Suspension Bridge Between Village Tiwari Goan and Village Ghangreti over Kosi River
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4129 |
Sanction Cost: |
1357.63 lakh |
Span:
|
160.000 M |
District: |
Nainital |
Block: |
Betalghat |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA Nanital |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 653
Package Name: 
UDRP/AF/BR/86
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 06-10-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/86
Contractor Name: V. K. Gupta & Associates
|
Start Date: 13-11-2020
Intended Completion Date: 12-02-2023
Original End Date: 13-03-2022 |
Total Bond Cost: 138294240 (1382.94 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 31047003 for 449 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 22.64 | 10-09-2022 | 31-10-2022 | 1.00 Job | 0.00 Job | 0 | 0.00 | 2. | Group of Pile | 6.00 No | 82.76 | 01-02-2021 | 31-05-2021 | 1.00 No | 1.00 No | 8.08 | 82.76 | 3. | Foundation RHS | 1.00 Job | 82.76 | 10-03-2021 | 25-03-2021 | 1.00 Job | 1.00 Job | 8.08 | 82.76 | 4. | Foundation LHS | 1.00 Job | 82.76 | 15-03-2021 | 13-05-2021 | 1.00 Job | 1.00 Job | 8.08 | 82.76 | 5. | Steel Railing/crush barrier | 320.00 m | 9.86 | 01-08-2022 | 20-09-2022 | 320.00 m | 0.00 m | 0 | 0.00 | 6. | Approach Ramp /path | 200.00 m | 21.68 | 10-09-2022 | 10-10-2022 | 200.00 m | 0.00 m | 0 | 0.00 | 7. | Errection Work | 1.00 Job | 36.33 | 08-04-2022 | 06-07-2022 | 1.00 Job | 0.00 Job | 0 | 0.00 | 8. | Gabion work | 100.00 m | 65.48 | 10-09-2022 | 15-10-2022 | 100.00 m | 0.00 m | 0 | 0.00 | 9. | Fabrication Work | 1.00 job | 123.84 | 07-02-2022 | 07-04-2022 | 1.00 job | 0.00 job | 0 | 0.00 | 10. | Abutment Substructure RHS | 1.00 Job | 210.34 | 10-03-2021 | 25-03-2021 | 1.00 Job | 1.00 Job | 20.53 | 210.34 | 11. | Abutment Substructure LHS | 1.00 Job | 210.34 | 15-03-2021 | 13-05-2021 | 1.00 Job | 1.00 Job | 20.53 | 210.34 | 12. | Back Wall/ Approach slab | 1.00 job | 75.68 | 20-02-2022 | 19-07-2022 | 1.00 job | 0.00 job | 0 | 0.00 | 13. | Admin Block | 0.00 Job | 0.00 | 01-02-2021 | 31-05-2021 | 0.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
1024.47 |
|
65.3 |
668.96 |
|
Remarks:
No Remarks
Work Program Made On:
25-03-2021 } ?>
Updation of work program on:
28-01-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2021 | 79.93 lakh | 2. | 31-May-2021 | 249.79 lakh | 3. | 25-September-2021 | 59.36 lakh | 4. | 29-November-2021 | 239.02 lakh | 5. | 12-January-2022 | 94.04 lakh | 6. | 21-March-2022 | 239.02 lakh | 7. | 17-May-2022 | 23.90 lakh | 8. | 27-June-2022 | 52.90 lakh | 9. | 25-July-2022 | 14.11 lakh | 10. | 22-September-2022 | 27.66 lakh | 11. | 07-October-2022 | 27.66 lakh | 12. | 26-November-2022 | 52.90 lakh | 13. | 22-December-2022 | 5.80 lakh | 14. | 27-January-2023 | 74.31 lakh | 15. | 25-February-2023 | 51.00 lakh | 16. | 17-April-2023 | 51.00 lakh | 17. | 12-May-2023 | 45.96 lakh |
Total |
1388.36 lakh |
% Payment |
100.39 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 866 No. of Test Done : 903 No. of Test Passed : 867 No. of Test Failed : 36 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.70 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 240 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-06-2022 | Tiwari gaon Betalghat Nainital | Curing work is in progress for A1 Abutment side approach road Footing & Column | Surendra Singh | ` | ` | See Pic |
2. | 20-06-2022 | Tiwari Goan | Column steel fixing is in progress for approach road work | Shivam | ` | ` | See Pic |
3. | 07-06-2022 | Tiwari gaon Betalghat Nainital | A1 Abutment side approach road F5,F6 & F7 Footing Reinforcement Fixing work | Surendra Singh Bisht | ` | ` | See Pic |
4. | 07-06-2022 | Ghiroli Betalghat Nainital | Crash Barrier shuttering fixing is in progress | Surendra Singh Bisht | ` | ` | See Pic |
5. | 03-06-2022 | Tiwari gaon Betalghat Nainital | Curing work is in progress for A1 Abutment side approach road Footing & Column | Surendra Singh Bisht | ` | ` | See Pic |
6. | 03-06-2022 | Tiwari gaon Betalghat Nainital | Curing work is in progress for A1 Abutment side approach road Footing & Column | Surendra Singh | ` | ` | See Pic |
7. | 03-06-2022 | Tiwari gaon Betalghat Nainital | Curing work is in progress for A1 Abutment side approach road Footing & Column | Surendra Singh | ` | ` | See Pic |
8. | 03-06-2022 | Tiwari gaon | Curing work is in progress for approach road RCC work A-1 side | Shivam | ` | ` | See Pic |
9. | 28-05-2022 | Tiwari gaon Betalghat Nainital | Cube casting for A1 Abutment side approach road Footing concreting work | Surendra Singh Bisht | ` | ` | See Pic |
10. | 28-05-2022 | Tiwari gaon Betalghat Nainital | A1 Abutment side approach road F1,F2 & F3 Footing concreting work done | Surendra Singh Bisht | ` | ` | See Pic |
11. | 28-05-2022 | Tiwari gaon Betalghat Nainital | A1 Abutment side approach road Footing concreting work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
12. | 28-05-2022 | Tiwari gaon Betalghat Nainital | A1 Abutment side approach road Footing concreting work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
13. | 27-05-2022 | Tiwari gaon Betalghat Nainital | A1 Abutment side approach road Footing concreting work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
14. | 26-05-2022 | Tiwari gaon Betalghat Nainital | A1 Abutment side approach road Steel fixing for F1 ,F2 & F3 footing reinforcement checked and found ok | Surendra Singh Bisht | ` | ` | See Pic |
15. | 26-05-2022 | Tiwari gaon Betalghat Nainital. | A1 Abutment side Approach Road Steel Checked for F1 ,F2 & F3 footing | Surendra Singh Bisht | ` | ` | See Pic |
16. | 26-05-2022 | Tiwari gaon Betalghat Nainital | A1Abutment Side Approach Road Footing steel Fixing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
17. | 26-05-2022 | Tiwari gaon Betalghat Nainital | A1Abutment Side Approach Road Footing steel Fixing work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
18. | 21-05-2022 | Tiwari gaon Betalghat Nainital | A1 Side Approach Road footing Excavation work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
19. | 20-05-2022 | Tiwari gaon Betalghat Nainital | VT Column Erection work is in progress | Surendra Singh Bisht | ` | ` | See Pic |
20. | 20-05-2022 | Tiwari gaon Betalghat Nainital | Site visit with EE sir, AE Sir, & DSC RE sir | Surendra Singh Bisht | ` | ` | See Pic |
|
|