Steel Truss Motor Bridge over Kamal River on Netri Chandeli MR at KM-3
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4122 |
Sanction Cost: |
565.56 lakh |
Span:
|
48.000 M |
District: |
Uttarkashi |
Block: |
Puraula |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 647
Package Name: 
UDRP/AF/BR/80
Tender Date: 11-11-2019
Current Status: Agreement signed
Achieved on Date: 04-08-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/80
Contractor Name: Tons Builderes
|
Start Date: 21-08-2020
Intended Completion Date: 20-02-2022
Original End Date: 14-07-2021 |
Total Bond Cost: 55121698.15 (551.22 lakh)
Variation Cost: 5410941.57 (54.11 lakh) Hence Total Bond Cost is 60532639.72 (605.33 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 11630742 for 422 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 27.35 | 01-07-2021 | 19-02-2022 | 1.00 Job | 1.00 Job | 5.36 | 27.35 | 2. | Foundation RHS | 1.00 Job | 25.07 | 30-09-2020 | 31-12-2020 | 1.00 Job | 1.00 Job | 4.91 | 25.07 | 3. | Foundation LHS | 1.00 Job | 25.07 | 30-10-2020 | 13-03-2021 | 1.00 Job | 1.00 Job | 4.91 | 25.07 | 4. | Abutment Superstructure RHS | 1.00 Job | 46.96 | 30-11-2020 | 25-03-2021 | 1.00 Job | 1.00 Job | 9.2 | 46.96 | 5. | Abutment Superstructure LHS | 1.00 Job | 46.96 | 30-12-2020 | 28-04-2021 | 1.00 Job | 1.00 Job | 9.2 | 46.96 | 6. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 18.26 | 15-08-2021 | 15-10-2021 | 1.00 sqm | 1.00 sqm | 3.58 | 18.26 | 7. | Steel Railing/crush barrier | 1.00 m | 6.09 | 15-12-2021 | 19-12-2021 | 1.00 m | 1.00 m | 1.19 | 6.09 | 8. | Approach Ramp /path | 1.00 m | 35.08 | 15-01-2021 | 30-10-2021 | 1.00 m | 1.00 m | 6.87 | 35.08 | 9. | Protection Work | 1.00 Job | 19.61 | 02-01-2021 | 30-08-2021 | 1.00 Job | 1.00 Job | 3.84 | 19.61 | 10. | Errection Work | 1.00 Job | 52.62 | 15-09-2021 | 15-11-2021 | 1.00 Job | 1.00 Job | 10.31 | 52.62 | 11. | Fabrication Work | 1.00 job | 185.79 | 15-11-2020 | 27-05-2021 | 1.00 job | 1.00 job | 36.4 | 185.79 | 12. | Fixing Bearing/Slab Casting | 1.00 job | 21.55 | 15-04-2021 | 15-12-2021 | 1.00 job | 1.00 job | 4.22 | 21.55 |
Total Amount: |
510.41 |
|
100 |
510.41 |
|
Remarks:
No Remarks
Work Program Made On:
06-11-2020 } ?>
Updation of work program on:
24-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 19-March-2021 | 93.41 lakh | 2. | 30-March-2021 | 58.82 lakh | 3. | 22-July-2021 | 36.48 lakh | 4. | 07-September-2021 | 81.71 lakh | 5. | 06-November-2021 | 131.95 lakh | 6. | 26-November-2021 | 44.68 lakh | 7. | 07-January-2022 | 53.79 lakh | 8. | 24-February-2022 | 93.63 lakh | 9. | 31-March-2022 | 40.16 lakh | 10. | 26-August-2022 | 39.68 lakh |
Total |
674.31 lakh |
% Payment |
111.41 % |
|
Advance Amount: 48.50 lakh
Recovered Amount: 48.50 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 799 No. of Test Done : 895 No. of Test Passed : 879 No. of Test Failed : 16 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.41 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 164 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-05-2022 | BR 80 netri chandeli | Bridge work has been completed | Manoj sain QC | ` | ` | See Pic |
2. | 13-05-2022 | BR 80 netri chandeli | Bridge work has been completed | Manoj sain QC | ` | ` | See Pic |
3. | 18-02-2022 | Netri-chandeli motor bridge | Painting work is in progress at netri-chandeli motor bridge in district Uttarkashi. | Abhishek tiwari | ` | ` | See Pic |
4. | 18-02-2022 | Netri-chandeli motor bridge | Shuttering of deck slab is in progress at netri-chandeli motor bridge in district Uttarkashi | Abhishek tiwari | ` | ` | See Pic |
5. | 30-01-2022 | Netri Chandeli BR80 | Netri Chandeli BR80 | Sandeep kumar | unknown | unknown | See Pic |
6. | 30-01-2022 | Netri Chandeli BR80 | BR80 Netri Chandeli (Bolt Torquing in progress) | Sandeep kumar | unknown | unknown | See Pic |
7. | 30-01-2022 | BR80 NETRI CHANDELI | Netri Chandeli BR80 Labour training camp. | Sandeep kumar | unknown | unknown | See Pic |
8. | 30-01-2022 | BR80 NETRI CHANDELI | BR80 Netri Chandeli Labour training caomp. | Sandeep kumar | unknown | unknown | See Pic |
9. | 30-01-2022 | Netri chamdeli BR80 | BR80 Labour Training | Sandeep kumar | unknown | unknown | See Pic |
10. | 18-01-2022 | Erection of netri-chandeli motor bridge is in progress at site of district Uttarkashi. | Erection of netri-chandeli motor bridge is in progress at site of district Uttarkashi. | Abhishek tiwari | ` | ` | See Pic |
11. | 18-01-2022 | Netri-chandeli motor bridge | RR 1:5 work completed for approach road at A1 side . | Abhishek tiwari | ` | ` | See Pic |
12. | 18-01-2022 | Netri-chandeli motor bridge | Erection of bridge is in progress at netri-chandeli motor bridge in district Uttarkashi. | Abhishek tiwari | ` | ` | See Pic |
13. | 18-01-2022 | Netri-chandeli motor bridge | Erection of top members is in progress at netri-chandeli motor bridge in district Uttarkashi | Abhishek tiwari | ` | ` | See Pic |
14. | 17-01-2022 | BR 80 netri chandeli | Eraction work is in Progress | Manoj sain QC | ` | ` | See Pic |
15. | 10-01-2022 | BR 80 Netri chandeli | Eraction Work stopped due to rain | Manoj sain QC | ` | ` | See Pic |
16. | 03-01-2022 | BR80 | Netri chandeli BR80 Erection work in progress. | Sandeep kumar | unknown | unknown | See Pic |
17. | 27-12-2021 | Netri Chandeli motor bridge | A2 abutment | AAE CL Bharti | ` | ` | See Pic |
18. | 25-09-2021 | A2 abutment of Netri | A2 abutment | CL Bharti AAE | ` | ` | See Pic |
19. | 23-09-2021 | Netri-chandeli motor bridge fabrication. | Ground erection of netri-chandeli motor bridge is in progress at Fabrication yard situated at roorkee. | Abhishek tiwari | ` | ` | See Pic |
20. | 23-09-2021 | Netri-chandeli motor bridge | Ground erection of netri-chandeli motor bridge is in progress at Fabrication yard situated at roorkee. | Abhishek tiwari | ` | ` | See Pic |
|
|