Sub Project Profile Report

Steel Girder Bridle Bridge over Jalkur River on Sem Bhardar Gajna Bridle Road Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4121 Sanction Cost: 171.27  lakh Span: 36.000 M
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 644        Package Name:  UDRP/AF/BR/79        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 29-09-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/79      Contractor Name: M/S Utsav Associate
Start Date:  06-11-2020      Intended Completion Date:  26-09-2022      Original End Date:  05-02-2022
Total Bond Cost: 16727986.49 (167.28 lakh)        Variation Cost: -3611540.26 (-36.12 lakh)    Hence Total Bond Cost is   13116446.23 (131.16 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1154232 for 138 days        LD Analysis for Milestone2: calculated LD is Rs 2325192 for 278 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job4.3521-01-202220-05-20221.00 Job0.85 Job2.483.70
2.Foundation RHS1.00 Job7.1506-11-202014-01-20211.00 Job1.00 Job4.797.15
3.Foundation LHS1.00 Job7.1520-11-202014-01-20211.00 Job1.00 Job4.797.15
4.Abutment Superstructure RHS1.00 Job7.9515-01-202112-05-20211.00 Job1.00 Job5.337.95
5.Abutment Superstructure LHS1.00 Job7.9515-01-202101-06-20211.00 Job1.00 Job5.337.95
6.Fixing of chequered Plate/RCC Deck88.80 sqm0.9015-05-202214-06-202288.80 sqm0.00 sqm00.00
7.Steel Railing/crush barrier1.00 m1.0815-06-202218-06-20221.00 m0.00 m00.00
8.Approach Ramp /path 1.00 m19.2610-06-202130-04-20221.00 m1.00 m12.8919.26
9.Protection Work1.00 Job30.7513-05-202105-07-20211.00 Job1.00 Job20.5930.75
10.Errection Work1.00 Job21.7601-05-202210-06-20221.00 Job0.10 Job1.462.18
11.Fabrication Work1.00 job39.7815-05-202120-05-20221.00 job1.00 job26.6339.78
12.Fixing Bearing/Slab Casting1.00 job1.2702-02-202212-06-20221.00 job1.00 job0.851.27
Total Amount: 149.35 85.13   127.14
Remarks: No Remarks       Work Program Made On: 29-01-2021        Updation of work program on: 25-05-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-July-202121.17  lakh
2.02-November-202119.93  lakh
3.10-May-20226.82  lakh
4.15-June-202226.53  lakh
5.28-July-20227.81  lakh
6.11-October-20224.59  lakh
7.22-December-202211.72  lakh
8.31-March-202334.97  lakh
Total 133.54  lakh
% Payment 81.64 %
Advance Amount:  15.28  lakh        Recovered Amount:  15.28  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 285   No. of Test Done : 331    No. of Test Passed : 330   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.48
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 58
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-06-2022Sembhardhar GajnaApproach road A2 side on progressAjay Singh Rana ` ` See Pic
2.15-06-2022Sembhardhar GajnaGabions work on progress in R.H.SAjay Singh Rana ` ` See Pic
3.23-05-202236m Span steel truss bridle bridge at Sembhardhar GajnaAbutment A2 side protection work on progressAjay Singh Rana ` ` See Pic
4.20-05-202236m span steel truss bridle bridge at Sembhardhar GajnaRR Wall(1:5) completed for Abutment A2 side Approach roadAjay Singh Rana ` ` See Pic
5.20-05-202236m span steel truss bridle bridge at Sembhardhar GajnaApproach road A1 side on progressAjay Singh Rana ` ` See Pic
6.14-05-202236m span steel truss bridge at Sembhardhar GajnaA2 side RR wall(1:5) for approach roadAjay Singh Rana ` ` See Pic
7.14-05-202236m span steel truss bridge at Sembhardhar GajnaApproach road RR wall(1:5)Ajay Singh Rana ` ` See Pic
8.16-11-2021BR/79A2,cap concrete sampling work in progress, concrete grade M35.Niraj pathakunknownunknown See Pic
9.16-11-2021Sembhardhar Gajna Bridle BridgeAbutment A1 side shuttering work completed for capAjay Singh Rana ` ` See Pic
10.13-11-2021Sembhardhar Gajna Bridle BridgeCap reinforcement work on progressAjay Singh Rana ` ` See Pic
11.13-10-2021Sembhardar km1Cap casting A2 side at sembhardar BR/79Deepak ` ` See Pic
12.17-07-2021Km01Abutment R.H.S side Protection work in Progress at 36 M span Steel Girder Bridge Sembhardar UttarkashiYogesh Dobhalunknownunknown See Pic
13.17-07-2021Sembhardhar Gajna Bridle BridgeAbutment A1 side Protection work on progressAjay Singh Rana ` ` See Pic
14.07-07-2021Sem bhardarT.s Survey For Abutment R.H.S and L.H.S side Cap Marking At 36M span Steel Girder Bridge District UttarkashiYogesh Dobhalunknownunknown See Pic
15.07-07-2021Sembhardhar Gajna Bridle BridgeT.S. Survey for Abutment LHS and RHS side for Cap and Padestal markingAjay Singh Rana ` ` See Pic
16.01-07-2021Sembhardhar Gajna Bridle BridgeAbhutment A1 side earthwork for gabionsAjay Singh Ranaunknownunknown See Pic
17.01-07-2021Sembhardhar Gajna Bridle BridgeA2 side 4th lift Deshuttering work on progressAjay Singh Rana ` ` See Pic
18.01-07-2021Sembhardhar Gajna Bridle BridgeAbutment A2 side 4th lift M-35 Grade concreting work on progressAjay Singh Ranaunknownunknown See Pic
19.26-06-2021Sembhardhar Gajna Bridle BridgeA2 side 4th lift reinforcement steel work on progressAjay Singh Rana ` ` See Pic
20.26-06-2021Sembhardhar bridle bridgeSembhardhar Bridle Bridge A2 side 4th lift reinforcement checkingAjay Singh Rana ` ` See Pic