Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

60M Steel Truss Motor Bridge at KM-1 of Bhonsal Bheti MR Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4110 Sanction Cost: 571.76  lakh Span: 60.000 M
District: Pauri Block: Kaljikhal Constituency: Pauri Circle:
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 635        Package Name:  UDRP/AF/BR/51        Tender Date: 22-01-2020        Current Status: Agreement signed        Achieved on Date: 24-08-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/51      Contractor Name: Gaurav Builder
Start Date:  09-09-2020      Intended Completion Date:  06-10-2022      Original End Date:  09-03-2022
Total Bond Cost: 58111371.92 (581.11 lakh)        Variation Cost: -2296757.17 (-22.97 lakh)    Hence Total Bond Cost is   55814614.75 (558.15 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 15254400 for 525 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.10 KM8.7909-08-202125-01-20220.10 KM0.10 KM1.528.79
2.R/Wall, B/ Wall Type Protection works200.00 m37.8415-07-202131-03-2022200.00 m50.00 m1.639.46
3.PC/CC i/c Prime Coat, Tack Coat0.10 KM4.9101-02-202215-05-20220.10 KM0.10 KM0.854.91
4.Crash Barrier110.00 m3.7015-02-202220-03-20220.00 m0.00 m00.00
5.Road Furniture2.00 No0.4615-09-202020-03-20222.00 No2.00 No0.080.46
6.Env. Man & Moni Plan1.00 Job10.0210-09-202112-06-20221.00 Job1.00 Job1.7310.02
7.Other Allied Works & Finishing Work 1.00 Job5.4910-09-202024-05-20221.00 Job1.00 Job0.955.49
8.Foundation RHS1.00 Job1.3310-09-202014-04-20211.00 Job1.00 Job0.231.33
9.Foundation LHS1.00 Job1.3311-10-202013-02-20211.00 Job1.00 Job0.231.33
10.Abutment Superstructure RHS1.00 Job72.5101-04-202105-02-20221.00 Job1.00 Job12.572.51
11.Abutment Superstructure LHS1.00 Job72.5122-12-202010-02-20221.00 Job1.00 Job12.572.51
12.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no18.9601-05-202210-05-20221.00 no1.00 no3.2718.96
13.Steel Railing/crush barrier120.00 m7.3910-10-202120-05-20220.00 m0.00 m00.00
14.Approach Ramp /path 100.00 m11.8711-10-202120-05-2022100.00 m100.00 m2.0511.87
15.Protection Work1.00 Job22.1615-07-202123-05-20221.00 Job0.20 Job0.764.43
16.Errection Work1.00 Job102.1001-04-202228-04-20221.00 Job1.00 Job17.6102.10
17.Gabion work136.50 m25.3725-04-202222-05-2022720.00 m136.50 m0.834.81
18.PCC in Foundation25.16 cum1.8611-10-202020-12-202025.16 cum25.16 cum0.321.86
19.Fabrication Work1.00 job161.9020-04-202124-01-20221.00 job1.00 job27.91161.90
20.Fixing Bearing/Slab Casting6.00 job5.5420-04-202230-04-20226.00 job6.00 job0.965.54
21.Wearing Coat14.90 Cum4.0116-02-202220-05-202214.90 Cum14.90 Cum0.694.01
Total Amount: 580.05 86.6   502.29
Remarks: No Remarks       Work Program Made On: 15-12-2020        Updation of work program on: 28-01-2023       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.01-February-20217.21  lakh
2.26-February-202132.05  lakh
3.31-May-202126.03  lakh
4.01-July-202123.34  lakh
5.27-August-202118.97  lakh
6.25-September-20219.10  lakh
7.03-November-202121.46  lakh
8.03-December-202115.35  lakh
9.10-February-2022161.45  lakh
10.15-March-202217.71  lakh
11.31-May-202259.89  lakh
12.30-June-202279.59  lakh
13.30-July-20227.57  lakh
14.19-September-202223.44  lakh
15.10-November-202230.58  lakh
16.17-December-202229.03  lakh
Total 562.77  lakh
% Payment 98.16 %
Advance Amount:  52.83  lakh        Recovered Amount:  52.83  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 502   No. of Test Done : 505    No. of Test Passed : 502   No. of Test Failed : 3   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.48
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 851
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
2.18-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
3.18-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
4.18-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
5.16-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
6.16-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
7.15-06-2022Bhonsal bhetiErrection work is in progress.Sukhchain singh ` ` See Pic
8.15-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
9.15-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
10.14-06-2022Bhonsal bhetiErrection work is in progressSukhchain singh ` ` See Pic
11.13-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
12.13-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
13.13-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
14.13-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
15.11-06-2022RHSErrection work in progressParvinder singh ` ` See Pic
16.11-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
17.11-06-2022LHSErrection work in progressErrection work in progress ` ` See Pic
18.11-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
19.10-06-2022LHSErrection work in progressParvinder singh ` ` See Pic
20.10-06-2022LHSErrection work in progressParvinder singh ` ` See Pic