Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Steel Truss Bridge on Vijay Kwetha Khatal MR KM-16 Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4105 Sanction Cost: 193.03  lakh Span: 30.000 M
District: Dehradun Block: Kalsi Constituency: Chakrata Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 623        Package Name:  UDRP/AF/BR/56        Tender Date: 26-09-2019        Current Status: Agreement signed        Achieved on Date: 22-01-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/56      Contractor Name: Border Builders
Start Date:  01-02-2020      Intended Completion Date:  23-07-2021      Original End Date:  31-01-2021
Total Bond Cost: 19830911.52 (198.31 lakh)        Variation Cost: 1393401.69 (13.93 lakh)    Hence Total Bond Cost is   21224313.21 (212.24 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 961755 for 97 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job20.1525-01-202123-05-20211.00 Job1.00 Job11.0920.15
2.Foundation RHS1.00 Job5.1101-02-202018-07-20201.00 Job1.00 Job2.815.11
3.Foundation LHS1.00 Job5.1115-02-202017-10-20201.00 Job1.00 Job2.815.11
4.Abutment Superstructure RHS1.00 Job8.1915-06-202021-09-20201.00 Job1.00 Job4.518.19
5.Abutment Superstructure LHS1.00 Job8.1920-06-202013-12-20201.00 Job1.00 Job4.518.19
6.Steel Railing/crush barrier80.00 m4.7630-03-202115-04-202180.00 m80.00 m2.624.76
7.Approach Ramp /path 80.00 m40.6715-11-202015-05-202180.00 m80.00 m22.3840.67
8.Protection Work1.00 Job30.5815-08-202005-04-20211.00 Job1.00 Job16.8330.58
9.Errection Work1.00 Job9.7325-01-202115-03-20211.00 Job1.00 Job5.359.73
10.Fabrication Work1.00 job35.8015-08-202015-12-20201.00 job1.00 job19.735.80
11.Fixing Bearing/Slab Casting1.00 job2.0015-03-202120-03-20211.00 job1.00 job1.12.00
12.Back Wall/ Approach slab1.00 job11.4325-03-202110-04-20211.00 job1.00 job6.2911.43
Total Amount: 181.72 100   181.72
Remarks: No Remarks       Work Program Made On: 03-07-2020        Updation of work program on: 18-02-2021       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-October-202038.40  lakh
2.11-November-20203.58  lakh
3.18-December-202017.10  lakh
4.04-January-202140.09  lakh
5.09-March-202122.70  lakh
6.03-April-202129.72  lakh
7.31-May-202125.31  lakh
8.15-July-202120.88  lakh
9.30-November-202114.46  lakh
Total 212.24  lakh
% Payment 100.01 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 196   No. of Test Done : 196    No. of Test Passed : 196   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 93.18
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 16
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-09-2021Vinay Kwetha Bridge DehradunJoint inspection with AE PWD SahiyaSudhir Kumar ` ` See Pic
2.17-07-2021Vijay Kwetha KM-16Vijay Kwetha KM-16 Measurements taken Approach roadSuresh Prasad ` ` See Pic
3.17-07-2021Vijay Kwetha KM-16Vijay Kwetha Bridge completedSuresh Prasad ` ` See Pic
4.06-05-2021Vijay Kwetha Bridge DehradunSlab CastingSudhir Kumar ` ` See Pic
5.06-05-2021Vijay Kwetha Bridge DehradunDeck Slab CastingSudhir Kumar ` ` See Pic
6.25-02-2021Vijay kwetha khatar motor Road KM-16 Shuttering work in progress for Deck SlabVijay kwetha khatar motor Road KM-16 Shuttering work in progress for Deck SlabSuresh Prasad ` ` See Pic
7.22-02-2021Vijay Kwetha Bridge Km 16 Abutment A2Pedestal Casting work on progressAshish Singh ` ` See Pic
8.22-02-2021Vijay kwetha Bridge km 16 , Abutment A2Excavation for R/wallAshish Singh ` ` See Pic
9.19-02-2021Vijay Kwetha Bridge Km 16Bearings fixing work on progressSudhir kumar ` ` See Pic
10.19-02-2021Vijay Kwetha km 16Erraction CompletedSudhir Kumar ` ` See Pic
11.08-02-2021Vijay kwetha khatar motor bridge KM-16 Erection work in progressViay kwetha khatar motor bridge KM-16 Guider erection work in progressSuresh Prasad ` ` See Pic
12.08-02-2021Vijay kwetha khatar motor Road KM-16 Girder erection work in progressVijay kwetha Khatar motor Road KM-16 Girder erection work in progressSuresh Prasad ` ` See Pic
13.20-11-2020Bridge at Vijay Kwetha M/R km 16Site inspection by EE SirSudhir kumarunknownunknown See Pic
14.08-08-2020Vijay kwetha km16 Abutment A1 Side 2nd lift cube castingAbutment A1 2nd Lift RCC M-35 cube castingSuresh PrasadREBSC R&B WB Rudraprayag See Pic
15.08-08-2020Vijay kwetha km16 Abutment A1 2nd LiftAbutment A1 Side Shaft 2nd Lift RCC M-35 Casting in progressSuresh PrasadREBSC R&B WB Rudraprayag See Pic
16.22-07-2020Bijoy kwetha km16Abutment A2 Side PCC (M15)Suresh PrasadREBSC R&B WB Rudraprayag See Pic