Sub Project Profile Report

60M Span Bridge at Kot Malla talla kandiya kulashu rithakhal MR Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4109 Sanction Cost: 926.21  lakh Span: 70.000 M
District: Pauri Block: Zahrikhal Constituency: Chaubattakhal Circle: Tehri WB Circle
DEA: DEA Pauri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 650        Package Name:  UDRP/AF/BR/83        Tender Date: 22-01-2020        Current Status: Agreement signed        Achieved on Date: 15-07-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/83      Contractor Name: M/S.ARKS Universal pvt.ltd
Start Date:  03-09-2020      Intended Completion Date:  01-02-2023      Original End Date:  01-02-2022
Total Bond Cost: 94947092.68 (949.47 lakh)        Variation Cost: -6244317.40 (-62.44 lakh)    Hence Total Bond Cost is   88702775.28 (887.03 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 28674296 for 604 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.20 KM9.4630-06-202110-04-20220.20 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works200.00 m23.7401-11-202125-05-2022200.00 m25.00 m0.312.97
3.PC/CC i/c Prime Coat, Tack Coat0.10 KM1.6401-06-202215-06-20220.10 KM0.00 KM00.00
4.Crash Barrier142.00 m9.0712-06-202220-06-2022142.00 m0.00 m00.00
5.Road Furniture4.00 No0.4703-09-202020-06-20224.00 No4.00 No0.050.47
6.Env. Man & Moni Plan1.00 Job3.8303-09-202026-06-20221.00 Job0.66 Job0.262.53
7.Other Allied Works & Finishing Work 1.00 Job4.4810-01-202225-06-20221.00 Job0.40 Job0.181.79
8.Foundation RHS1.00 Job4.1803-09-202025-12-20201.00 Job1.00 Job0.434.18
9.Foundation LHS1.00 Job4.1815-11-202005-01-20211.00 Job0.90 Job0.393.76
10.Abutment Superstructure RHS1.00 Job135.4607-01-202105-02-20221.00 Job0.90 Job12.57121.91
11.Abutment Superstructure LHS1.00 Job135.4605-04-202110-02-20221.00 Job0.80 Job11.17108.36
12.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 1.00 no28.8610-06-202120-06-20221.00 no0.00 no00.00
13.Steel Railing/crush barrier100.00 m4.4815-05-202230-05-2022100.00 m0.00 m00.00
14.Approach Ramp /path 100.00 m46.3501-06-202215-06-2022100.00 m0.00 m00.00
15.Protection Work1.00 Job28.3820-01-202115-06-20221.00 Job0.35 Job1.029.93
16.Errection Work1.00 Job141.9520-04-202128-05-20221.00 Job0.00 Job00.00
17.PCC in Foundation36.30 cum2.6427-12-202009-02-202236.30 cum26.00 cum0.191.89
18.H.P. Stone2261.50 cum20.4426-12-202015-02-20222261.50 cum350.00 cum0.333.16
19.Fabrication Work1.00 job354.9215-04-202131-01-20221.00 job0.90 job32.93319.43
20.Fixing Bearing/Slab Casting6.00 job6.7220-05-202230-05-20226.00 job0.00 job00.00
21.Wearing Coat26.15 Cum3.2210-06-202215-06-202226.15 Cum0.00 Cum00.00
Total Amount: 969.93 59.84   580.38
Remarks: No Remarks       Work Program Made On: 01-10-2020        Updation of work program on: 25-03-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.13-January-202117.16  lakh
2.12-July-2021106.66  lakh
3.03-September-202125.06  lakh
4.11-October-202111.33  lakh
5.15-March-2022322.80  lakh
6.31-May-20228.00  lakh
7.31-January-2023143.40  lakh
8.09-March-2023147.09  lakh
9.31-May-2023126.76  lakh
Total 908.26  lakh
% Payment 95.65 %
Advance Amount:  242.68  lakh        Recovered Amount:  204.40  lakh        Balance to be Recovered  38.28  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 462   No. of Test Done : 462    No. of Test Passed : 462   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.65
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 694
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-06-2022BR-83 kit talla kot MallaEE Sir site visitBharat Bhoosan Sharmaunknownunknown See Pic
2.07-06-2022Abutment A-2 RHSErection work is in progressBharat Bhoosan Sharmaunknownunknown See Pic
3.07-06-2022BR-83 Kot malla talla bridge Under FPIU PauriSite visit of ExEn sir and RE DSC-1 for errection work inspection.Jitendra Rawat ` ` See Pic
4.07-06-2022BR-83 Kot malla talla Bridge under FPIU Pauri.Site visit of ExEn sir with RE for errection work.Jitendra Rawat ` ` See Pic
5.04-06-2022Kot talla kot mallaErrection work is in progress.Sukhchain ` ` See Pic
6.03-06-2022Errection work is in progressErrection work is in progressJai Prakash Narayan Singhunknownunknown See Pic
7.02-06-2022RHS Approach Road cutting work is in progressRHS Approach Road cutting work is in progressJai Prakash Narayan Singhunknownunknown See Pic
8.01-06-2022Rope fixing work is in progressRope fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
9.01-06-2022RHS Rope Fixing work is in progressRHS Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
10.27-05-2022LHS Tower Errection and Rope Fixing workLHS Tower Errection and Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
11.27-05-2022RHS curing work is in progressRHS curing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
12.27-05-2022LHS Tower Errection and Rope Fixing workLHS Tower Errection and Rope Fixing workJai Prakash Narayan Singhunknownunknown See Pic
13.26-05-2022RHS Tower Errection and Rope Fixing workRHS Tower Errection and Rope Fixing workJai Prakash Narayan Singhunknownunknown See Pic
14.26-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic
15.26-05-2022RHS Tower Errection and Rope Fixing work is in progressRHS Tower Errection and Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
16.26-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic
17.26-05-2022Deevin Sesmic System BhopalBearing testing for BR-83 is in progressBharat Bhoosan Sharmaunknownunknown See Pic
18.25-05-2022LHS Tower Errection and Rope Fixing work is in progressLHS Tower Errection and Rope Fixing work is in progressJai Prakash Narayan Singhunknownunknown See Pic
19.25-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic
20.25-05-2022RHS RR Masonry work is in progressRHS RR Masonry work is in progressJai Prakash Narayan Singhunknownunknown See Pic