Sukhi River
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4099 |
Sanction Cost: |
1027.01 lakh |
Span:
|
120.000 M |
District: |
Udham Singh Nagar |
Block: |
Sitarganj |
Constituency: |
Sitarganj |
Circle: |
|
DEA: |
DEA Nanital |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 608
Package Name: 
UDRP/AF/35(BR)
Tender Date: 10-01-2019
Current Status: Agreement signed
Achieved on Date: 03-06-2019 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/35(BR)
Contractor Name: Doon Infrastructure Ltd.
|
Start Date: 15-06-2019
Intended Completion Date: 28-02-2022
Original End Date: 14-09-2020 |
Total Bond Cost: 94827516.3 (948.28 lakh)
Variation Cost: 16048163.49 (160.48 lakh) Hence Total Bond Cost is 110875679.79 (1108.76 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 29538922 for 623 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Stressing & Grouting | 48.00 Job | 69.44 | 14-12-2020 | 20-06-2021 | 120.00 Job | 120.00 Job | 6.56 | 69.44 | 2. | Env. Man & Moni Plan | 45.00 Job | 5.10 | 15-09-2019 | 20-02-2022 | 45.00 Job | 45.00 Job | 0.48 | 5.10 | 3. | Other Allied Works & Finishing Work | 12.00 Job | 27.57 | 06-02-2022 | 20-02-2022 | 12.00 Job | 12.00 Job | 2.61 | 27.57 | 4. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 6.00 no | 83.22 | 15-01-2021 | 20-06-2021 | 6.00 no | 6.00 no | 7.86 | 83.22 | 5. | Steel Railing/crush barrier | 240.00 m | 28.87 | 30-01-2021 | 22-06-2021 | 360.00 m | 360.00 m | 2.73 | 28.87 | 6. | Approach Ramp /path | 850.00 m | 156.96 | 01-04-2020 | 05-02-2022 | 850.00 m | 850.00 m | 14.83 | 156.96 | 7. | Protection Work | 4.00 Job | 175.35 | 01-04-2020 | 25-04-2021 | 4.00 Job | 4.00 Job | 16.57 | 175.35 | 8. | Fixing Bearing/Slab Casting | 48.00 job | 15.02 | 01-11-2020 | 25-04-2021 | 48.00 job | 48.00 job | 1.42 | 15.02 | 9. | Back Wall/ Approach slab | 2.00 job | 10.05 | 10-03-2021 | 23-06-2021 | 2.00 job | 2.00 job | 0.95 | 10.05 | 10. | Providing and laying cutting | 6.78 mt | 6.08 | 05-09-2019 | 05-07-2020 | 6.78 mt | 6.78 mt | 0.57 | 6.08 | 11. | Concreting Well Curb and Steaming | 7.00 job | 179.20 | 05-09-2019 | 20-12-2020 | 7.00 job | 7.00 job | 16.93 | 179.20 | 12. | Well Sinking | 160.38 rmt | 25.41 | 15-10-2019 | 28-01-2021 | 149.00 rmt | 149.00 rmt | 2.4 | 25.41 | 13. | Bottom Plug/Top Plug | 329.00 Cum | 40.32 | 10-12-2019 | 30-01-2021 | 329.00 Cum | 329.00 Cum | 3.81 | 40.32 | 14. | Sand Filling | 2087.52 Cum | 41.21 | 15-12-2019 | 03-02-2021 | 2087.52 Cum | 2087.52 Cum | 3.89 | 41.21 | 15. | Well-Abutments/Pier/Shafts/Caps | 7.00 job | 63.73 | 20-05-2020 | 20-04-2021 | 7.00 job | 7.00 job | 6.02 | 63.73 | 16. | PSC girder & Diaphragms | 24.00 No | 118.42 | 01-11-2020 | 20-05-2021 | 24.00 No | 24.00 No | 11.19 | 118.42 | 17. | Wearing Coat | 101.75 Cum | 12.42 | 15-04-2021 | 10-06-2021 | 101.75 Cum | 101.75 Cum | 1.17 | 12.42 |
Total Amount: |
1058.37 |
|
100 |
1058.37 |
|
Remarks:
No Remarks
Work Program Made On:
26-11-2019 } ?>
Updation of work program on:
27-01-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 06-January-2020 | 70.21 lakh | 2. | 29-December-2020 | 0.00 lakh | 3. | 19-February-2021 | 438.96 lakh | 4. | 30-March-2021 | 83.45 lakh | 5. | 31-May-2021 | 106.06 lakh | 6. | 27-August-2021 | 92.03 lakh | 7. | 01-November-2021 | 97.52 lakh | 8. | 03-January-2022 | 54.70 lakh | 9. | 19-February-2022 | 53.66 lakh | 10. | 15-June-2022 | 61.29 lakh | 11. | 28-July-2022 | 50.72 lakh |
Total |
1108.6 lakh |
% Payment |
99.99 % |
|
Advance Amount: 113.28 lakh
Recovered Amount: 113.28 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 4737 No. of Test Done : 4834 No. of Test Passed : 4763 No. of Test Failed : 71 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.79 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 443 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-04-2022 | BR 35 | Thermo plastic Rode Rode marking | Santosh Shukla | ` | ` | See Pic |
2. | 04-03-2022 | A1 Site | Crush Variar post fixing | Santosh Shukla | ` | ` | See Pic |
3. | 02-03-2022 | 510 +715 | DBM laying work in progress | Santosh Shukla | ` | ` | See Pic |
4. | 01-03-2022 | Ch 120 to 1060 | DBM and BC laying in progress | Chhatrapati Pant | ` | ` | See Pic |
5. | 01-03-2022 | A1 site | BC work in Compelled | Santosh Shukla | ` | ` | See Pic |
6. | 01-03-2022 | A1 site | BC leyin work in progress | Santosh Shukla | ` | ` | See Pic |
7. | 01-03-2022 | Ch 120 to 1060 | BC laying in progress ( BR 35) | Chhatrapati Pant | ` | ` | See Pic |
8. | 28-02-2022 | 815 +1060 | BC work in progress | Santosh Shukla | ` | ` | See Pic |
9. | 28-02-2022 | Ch 513.5 to 1060 | BC laying in Progress | Chhatrapati Pant | ` | ` | See Pic |
10. | 28-02-2022 | Ch 513.5 to 1060 (A2 Side Approach) | BC laying in progress | Chhatrapati Pant | ` | ` | See Pic |
11. | 28-02-2022 | Chainage 120 to 330 | BC laying in Progress | Chhatrapati Pant | ` | ` | See Pic |
12. | 28-02-2022 | BR 35 | BC 1st grade Bitumen Extraction test | Santosh Shukla | ` | ` | See Pic |
13. | 28-02-2022 | 715 + 1030 | DBM laying in progress | Santosh Shukla | ` | ` | See Pic |
14. | 25-02-2022 | Ch 120 to 715 | DBM laying in progress | Chhatrapati Pant | ` | ` | See Pic |
15. | 08-02-2022 | Ch 295 to 330 | A1 Side retaining wall foundation protection work( Gabion Wall) in progress | Chhatrapati Pant | ` | ` | See Pic |
16. | 17-01-2022 | Ch 190 Box Culvert | Box Culvert wall 2nd lift concrete done | Chhatrapati Pant | ` | ` | See Pic |
17. | 17-01-2022 | Ch190 Box Culvert | Box Culvert concrete work | Chhatrapati Pant | ` | ` | See Pic |
18. | 15-01-2022 | A1 Abutment 295 + 230 | Protection work | Santosh Shukla | ` | ` | See Pic |
19. | 15-01-2022 | Ch 295 to 330 | Protection work A1 side | Chhatrapati Pant | ` | ` | See Pic |
20. | 15-01-2022 | Ch 190 Box Culvert | Reinforcement and Concrete work for Box Culvert BR35 | Chhatrapati Pant | ` | ` | See Pic |
|
|