60M Steel Truss Motor Bridge at KM-1 of Bhonsal Bheti MR
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4110 |
Sanction Cost: |
571.76 lakh |
Span:
|
60.000 M |
District: |
Pauri |
Block: |
Kaljikhal |
Constituency: |
Pauri |
Circle: |
|
DEA: |
DEA Pauri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 635
Package Name: 
UDRP/AF/BR/51
Tender Date: 22-01-2020
Current Status: Agreement signed
Achieved on Date: 24-08-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/51
Contractor Name: Gaurav Builder
|
Start Date: 09-09-2020
Intended Completion Date: 06-10-2022
Original End Date: 09-03-2022 |
Total Bond Cost: 58111371.92 (581.11 lakh)
Variation Cost: -2296757.17 (-22.97 lakh) Hence Total Bond Cost is 55814614.75 (558.15 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 15254400 for 525 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.10 KM | 8.79 | 09-08-2021 | 25-01-2022 | 0.10 KM | 0.10 KM | 1.52 | 8.79 | 2. | R/Wall, B/ Wall Type Protection works | 200.00 m | 37.84 | 15-07-2021 | 31-03-2022 | 200.00 m | 50.00 m | 1.63 | 9.46 | 3. | PC/CC i/c Prime Coat, Tack Coat | 0.10 KM | 4.91 | 01-02-2022 | 15-05-2022 | 0.10 KM | 0.10 KM | 0.85 | 4.91 | 4. | Crash Barrier | 110.00 m | 3.70 | 15-02-2022 | 20-03-2022 | 0.00 m | 0.00 m | 0 | 0.00 | 5. | Road Furniture | 2.00 No | 0.46 | 15-09-2020 | 20-03-2022 | 2.00 No | 2.00 No | 0.08 | 0.46 | 6. | Env. Man & Moni Plan | 1.00 Job | 10.02 | 10-09-2021 | 12-06-2022 | 1.00 Job | 1.00 Job | 1.73 | 10.02 | 7. | Other Allied Works & Finishing Work | 1.00 Job | 5.49 | 10-09-2020 | 24-05-2022 | 1.00 Job | 1.00 Job | 0.95 | 5.49 | 8. | Foundation RHS | 1.00 Job | 1.33 | 10-09-2020 | 14-04-2021 | 1.00 Job | 1.00 Job | 0.23 | 1.33 | 9. | Foundation LHS | 1.00 Job | 1.33 | 11-10-2020 | 13-02-2021 | 1.00 Job | 1.00 Job | 0.23 | 1.33 | 10. | Abutment Superstructure RHS | 1.00 Job | 72.51 | 01-04-2021 | 05-02-2022 | 1.00 Job | 1.00 Job | 12.5 | 72.51 | 11. | Abutment Superstructure LHS | 1.00 Job | 72.51 | 22-12-2020 | 10-02-2022 | 1.00 Job | 1.00 Job | 12.5 | 72.51 | 12. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 1.00 no | 18.96 | 01-05-2022 | 10-05-2022 | 1.00 no | 1.00 no | 3.27 | 18.96 | 13. | Steel Railing/crush barrier | 120.00 m | 7.39 | 10-10-2021 | 20-05-2022 | 0.00 m | 0.00 m | 0 | 0.00 | 14. | Approach Ramp /path | 100.00 m | 11.87 | 11-10-2021 | 20-05-2022 | 100.00 m | 100.00 m | 2.05 | 11.87 | 15. | Protection Work | 1.00 Job | 22.16 | 15-07-2021 | 23-05-2022 | 1.00 Job | 0.20 Job | 0.76 | 4.43 | 16. | Errection Work | 1.00 Job | 102.10 | 01-04-2022 | 28-04-2022 | 1.00 Job | 1.00 Job | 17.6 | 102.10 | 17. | Gabion work | 136.50 m | 25.37 | 25-04-2022 | 22-05-2022 | 720.00 m | 136.50 m | 0.83 | 4.81 | 18. | PCC in Foundation | 25.16 cum | 1.86 | 11-10-2020 | 20-12-2020 | 25.16 cum | 25.16 cum | 0.32 | 1.86 | 19. | Fabrication Work | 1.00 job | 161.90 | 20-04-2021 | 24-01-2022 | 1.00 job | 1.00 job | 27.91 | 161.90 | 20. | Fixing Bearing/Slab Casting | 6.00 job | 5.54 | 20-04-2022 | 30-04-2022 | 6.00 job | 6.00 job | 0.96 | 5.54 | 21. | Wearing Coat | 14.90 Cum | 4.01 | 16-02-2022 | 20-05-2022 | 14.90 Cum | 14.90 Cum | 0.69 | 4.01 |
Total Amount: |
580.05 |
|
86.6 |
502.29 |
|
Remarks:
No Remarks
Work Program Made On:
15-12-2020 } ?>
Updation of work program on:
28-01-2023
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 01-February-2021 | 7.21 lakh | 2. | 26-February-2021 | 32.05 lakh | 3. | 31-May-2021 | 26.03 lakh | 4. | 01-July-2021 | 23.34 lakh | 5. | 27-August-2021 | 18.97 lakh | 6. | 25-September-2021 | 9.10 lakh | 7. | 03-November-2021 | 21.46 lakh | 8. | 03-December-2021 | 15.35 lakh | 9. | 10-February-2022 | 161.45 lakh | 10. | 15-March-2022 | 17.71 lakh | 11. | 31-May-2022 | 59.89 lakh | 12. | 30-June-2022 | 79.59 lakh | 13. | 30-July-2022 | 7.57 lakh | 14. | 19-September-2022 | 23.44 lakh | 15. | 10-November-2022 | 30.58 lakh | 16. | 17-December-2022 | 29.03 lakh |
Total |
562.77 lakh |
% Payment |
98.16 % |
|
Advance Amount: 52.83 lakh
Recovered Amount: 52.83 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 502 No. of Test Done : 505 No. of Test Passed : 502 No. of Test Failed : 3 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.48 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 851 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
2. | 18-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
3. | 18-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
4. | 18-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
5. | 16-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
6. | 16-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
7. | 15-06-2022 | Bhonsal bheti | Errection work is in progress. | Sukhchain singh | ` | ` | See Pic |
8. | 15-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
9. | 15-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
10. | 14-06-2022 | Bhonsal bheti | Errection work is in progress | Sukhchain singh | ` | ` | See Pic |
11. | 13-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
12. | 13-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
13. | 13-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
14. | 13-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
15. | 11-06-2022 | RHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
16. | 11-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
17. | 11-06-2022 | LHS | Errection work in progress | Errection work in progress | ` | ` | See Pic |
18. | 11-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
19. | 10-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
20. | 10-06-2022 | LHS | Errection work in progress | Parvinder singh | ` | ` | See Pic |
|
|