Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Steel Girder Bridle Bridge over Jalkur River on Sem Bhardar Gajna Bridle Road Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4121 Sanction Cost: 171.27  lakh Span: 36.000 M
District: Uttarkashi Block: Dunda Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 644        Package Name:  UDRP/AF/BR/79        Tender Date: 11-11-2019        Current Status: Agreement signed        Achieved on Date: 29-09-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/79      Contractor Name: M/S Utsav Associate
Start Date:  06-11-2020      Intended Completion Date:  26-09-2022      Original End Date:  05-02-2022
Total Bond Cost: 16727986.49 (167.28 lakh)        Variation Cost: -371155.73 (-3.71 lakh)    Hence Total Bond Cost is   16356830.76 (163.57 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1154232 for 138 days        LD Analysis for Milestone2: calculated LD is Rs 1564068 for +187 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job4.3521-01-202220-05-20221.00 Job0.85 Job2.483.70
2.Foundation RHS1.00 Job7.1506-11-202014-01-20211.00 Job1.00 Job4.797.15
3.Foundation LHS1.00 Job7.1520-11-202014-01-20211.00 Job1.00 Job4.797.15
4.Abutment Superstructure RHS1.00 Job7.9515-01-202112-05-20211.00 Job1.00 Job5.337.95
5.Abutment Superstructure LHS1.00 Job7.9515-01-202101-06-20211.00 Job1.00 Job5.337.95
6.Fixing of chequered Plate/RCC Deck88.80 sqm0.9015-05-202214-06-202288.80 sqm0.00 sqm00.00
7.Steel Railing/crush barrier1.00 m1.0815-06-202218-06-20221.00 m0.00 m00.00
8.Approach Ramp /path 1.00 m19.2610-06-202130-04-20221.00 m1.00 m12.8919.26
9.Protection Work1.00 Job30.7513-05-202105-07-20211.00 Job1.00 Job20.5930.75
10.Errection Work1.00 Job21.7601-05-202210-06-20221.00 Job0.10 Job1.462.18
11.Fabrication Work1.00 job39.7815-05-202120-05-20221.00 job1.00 job26.6339.78
12.Fixing Bearing/Slab Casting1.00 job1.2702-02-202212-06-20221.00 job1.00 job0.851.27
Total Amount: 149.35 85.13   127.14
Remarks: No Remarks       Work Program Made On: 29-01-2021        Updation of work program on: 25-05-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-July-202121.17  lakh
2.02-November-202119.93  lakh
3.10-May-20226.82  lakh
4.15-June-202226.53  lakh
5.28-July-20227.81  lakh
6.11-October-20224.59  lakh
7.22-December-202211.72  lakh
Total 98.57  lakh
% Payment 60.26 %
Advance Amount:  15.28  lakh        Recovered Amount:  13.88  lakh        Balance to be Recovered  1.40  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): No Pending Issue
Detailed report of this subproject
Quality
No. of Test Required : 285   No. of Test Done : 331    No. of Test Passed : 330   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.48
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 58
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.16-06-2022Sembhardhar GajnaApproach road A2 side on progressAjay Singh Rana ` ` See Pic
2.15-06-2022Sembhardhar GajnaGabions work on progress in R.H.SAjay Singh Rana ` ` See Pic
3.23-05-202236m Span steel truss bridle bridge at Sembhardhar GajnaAbutment A2 side protection work on progressAjay Singh Rana ` ` See Pic
4.20-05-202236m span steel truss bridle bridge at Sembhardhar GajnaRR Wall(1:5) completed for Abutment A2 side Approach roadAjay Singh Rana ` ` See Pic
5.20-05-202236m span steel truss bridle bridge at Sembhardhar GajnaApproach road A1 side on progressAjay Singh Rana ` ` See Pic
6.14-05-202236m span steel truss bridge at Sembhardhar GajnaA2 side RR wall(1:5) for approach roadAjay Singh Rana ` ` See Pic
7.14-05-202236m span steel truss bridge at Sembhardhar GajnaApproach road RR wall(1:5)Ajay Singh Rana ` ` See Pic
8.16-11-2021BR/79A2,cap concrete sampling work in progress, concrete grade M35.Niraj pathakunknownunknown See Pic
9.16-11-2021Sembhardhar Gajna Bridle BridgeAbutment A1 side shuttering work completed for capAjay Singh Rana ` ` See Pic
10.13-11-2021Sembhardhar Gajna Bridle BridgeCap reinforcement work on progressAjay Singh Rana ` ` See Pic
11.13-10-2021Sembhardar km1Cap casting A2 side at sembhardar BR/79Deepak ` ` See Pic
12.17-07-2021Km01Abutment R.H.S side Protection work in Progress at 36 M span Steel Girder Bridge Sembhardar UttarkashiYogesh Dobhalunknownunknown See Pic
13.17-07-2021Sembhardhar Gajna Bridle BridgeAbutment A1 side Protection work on progressAjay Singh Rana ` ` See Pic
14.07-07-2021Sem bhardarT.s Survey For Abutment R.H.S and L.H.S side Cap Marking At 36M span Steel Girder Bridge District UttarkashiYogesh Dobhalunknownunknown See Pic
15.07-07-2021Sembhardhar Gajna Bridle BridgeT.S. Survey for Abutment LHS and RHS side for Cap and Padestal markingAjay Singh Rana ` ` See Pic
16.01-07-2021Sembhardhar Gajna Bridle BridgeAbhutment A1 side earthwork for gabionsAjay Singh Ranaunknownunknown See Pic
17.01-07-2021Sembhardhar Gajna Bridle BridgeA2 side 4th lift Deshuttering work on progressAjay Singh Rana ` ` See Pic
18.01-07-2021Sembhardhar Gajna Bridle BridgeAbutment A2 side 4th lift M-35 Grade concreting work on progressAjay Singh Ranaunknownunknown See Pic
19.26-06-2021Sembhardhar Gajna Bridle BridgeA2 side 4th lift reinforcement steel work on progressAjay Singh Rana ` ` See Pic
20.26-06-2021Sembhardhar bridle bridgeSembhardhar Bridle Bridge A2 side 4th lift reinforcement checkingAjay Singh Rana ` ` See Pic