Steel Truss Motor Bridge over Kamal River on Netri Chandeli MR at KM-3 Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4122 Sanction Cost: 565.56  lakh Span: 48.000 M
District: Uttarkashi Block: Puraula Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 647        Package Name:  UDRP/AF/BR/80        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 04-08-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/80      Contractor Name: Tons Builderes
Start Date:  21-08-2020      Intended Completion Date:  20-02-2022      Original End Date:  14-07-2021
Total Bond Cost: 55121698.15 (551.22 lakh)        Variation Cost: 5410941.57 (54.11 lakh)    Hence Total Bond Cost is   60532639.72 (605.33 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11630742 for 422 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job27.3501-07-202119-02-20221.00 Job1.00 Job5.3627.35
2.Foundation RHS1.00 Job25.0730-09-202031-12-20201.00 Job1.00 Job4.9125.07
3.Foundation LHS1.00 Job25.0730-10-202013-03-20211.00 Job1.00 Job4.9125.07
4.Abutment Superstructure RHS1.00 Job46.9630-11-202025-03-20211.00 Job1.00 Job9.246.96
5.Abutment Superstructure LHS1.00 Job46.9630-12-202028-04-20211.00 Job1.00 Job9.246.96
6.Fixing of chequered Plate/RCC Deck1.00 sqm18.2615-08-202115-10-20211.00 sqm1.00 sqm3.5818.26
7.Steel Railing/crush barrier1.00 m6.0915-12-202119-12-20211.00 m1.00 m1.196.09
8.Approach Ramp /path 1.00 m35.0815-01-202130-10-20211.00 m1.00 m6.8735.08
9.Protection Work1.00 Job19.6102-01-202130-08-20211.00 Job1.00 Job3.8419.61
10.Errection Work1.00 Job52.6215-09-202115-11-20211.00 Job1.00 Job10.3152.62
11.Fabrication Work1.00 job185.7915-11-202027-05-20211.00 job1.00 job36.4185.79
12.Fixing Bearing/Slab Casting1.00 job21.5515-04-202115-12-20211.00 job1.00 job4.2221.55
Total Amount: 510.41 100   510.41
Remarks: No Remarks       Work Program Made On: 06-11-2020        Updation of work program on: 24-05-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.19-March-202193.41  lakh
2.30-March-202158.82  lakh
3.22-July-202136.48  lakh
4.07-September-202181.71  lakh
5.06-November-2021131.95  lakh
6.26-November-202144.68  lakh
7.07-January-202253.79  lakh
8.24-February-202293.63  lakh
9.31-March-202240.16  lakh
10.26-August-202239.68  lakh
Total 674.31  lakh
% Payment 111.41 %
Advance Amount:  48.50  lakh        Recovered Amount:  48.50  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 799   No. of Test Done : 895    No. of Test Passed : 879   No. of Test Failed : 16   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.41
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 164
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-05-2022BR 80 netri chandeliBridge work has been completedManoj sain QC ` ` See Pic
2.13-05-2022BR 80 netri chandeliBridge work has been completedManoj sain QC ` ` See Pic
3.18-02-2022Netri-chandeli motor bridgePainting work is in progress at netri-chandeli motor bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic
4.18-02-2022Netri-chandeli motor bridgeShuttering of deck slab is in progress at netri-chandeli motor bridge in district UttarkashiAbhishek tiwari ` ` See Pic
5.30-01-2022Netri Chandeli BR80Netri Chandeli BR80Sandeep kumarunknownunknown See Pic
6.30-01-2022Netri Chandeli BR80BR80 Netri Chandeli (Bolt Torquing in progress)Sandeep kumarunknownunknown See Pic
7.30-01-2022BR80 NETRI CHANDELINetri Chandeli BR80 Labour training camp.Sandeep kumarunknownunknown See Pic
8.30-01-2022BR80 NETRI CHANDELIBR80 Netri Chandeli Labour training caomp.Sandeep kumarunknownunknown See Pic
9.30-01-2022Netri chamdeli BR80BR80 Labour TrainingSandeep kumarunknownunknown See Pic
10.18-01-2022Erection of netri-chandeli motor bridge is in progress at site of district Uttarkashi.Erection of netri-chandeli motor bridge is in progress at site of district Uttarkashi.Abhishek tiwari ` ` See Pic
11.18-01-2022Netri-chandeli motor bridgeRR 1:5 work completed for approach road at A1 side .Abhishek tiwari ` ` See Pic
12.18-01-2022Netri-chandeli motor bridgeErection of bridge is in progress at netri-chandeli motor bridge in district Uttarkashi.Abhishek tiwari ` ` See Pic
13.18-01-2022Netri-chandeli motor bridgeErection of top members is in progress at netri-chandeli motor bridge in district UttarkashiAbhishek tiwari ` ` See Pic
14.17-01-2022BR 80 netri chandeliEraction work is in ProgressManoj sain QC ` ` See Pic
15.10-01-2022BR 80 Netri chandeliEraction Work stopped due to rainManoj sain QC ` ` See Pic
16.03-01-2022BR80Netri chandeli BR80 Erection work in progress.Sandeep kumarunknownunknown See Pic
17.27-12-2021Netri Chandeli motor bridgeA2 abutmentAAE CL Bharti ` ` See Pic
18.25-09-2021A2 abutment of NetriA2 abutmentCL Bharti AAE ` ` See Pic
19.23-09-2021Netri-chandeli motor bridge fabrication.Ground erection of netri-chandeli motor bridge is in progress at Fabrication yard situated at roorkee.Abhishek tiwari ` ` See Pic
20.23-09-2021Netri-chandeli motor bridgeGround erection of netri-chandeli motor bridge is in progress at Fabrication yard situated at roorkee.Abhishek tiwari ` ` See Pic