Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

RCC Bridge at Rathuadab over Mandal River Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4119 Sanction Cost: 1927.48  lakh Span: 200.000 M
District: Pauri Block: Rikhnikhal Constituency: Lansdowne Circle:
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 665        Package Name:  UDRP/AF/BR/66        Tender Date: 11-10-2019        Current Status: Agreement signed        Achieved on Date: 06-10-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/66      Contractor Name: V. K. Gupta & Associates
Start Date:  29-10-2020      Intended Completion Date:  18-02-2023      Original End Date:  31-03-2022
Total Bond Cost: 184550240 (1845.5 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 47337075 for 513 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job92.2822-03-202114-08-20221.00 Job0.75 Job3.7569.21
2.Pile Cap4.00 No253.9401-01-202124-09-20214.00 No4.00 No13.76253.94
3.Group of Pile4.00 No169.2915-12-202031-05-20214.00 No4.00 No9.17169.29
4.Abutment Superstructure RHS1.00 Job137.5526-03-202104-05-20211.00 Job1.00 Job7.45137.55
5.Abutment Superstructure LHS1.00 Job137.5514-04-202126-05-20211.00 Job1.00 Job7.45137.55
6.Approach Ramp /path 800.00 m166.1018-08-202110-08-2022800.00 m0.00 m00.00
7.Fixing Bearing/Slab Casting5.00 job206.3320-10-202109-08-20225.00 job5.00 job11.18206.33
8.Well-Abutments/Pier/Shafts/Caps4.00 job126.9711-04-202130-11-20214.00 job4.00 job6.88126.97
9.PSC girder & Diaphragms5.00 No555.5015-09-202105-07-20225.00 No5.00 No30.1555.50
Total Amount: 1845.51 89.75   1656.34
Remarks: No Remarks       Work Program Made On: 20-03-2021        Updation of work program on: 15-06-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.26-February-2021105.81  lakh
2.26-March-2021105.81  lakh
3.08-May-2021253.94  lakh
4.31-May-202163.49  lakh
5.01-July-202188.46  lakh
6.07-September-202163.49  lakh
7.07-October-202131.74  lakh
8.03-November-202195.23  lakh
9.21-January-202263.49  lakh
10.18-July-2022223.05  lakh
11.28-July-2022133.32  lakh
12.20-October-2022221.24  lakh
13.24-November-2022195.22  lakh
14.04-January-202365.21  lakh
15.09-March-20230.00  lakh
16.24-March-2023188.20  lakh
Total 1897.7  lakh
% Payment 102.82 %
Advance Amount:  92.00  lakh        Recovered Amount:  92.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1486   No. of Test Done : 1488    No. of Test Passed : 1488   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 98.32
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 834
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-06-2022BR-66E.E.sir visit at siteDeepak Rawat ` ` See Pic
2.24-06-2022BR-66E.E sir visit at siteDeepak Rawat ` ` See Pic
3.24-06-2022BR-66Grouting at psc girders is in progressDeepak Rawat ` ` See Pic
4.24-06-2022BR-66Grouting at psc girders is in progressDeepak Rawat ` ` See Pic
5.24-06-2022BR-66Grouting at psc girders is in progressDeepak Rawat ` ` See Pic
6.24-06-2022BR-66Grouting at psc girders is in progressDeepak Rawat ` ` See Pic
7.22-06-2022BR-66First stage stressing work of PSC Girder is in progress.Digambar prasad ` ` See Pic
8.22-06-2022BR-66First stage stressing work of PSC Girder is in progress.Digambar prasad ` ` See Pic
9.22-06-2022BR-66First stage stressing PSC Girders is in progress .Digambar prasad ` ` See Pic
10.22-06-2022BR-66Stressing of psc girder is in progressDeepak Rawat ` ` See Pic
11.22-06-2022BR-66Stressing of psc girder is in progressDeepak Rawat ` ` See Pic
12.20-06-2022BR-66Stressing of psc girder is in progressDeepak Rawat ` ` See Pic
13.20-06-2022BR-66Stressing of psc girder is in progressDeepak Rawat ` ` See Pic
14.20-06-2022BR-66Stressing of psc girder is in progressDeepak Rawat ` ` See Pic
15.20-06-2022BR-66Girder stressing work is in progressDeepak Rawat ` ` See Pic
16.15-06-2022BR-661nos.crane shifted at siteDeepak Rawat ` ` See Pic
17.08-06-2022BR-66Crane parts reached at siteDeepak Rawat ` ` See Pic
18.08-06-2022BR-66R.E.sir visit at siteDeepak Rawat ` ` See Pic
19.28-05-2022BR-66Curing at psc girdersDeepak Rawat ` ` See Pic
20.28-05-2022BR-66Curing at psc girdersDeepak Rawat ` ` See Pic