RCC Bridge at Rathuadab over Mandal River
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4119 |
Sanction Cost: |
1927.48 lakh |
Span:
|
200.000 M |
District: |
Pauri |
Block: |
Rikhnikhal |
Constituency: |
Lansdowne |
Circle: |
|
DEA: |
DEA Pauri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 665
Package Name: 
UDRP/AF/BR/66
Tender Date: 11-10-2019
Current Status: Agreement signed
Achieved on Date: 06-10-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/66
Contractor Name: V. K. Gupta & Associates
|
Start Date: 29-10-2020
Intended Completion Date: 18-02-2023
Original End Date: 31-03-2022 |
Total Bond Cost: 184550240 (1845.5 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 47337075 for 513 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 92.28 | 22-03-2021 | 14-08-2022 | 1.00 Job | 0.75 Job | 3.75 | 69.21 | 2. | Pile Cap | 4.00 No | 253.94 | 01-01-2021 | 24-09-2021 | 4.00 No | 4.00 No | 13.76 | 253.94 | 3. | Group of Pile | 4.00 No | 169.29 | 15-12-2020 | 31-05-2021 | 4.00 No | 4.00 No | 9.17 | 169.29 | 4. | Abutment Superstructure RHS | 1.00 Job | 137.55 | 26-03-2021 | 04-05-2021 | 1.00 Job | 1.00 Job | 7.45 | 137.55 | 5. | Abutment Superstructure LHS | 1.00 Job | 137.55 | 14-04-2021 | 26-05-2021 | 1.00 Job | 1.00 Job | 7.45 | 137.55 | 6. | Approach Ramp /path | 800.00 m | 166.10 | 18-08-2021 | 10-08-2022 | 800.00 m | 0.00 m | 0 | 0.00 | 7. | Fixing Bearing/Slab Casting | 5.00 job | 206.33 | 20-10-2021 | 09-08-2022 | 5.00 job | 5.00 job | 11.18 | 206.33 | 8. | Well-Abutments/Pier/Shafts/Caps | 4.00 job | 126.97 | 11-04-2021 | 30-11-2021 | 4.00 job | 4.00 job | 6.88 | 126.97 | 9. | PSC girder & Diaphragms | 5.00 No | 555.50 | 15-09-2021 | 05-07-2022 | 5.00 No | 5.00 No | 30.1 | 555.50 |
Total Amount: |
1845.51 |
|
89.75 |
1656.34 |
|
Remarks:
No Remarks
Work Program Made On:
20-03-2021 } ?>
Updation of work program on:
15-06-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-February-2021 | 105.81 lakh | 2. | 26-March-2021 | 105.81 lakh | 3. | 08-May-2021 | 253.94 lakh | 4. | 31-May-2021 | 63.49 lakh | 5. | 01-July-2021 | 88.46 lakh | 6. | 07-September-2021 | 63.49 lakh | 7. | 07-October-2021 | 31.74 lakh | 8. | 03-November-2021 | 95.23 lakh | 9. | 21-January-2022 | 63.49 lakh | 10. | 18-July-2022 | 223.05 lakh | 11. | 28-July-2022 | 133.32 lakh | 12. | 20-October-2022 | 221.24 lakh | 13. | 24-November-2022 | 195.22 lakh | 14. | 04-January-2023 | 65.21 lakh | 15. | 09-March-2023 | 0.00 lakh | 16. | 24-March-2023 | 188.20 lakh |
Total |
1897.7 lakh |
% Payment |
102.82 % |
|
Advance Amount: 92.00 lakh
Recovered Amount: 92.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1486 No. of Test Done : 1488 No. of Test Passed : 1488 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 98.32 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 834 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-06-2022 | BR-66 | E.E.sir visit at site | Deepak Rawat | ` | ` | See Pic |
2. | 24-06-2022 | BR-66 | E.E sir visit at site | Deepak Rawat | ` | ` | See Pic |
3. | 24-06-2022 | BR-66 | Grouting at psc girders is in progress | Deepak Rawat | ` | ` | See Pic |
4. | 24-06-2022 | BR-66 | Grouting at psc girders is in progress | Deepak Rawat | ` | ` | See Pic |
5. | 24-06-2022 | BR-66 | Grouting at psc girders is in progress | Deepak Rawat | ` | ` | See Pic |
6. | 24-06-2022 | BR-66 | Grouting at psc girders is in progress | Deepak Rawat | ` | ` | See Pic |
7. | 22-06-2022 | BR-66 | First stage stressing work of PSC Girder is in progress. | Digambar prasad | ` | ` | See Pic |
8. | 22-06-2022 | BR-66 | First stage stressing work of PSC Girder is in progress. | Digambar prasad | ` | ` | See Pic |
9. | 22-06-2022 | BR-66 | First stage stressing PSC Girders is in progress . | Digambar prasad | ` | ` | See Pic |
10. | 22-06-2022 | BR-66 | Stressing of psc girder is in progress | Deepak Rawat | ` | ` | See Pic |
11. | 22-06-2022 | BR-66 | Stressing of psc girder is in progress | Deepak Rawat | ` | ` | See Pic |
12. | 20-06-2022 | BR-66 | Stressing of psc girder is in progress | Deepak Rawat | ` | ` | See Pic |
13. | 20-06-2022 | BR-66 | Stressing of psc girder is in progress | Deepak Rawat | ` | ` | See Pic |
14. | 20-06-2022 | BR-66 | Stressing of psc girder is in progress | Deepak Rawat | ` | ` | See Pic |
15. | 20-06-2022 | BR-66 | Girder stressing work is in progress | Deepak Rawat | ` | ` | See Pic |
16. | 15-06-2022 | BR-66 | 1nos.crane shifted at site | Deepak Rawat | ` | ` | See Pic |
17. | 08-06-2022 | BR-66 | Crane parts reached at site | Deepak Rawat | ` | ` | See Pic |
18. | 08-06-2022 | BR-66 | R.E.sir visit at site | Deepak Rawat | ` | ` | See Pic |
19. | 28-05-2022 | BR-66 | Curing at psc girders | Deepak Rawat | ` | ` | See Pic |
20. | 28-05-2022 | BR-66 | Curing at psc girders | Deepak Rawat | ` | ` | See Pic |
|
|