Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Suspension Bridge at Bhatkot (near Bhatkot Jhala Village) Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4128 Sanction Cost: 1171.03  lakh Span: 125.000 M
District: Almora Block: Chaukhutiya Constituency: Dwarahat Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 646        Package Name:  UDRP/AF/BR/88        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 02-12-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/88      Contractor Name: V. K. Gupta & Associates
Start Date:  13-12-2020      Intended Completion Date:  28-02-2023      Original End Date:  31-03-2022
Total Bond Cost: 119142240 (1191.42 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 31632201 for 531 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job15.7915-04-202117-09-20221.00 Job1.00 Job1.3315.79
2.Other Allied Works & Finishing Work 1.00 Job33.3613-12-202017-09-20221.00 Job1.00 Job2.833.36
3.Foundation RHS1.00 Job122.1215-04-202109-07-20211.00 Job1.00 Job10.25122.12
4.Foundation LHS1.00 Job122.1215-04-202109-07-20211.00 Job1.00 Job10.25122.12
5.Abutment Superstructure RHS1.00 Job15.1216-11-202115-12-20211.00 Job1.00 Job1.2715.12
6.Abutment Superstructure LHS1.00 Job15.1211-10-202131-10-20211.00 Job1.00 Job1.2715.12
7.Fixing of chequered Plate/RCC Deck125.00 sqm33.6016-07-202215-08-2022125.00 sqm125.00 sqm2.8233.60
8.Steel Railing/crush barrier250.00 m33.2616-08-202231-08-2022250.00 m250.00 m2.7933.26
9.Approach Ramp /path 250.00 m131.0401-04-202215-08-2022250.00 m250.00 m11131.04
10.Errection Work1.00 Job131.8201-06-202215-07-20221.00 Job1.00 Job11.06131.82
11.Fabrication Work1.00 job98.2801-05-202231-05-20221.00 job1.00 job8.2598.28
12.Abutment Substructure RHS1.00 Job102.1101-07-202115-11-20211.00 Job1.00 Job8.57102.11
13.Abutment Substructure LHS1.00 Job102.1101-07-202110-10-20211.00 Job1.00 Job8.57102.11
14.Well-Abutments/Pier/Shafts/Caps1.00 job235.5610-10-202131-05-20221.00 job1.00 job19.77235.56
Total Amount: 1191.41 100   1191.41
Remarks: No Remarks       Work Program Made On: 16-03-2021        Updation of work program on: 23-04-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-May-202162.89  lakh
2.30-June-2021208.36  lakh
3.30-September-202128.90  lakh
4.22-February-2022146.79  lakh
5.16-April-202224.22  lakh
6.11-May-202278.61  lakh
7.31-May-2022150.71  lakh
8.15-June-202279.13  lakh
9.13-July-20227.84  lakh
10.03-August-202279.13  lakh
11.23-September-202248.55  lakh
12.05-November-202239.57  lakh
13.27-December-202298.60  lakh
14.24-February-2023112.25  lakh
Total 1165.55  lakh
% Payment 97.83 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 479   No. of Test Done : 479    No. of Test Passed : 479   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 201
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-06-2022BR88, bhatkot jhalaA2 approach 7no. Column footing pouring of concrete .Suresh chandra sharma ` ` See Pic
2.21-06-2022BR 88 BHATKOTLabour law rights campSS Desh Deepakunknownunknown See Pic
3.21-06-2022BR 88 BHATKOTLabour law rights campSS Desh Deepakunknownunknown See Pic
4.21-06-2022BR 88 BHATKOTGender sanitation campSS Desh Deepakunknownunknown See Pic
5.21-06-2022BR 88 BHATKOTSafety training campSS Desh Deepakunknownunknown See Pic
6.21-06-2022BR 88 BHATKOTHealth campSS Desh Deepakunknownunknown See Pic
7.21-06-2022BR 88 BHATKOTHealth campSS Desh Deepakunknownunknown See Pic
8.13-06-2022Bhatkot jhalaUnloading of super structure steel memberSuresh chandra sharma ` ` See Pic
9.26-05-2022BR 88 BHATKOTSuper structure steel arrive at siteSS Desh Deepakunknownunknown See Pic
10.26-05-2022BR 88 BHATKOTSuper structure steelSS Desh Deepakunknownunknown See Pic
11.26-05-2022BR 88 BHATKOT19MT super structure steel reach at siteSS Desh Deepakunknownunknown See Pic
12.26-05-2022BR 88 BHATKOTSuper structure steel 19 MT Reach at siteSS Desh Deepakunknownunknown See Pic
13.21-05-2022BR 88 BHATKOTPier 2nd lift pouring of concreteSS Desh Deepakunknownunknown See Pic
14.21-05-2022BR 88 BHATKOTPier 2nd lift pouring of concrete is completedSS Desh Deepakunknownunknown See Pic
15.10-05-2022BR 88 BHATKOTPile cap pouring of concrete is completedSS Desh Deepakunknownunknown See Pic
16.10-05-2022BR 88 BHATKOTPile cap pouring of concrete is completed.SS Desh Deepakunknownunknown See Pic
17.10-05-2022BR 88 BHATKOTPile cap pouring of concrete is completedSS Desh Deepakunknownunknown See Pic
18.10-05-2022BR 88 BHATKOTPile cap surface finishing is in progressSS Desh Deepakunknownunknown See Pic
19.10-05-2022BR 88 BHATKOTPile cap surface finishing work is in progressSS Desh Deepakunknownunknown See Pic
20.10-05-2022BR 88 BHATKOTPile cap pouring of concrete is in progressSS Desh Deepakunknownunknown See Pic