Gajna Bridge Distt Uttarkashi | Yogesh Dobhal | unknown | unknown | See Pic |
14. | 07-06-2021 | Bagi Bridge | Abutment R.H.S Side Protection work In progress at 42 M Span Bagi Gajna Bridge Dist Uttarkashi | Yogesh Dobhal | unknown | unknown | See Pic |
15. | 07-06-2021 | Bagi Bridge | Abutment R.H.S side Vth Lift Shutting Work In Progress At Bagi Gajna Bridge | Yogesh Dobhal | unknown | unknown | See Pic |
16. | 07-06-2021 | Abutment A1 | Shuttering of 5th lift of abutment A1 Is in progress at baghi bridle bridge. | Abhishek tiwari | ` | ` | See Pic |
17. | 07-06-2021 | Abutment A1 | HP stone filling behind the abutment A1 is in progress at baghi bridge. | Abhishek tiwari | ` | ` | See Pic |
18. | 07-06-2021 | Abutment A2 | Protection work of gabions is in progress for abutment A2 | Abhishek tiwari | ` | ` | See Pic |
19. | 07-06-2021 | Abutment A1 | Shuttering of 5th lift of abutment A1 is in progress at baghi bridge in district Uttarkashi. | Abhishek tiwari | ` | ` | See Pic |
20. | 27-04-2021 | Km10 | Earthwork in excavation for Protection work Abutment R.H.S Side | Yogesh Dobhal | unknown | unknown | See Pic |
|
|