Suspension Bridge at Tadagtaal near Dhanan
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4127 |
Sanction Cost: |
1170.28 lakh |
Span:
|
125.000 M |
District: |
Almora |
Block: |
Chaukhutiya |
Constituency: |
Dwarahat |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 654
Package Name: 
UDRP/AF/BR/87
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 10-12-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/87
Contractor Name: V. K. Gupta & Associates
|
Start Date: 19-12-2020
Intended Completion Date: 28-02-2023
Original End Date: 31-03-2022 |
Total Bond Cost: 119108640 (1191.09 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 25846436 for 434 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 38.14 | 10-10-2021 | 31-12-2022 | 1.00 Job | 1.00 Job | 3.2 | 38.14 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 19.05 | 01-09-2021 | 31-12-2022 | 1.00 Job | 1.00 Job | 1.6 | 19.05 | 3. | Foundation RHS | 1.00 Job | 61.40 | 29-01-2021 | 29-05-2021 | 1.00 Job | 1.00 Job | 5.16 | 61.40 | 4. | Foundation LHS | 1.00 Job | 61.40 | 29-01-2021 | 29-05-2021 | 1.00 Job | 1.00 Job | 5.16 | 61.40 | 5. | Abutment Superstructure RHS | 1.00 Job | 7.50 | 16-12-2021 | 31-03-2022 | 1.00 Job | 1.00 Job | 0.63 | 7.50 | 6. | Abutment Superstructure LHS | 1.00 Job | 7.50 | 16-12-2021 | 30-04-2022 | 1.00 Job | 1.00 Job | 0.63 | 7.50 | 7. | Fixing of chequered Plate/RCC Deck | 250.00 sqm | 30.00 | 05-05-2022 | 30-11-2022 | 250.00 sqm | 250.00 sqm | 2.52 | 30.00 | 8. | Steel Railing/crush barrier | 340.00 m | 38.13 | 01-06-2022 | 31-12-2022 | 340.00 m | 340.00 m | 3.2 | 38.13 | 9. | Approach Ramp /path | 140.00 m | 59.54 | 01-01-2022 | 31-12-2022 | 140.00 m | 140.00 m | 5 | 59.54 | 10. | Protection Work | 1.00 Job | 59.54 | 01-10-2022 | 31-12-2022 | 1.00 Job | 0.00 Job | 0 | 0.00 | 11. | Errection Work | 1.00 Job | 139.28 | 01-01-2022 | 15-02-2022 | 1.00 Job | 0.00 Job | 0 | 0.00 | 12. | Fabrication Work | 1.00 job | 84.64 | 15-10-2021 | 31-12-2021 | 1.00 job | 0.00 job | 0 | 0.00 | 13. | Abutment Substructure RHS | 1.00 Job | 113.02 | 01-06-2021 | 31-07-2021 | 1.00 Job | 1.00 Job | 9.49 | 113.02 | 14. | Abutment Substructure LHS | 1.00 Job | 113.02 | 01-06-2021 | 15-09-2021 | 1.00 Job | 1.00 Job | 9.49 | 113.02 | 15. | Well-Abutments/Pier/Shafts/Caps | 2.00 job | 358.93 | 10-11-2021 | 15-02-2022 | 2.00 job | 2.00 job | 30.14 | 358.93 |
Total Amount: |
1191.09 |
|
76.2 |
907.63 |
|
Remarks:
No Remarks
Work Program Made On:
09-03-2021 } ?>
Updation of work program on:
22-12-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-March-2021 | 103.77 lakh | 2. | 20-May-2021 | 78.53 lakh | 3. | 15-July-2021 | 137.36 lakh | 4. | 30-September-2021 | 20.55 lakh | 5. | 18-December-2021 | 56.97 lakh | 6. | 30-December-2021 | 58.80 lakh | 7. | 16-February-2022 | 123.00 lakh | 8. | 22-February-2022 | 118.52 lakh | 9. | 27-May-2022 | 34.26 lakh | 10. | 03-August-2022 | 50.79 lakh | 11. | 26-August-2022 | 101.58 lakh | 12. | 21-October-2022 | 78.38 lakh | 13. | 21-December-2022 | 27.54 lakh | 14. | 27-December-2022 | 47.64 lakh | 15. | 31-January-2023 | 99.40 lakh | 16. | 28-February-2023 | 45.60 lakh |
Total |
1182.69 lakh |
% Payment |
99.3 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 522 No. of Test Done : 527 No. of Test Passed : 523 No. of Test Failed : 4 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 131 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-06-2022 | Tadagtaal | Curing work of coloum a2 side approach road in progress at 125 mtr span bridge at tadagtaal | Sumit Bisht (ss) | unknown | unknown | See Pic |
2. | 02-06-2022 | Bridge BR87 | RHS approach in progress. | Rajesh sharma | ` | ` | See Pic |
3. | 02-06-2022 | Bridge BR87 | LHS approach in progress. | Rajesh sharma | ` | ` | See Pic |
4. | 26-05-2022 | Tadagtaal (BR-87) | Abutment A1 side RR wall masonry work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
5. | 25-05-2022 | Tadagtaal | Approach (a2)side column 1St lift casting at 125 mtr span bridge at tadagtaal | Sumit Bisht (ss) | unknown | unknown | See Pic |
6. | 24-05-2022 | Tadagtaal (BR-87) | Abutment A1 side RR wall masonry work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
7. | 24-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C1 & C2 1st lift casting. | Lalit Kumar (SS) | ` | ` | See Pic |
8. | 24-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C1 & C2 1st lift casting. | Lalit Kumar (SS) | ` | ` | See Pic |
9. | 20-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C3 column raft casting. | Lalit Kumar (SS) | ` | ` | See Pic |
10. | 20-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C3 column raft casting. | Lalit Kumar (SS) | ` | ` | See Pic |
11. | 19-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C3 column raft shuttering work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
12. | 19-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C3 column raft shuttering work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
13. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C2 raft casted cubes. | Lalit Kumar (SS) | ` | ` | See Pic |
14. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C2 raft casting. | Lalit Kumar (SS) | ` | ` | See Pic |
15. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C2 raft casting. | Lalit Kumar (SS) | ` | ` | See Pic |
16. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C1 raft casted cubes. | Lalit Kumar (SS) | ` | ` | See Pic |
17. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C1 raft casting. | Lalit Kumar (SS) | ` | ` | See Pic |
18. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C1 & C2 reinforcement and shuttering. | Lalit Kumar (SS) | ` | ` | See Pic |
19. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C1 & C2 raft reinforcement and shuttering. | Lalit Kumar (SS) | ` | ` | See Pic |
20. | 17-05-2022 | Tadagtaal (BR-87) | Abutment A2 side C1 raft cube casting work in progress. | Lalit Kumar (SS) | ` | ` | See Pic |
|
|