Suspension Bridge at Bhatkot (near Bhatkot Jhala Village)
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4128 |
Sanction Cost: |
1171.03 lakh |
Span:
|
125.000 M |
District: |
Almora |
Block: |
Chaukhutiya |
Constituency: |
Dwarahat |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 646
Package Name: 
UDRP/AF/BR/88
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 02-12-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/88
Contractor Name: V. K. Gupta & Associates
|
Start Date: 13-12-2020
Intended Completion Date: 28-02-2023
Original End Date: 31-03-2022 |
Total Bond Cost: 119142240 (1191.42 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 31632201 for 531 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 15.79 | 15-04-2021 | 17-09-2022 | 1.00 Job | 1.00 Job | 1.33 | 15.79 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 33.36 | 13-12-2020 | 17-09-2022 | 1.00 Job | 1.00 Job | 2.8 | 33.36 | 3. | Foundation RHS | 1.00 Job | 122.12 | 15-04-2021 | 09-07-2021 | 1.00 Job | 1.00 Job | 10.25 | 122.12 | 4. | Foundation LHS | 1.00 Job | 122.12 | 15-04-2021 | 09-07-2021 | 1.00 Job | 1.00 Job | 10.25 | 122.12 | 5. | Abutment Superstructure RHS | 1.00 Job | 15.12 | 16-11-2021 | 15-12-2021 | 1.00 Job | 1.00 Job | 1.27 | 15.12 | 6. | Abutment Superstructure LHS | 1.00 Job | 15.12 | 11-10-2021 | 31-10-2021 | 1.00 Job | 1.00 Job | 1.27 | 15.12 | 7. | Fixing of chequered Plate/RCC Deck | 125.00 sqm | 33.60 | 16-07-2022 | 15-08-2022 | 125.00 sqm | 125.00 sqm | 2.82 | 33.60 | 8. | Steel Railing/crush barrier | 250.00 m | 33.26 | 16-08-2022 | 31-08-2022 | 250.00 m | 250.00 m | 2.79 | 33.26 | 9. | Approach Ramp /path | 250.00 m | 131.04 | 01-04-2022 | 15-08-2022 | 250.00 m | 250.00 m | 11 | 131.04 | 10. | Errection Work | 1.00 Job | 131.82 | 01-06-2022 | 15-07-2022 | 1.00 Job | 1.00 Job | 11.06 | 131.82 | 11. | Fabrication Work | 1.00 job | 98.28 | 01-05-2022 | 31-05-2022 | 1.00 job | 1.00 job | 8.25 | 98.28 | 12. | Abutment Substructure RHS | 1.00 Job | 102.11 | 01-07-2021 | 15-11-2021 | 1.00 Job | 1.00 Job | 8.57 | 102.11 | 13. | Abutment Substructure LHS | 1.00 Job | 102.11 | 01-07-2021 | 10-10-2021 | 1.00 Job | 1.00 Job | 8.57 | 102.11 | 14. | Well-Abutments/Pier/Shafts/Caps | 1.00 job | 235.56 | 10-10-2021 | 31-05-2022 | 1.00 job | 1.00 job | 19.77 | 235.56 |
Total Amount: |
1191.41 |
|
100 |
1191.41 |
|
Remarks:
No Remarks
Work Program Made On:
16-03-2021 } ?>
Updation of work program on:
23-04-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-May-2021 | 62.89 lakh | 2. | 30-June-2021 | 208.36 lakh | 3. | 30-September-2021 | 28.90 lakh | 4. | 22-February-2022 | 146.79 lakh | 5. | 16-April-2022 | 24.22 lakh | 6. | 11-May-2022 | 78.61 lakh | 7. | 31-May-2022 | 150.71 lakh | 8. | 15-June-2022 | 79.13 lakh | 9. | 13-July-2022 | 7.84 lakh | 10. | 03-August-2022 | 79.13 lakh | 11. | 23-September-2022 | 48.55 lakh | 12. | 05-November-2022 | 39.57 lakh | 13. | 27-December-2022 | 98.60 lakh | 14. | 24-February-2023 | 112.25 lakh |
Total |
1165.55 lakh |
% Payment |
97.83 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 479 No. of Test Done : 479 No. of Test Passed : 479 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 201 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-06-2022 | BR88, bhatkot jhala | A2 approach 7no. Column footing pouring of concrete . | Suresh chandra sharma | ` | ` | See Pic |
2. | 21-06-2022 | BR 88 BHATKOT | Labour law rights camp | SS Desh Deepak | unknown | unknown | See Pic |
3. | 21-06-2022 | BR 88 BHATKOT | Labour law rights camp | SS Desh Deepak | unknown | unknown | See Pic |
4. | 21-06-2022 | BR 88 BHATKOT | Gender sanitation camp | SS Desh Deepak | unknown | unknown | See Pic |
5. | 21-06-2022 | BR 88 BHATKOT | Safety training camp | SS Desh Deepak | unknown | unknown | See Pic |
6. | 21-06-2022 | BR 88 BHATKOT | Health camp | SS Desh Deepak | unknown | unknown | See Pic |
7. | 21-06-2022 | BR 88 BHATKOT | Health camp | SS Desh Deepak | unknown | unknown | See Pic |
8. | 13-06-2022 | Bhatkot jhala | Unloading of super structure steel member | Suresh chandra sharma | ` | ` | See Pic |
9. | 26-05-2022 | BR 88 BHATKOT | Super structure steel arrive at site | SS Desh Deepak | unknown | unknown | See Pic |
10. | 26-05-2022 | BR 88 BHATKOT | Super structure steel | SS Desh Deepak | unknown | unknown | See Pic |
11. | 26-05-2022 | BR 88 BHATKOT | 19MT super structure steel reach at site | SS Desh Deepak | unknown | unknown | See Pic |
12. | 26-05-2022 | BR 88 BHATKOT | Super structure steel 19 MT Reach at site | SS Desh Deepak | unknown | unknown | See Pic |
13. | 21-05-2022 | BR 88 BHATKOT | Pier 2nd lift pouring of concrete | SS Desh Deepak | unknown | unknown | See Pic |
14. | 21-05-2022 | BR 88 BHATKOT | Pier 2nd lift pouring of concrete is completed | SS Desh Deepak | unknown | unknown | See Pic |
15. | 10-05-2022 | BR 88 BHATKOT | Pile cap pouring of concrete is completed | SS Desh Deepak | unknown | unknown | See Pic |
16. | 10-05-2022 | BR 88 BHATKOT | Pile cap pouring of concrete is completed. | SS Desh Deepak | unknown | unknown | See Pic |
17. | 10-05-2022 | BR 88 BHATKOT | Pile cap pouring of concrete is completed | SS Desh Deepak | unknown | unknown | See Pic |
18. | 10-05-2022 | BR 88 BHATKOT | Pile cap surface finishing is in progress | SS Desh Deepak | unknown | unknown | See Pic |
19. | 10-05-2022 | BR 88 BHATKOT | Pile cap surface finishing work is in progress | SS Desh Deepak | unknown | unknown | See Pic |
20. | 10-05-2022 | BR 88 BHATKOT | Pile cap pouring of concrete is in progress | SS Desh Deepak | unknown | unknown | See Pic |
|
|