Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Suspension Bridge at Tadagtaal near Dhanan Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4127 Sanction Cost: 1170.28  lakh Span: 125.000 M
District: Almora Block: Chaukhutiya Constituency: Dwarahat Circle:
DEA: DEA Bageshwar DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 654        Package Name:  UDRP/AF/BR/87        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 10-12-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/87      Contractor Name: V. K. Gupta & Associates
Start Date:  19-12-2020      Intended Completion Date:  31-03-2022     
Total Bond Cost: 119108640 (1191.09 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 24059816 for 404 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job38.1410-10-202131-03-20221.00 Job0.00 Job00.00
2.Other Allied Works & Finishing Work 1.00 Job19.0501-09-202131-03-20221.00 Job0.00 Job00.00
3.Foundation RHS1.00 Job61.4029-01-202129-05-20211.00 Job1.00 Job5.1661.40
4.Foundation LHS1.00 Job61.4029-01-202129-05-20211.00 Job1.00 Job5.1661.40
5.Abutment Superstructure RHS1.00 Job7.5016-12-202131-12-20211.00 Job0.00 Job00.00
6.Abutment Superstructure LHS1.00 Job7.5016-12-202131-12-20211.00 Job0.00 Job00.00
7.Fixing of chequered Plate/RCC Deck1.00 sqm30.0016-02-202228-02-20221.00 sqm0.00 sqm00.00
8.Steel Railing/crush barrier250.00 m38.1301-03-202215-03-2022250.00 m0.00 m00.00
9.Approach Ramp /path 140.00 m59.5401-01-202231-03-2022140.00 m0.00 m00.00
10.Protection Work1.00 Job59.5401-01-202215-03-20221.00 Job0.00 Job00.00
11.Errection Work1.00 Job139.2801-01-202215-02-20221.00 Job0.00 Job00.00
12.Fabrication Work1.00 job84.6415-10-202131-12-20211.00 job0.00 job00.00
13.Abutment Substructure RHS1.00 Job113.0201-06-202131-07-20211.00 Job1.00 Job9.49113.02
14.Abutment Substructure LHS1.00 Job113.0201-06-202115-09-20211.00 Job1.00 Job9.49113.02
15.Well-Abutments/Pier/Shafts/Caps2.00 job358.9310-10-202115-12-20212.00 job0.00 job00.00
Total Amount: 1191.09 29.29   348.84
Remarks: No Remarks       Work Program Made On: 09-03-2021        Updation of work program on: 27-09-2021       
Work Program Status:Program Failed
Financial Progress
SNo. Date Payment
1.22-March-2021103.77  lakh
2.20-May-202178.53  lakh
3.15-July-2021137.36  lakh
4.30-September-202120.55  lakh
5.18-December-202156.97  lakh
6.30-December-202158.80  lakh
Total 455.98  lakh
% Payment 38.28 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): No Pending Issue
Environment & Social Compliances(Sub Project level): EMP
Detailed report of this subproject
Quality
No. of Test Required : 266   No. of Test Done : 271    No. of Test Passed : 267   No. of Test Failed : 4   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 92
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-01-2022TadagtaalCube mould casting of 3 rd lift pier p1 at BR-87Gaurav Airi ` ` See Pic
2.10-01-2022TadagtaalPouring of concrete 3 rd lift pier p1Gaurav Airi ` ` See Pic
3.10-01-2022TadagtaalPouring of concrete 3 rd lift P1 pier at BR-87Gaurav Airi ` ` See Pic
4.10-01-2022TadagtaalPouring of concrete 3rd lift at BR-87 tadagtaalGaurav Airi ` ` See Pic
5.30-12-2021BR-87 TadagtaalSlump cone test of pier p2 raft at BR-87Gaurav Airi ` ` See Pic
6.30-12-2021BR-87TadagtaalCube mould casting for pier p2 raft at BR-87 tadagtaalGaurav Airi ` ` See Pic
7.30-12-2021TadagtaalCube mould casting for pier p2 raft at BR-87Gaurav Airi ` ` See Pic
8.30-12-2021TadagtaalPouring of M35 grade concrete of pier p2 raft at BR-87 tadagtaalGaurav Airi ` ` See Pic
9.30-12-2021TadagtaalPouring of M35 grade concrete for pier p2 raft at BR-87 tadagtaalGaurav Airi ` ` See Pic
10.28-12-2021TadagtaalPouring of M35 grade concrete for P2 raftGaurav Airi ` ` See Pic
11.17-12-2021Bridge BR87Pier P1Rajesh sharma ` ` See Pic
12.17-12-2021Bridge BR87Excavation for P2 in progressRajesh sharma ` ` See Pic
13.16-12-2021TadagtaalDewatering and excavation work in progress of pier p2 at BR-87Gaurav Airi ` ` See Pic
14.06-12-2021Tadagtaal BR-87Cube mould casting for pier p1 raftGaurav Airi ` ` See Pic
15.06-12-2021Tadagtaal BR-87Cube mould casting of pier P1 raftGaurav Airi ` ` See Pic
16.06-12-2021TadagtaalConcreting of pier p1 raft at BR-87Gaurav Airi ` ` See Pic
17.06-12-2021TadagtaalConcreting of pier P1 raft at BR-87Gaurav Airi ` ` See Pic
18.06-12-2021TadagtaalConcreting of pier P1 raft at BR-87Gaurav Airi ` ` See Pic
19.01-12-2021TadagtaalReinforcement work in progress of pier P1 raft at BR-87Gaurav Airi ` ` See Pic
20.01-12-2021TadagtaalReinforcement work in progress of pier P1 raft at BR-87Gaurav Airi ` ` See Pic