Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Sukhi River Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4099 Sanction Cost: 1027.01  lakh Span: 120.000 M
District: Udham Singh Nagar Block: Sitarganj Constituency: Sitarganj Circle:
DEA: DEA Nanital DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 608        Package Name:  UDRP/AF/35(BR)        Tender Date: 10-01-2019        Current Status: Agreement signed        Achieved on Date: 03-06-2019

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/35(BR)      Contractor Name: Doon Infrastructure Ltd.
Start Date:  15-06-2019      Intended Completion Date:  28-02-2022      Original End Date:  14-09-2020
Total Bond Cost: 94827516.3 (948.28 lakh)        Variation Cost: 16048163.49 (160.48 lakh)    Hence Total Bond Cost is   110875679.79 (1108.76 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 29538922 for 623 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Stressing & Grouting48.00 Job69.4414-12-202020-06-2021120.00 Job120.00 Job6.5669.44
2.Env. Man & Moni Plan45.00 Job5.1015-09-201920-02-202245.00 Job45.00 Job0.485.10
3.Other Allied Works & Finishing Work 12.00 Job27.5706-02-202220-02-202212.00 Job12.00 Job2.6127.57
4.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 6.00 no83.2215-01-202120-06-20216.00 no6.00 no7.8683.22
5.Steel Railing/crush barrier240.00 m28.8730-01-202122-06-2021360.00 m360.00 m2.7328.87
6.Approach Ramp /path 850.00 m156.9601-04-202005-02-2022850.00 m850.00 m14.83156.96
7.Protection Work4.00 Job175.3501-04-202025-04-20214.00 Job4.00 Job16.57175.35
8.Fixing Bearing/Slab Casting48.00 job15.0201-11-202025-04-202148.00 job48.00 job1.4215.02
9.Back Wall/ Approach slab2.00 job10.0510-03-202123-06-20212.00 job2.00 job0.9510.05
10.Providing and laying cutting6.78 mt6.0805-09-201905-07-20206.78 mt6.78 mt0.576.08
11.Concreting Well Curb and Steaming7.00 job179.2005-09-201920-12-20207.00 job7.00 job16.93179.20
12.Well Sinking160.38 rmt25.4115-10-201928-01-2021149.00 rmt149.00 rmt2.425.41
13.Bottom Plug/Top Plug329.00 Cum40.3210-12-201930-01-2021329.00 Cum329.00 Cum3.8140.32
14.Sand Filling2087.52 Cum41.2115-12-201903-02-20212087.52 Cum2087.52 Cum3.8941.21
15.Well-Abutments/Pier/Shafts/Caps7.00 job63.7320-05-202020-04-20217.00 job7.00 job6.0263.73
16.PSC girder & Diaphragms24.00 No118.4201-11-202020-05-202124.00 No24.00 No11.19118.42
17.Wearing Coat101.75 Cum12.4215-04-202110-06-2021101.75 Cum101.75 Cum1.1712.42
Total Amount: 1058.37 100   1058.37
Remarks: No Remarks       Work Program Made On: 26-11-2019        Updation of work program on: 27-01-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.06-January-202070.21  lakh
2.29-December-20200.00  lakh
3.19-February-2021438.96  lakh
4.30-March-202183.45  lakh
5.31-May-2021106.06  lakh
6.27-August-202192.03  lakh
7.01-November-202197.52  lakh
8.03-January-202254.70  lakh
9.19-February-202253.66  lakh
10.15-June-202261.29  lakh
11.28-July-202250.72  lakh
Total 1108.6  lakh
% Payment 99.99 %
Advance Amount:  113.28  lakh        Recovered Amount:  113.28  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 4737   No. of Test Done : 4834    No. of Test Passed : 4763   No. of Test Failed : 71   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 92.79
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 443
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-04-2022BR 35Thermo plastic Rode Rode markingSantosh Shukla ` ` See Pic
2.04-03-2022A1 SiteCrush Variar post fixingSantosh Shukla ` ` See Pic
3.02-03-2022510 +715DBM laying work in progressSantosh Shukla ` ` See Pic
4.01-03-2022Ch 120 to 1060DBM and BC laying in progressChhatrapati Pant ` ` See Pic
5.01-03-2022A1 siteBC work in CompelledSantosh Shukla ` ` See Pic
6.01-03-2022A1 siteBC leyin work in progressSantosh Shukla ` ` See Pic
7.01-03-2022Ch 120 to 1060BC laying in progress ( BR 35)Chhatrapati Pant ` ` See Pic
8.28-02-2022815 +1060BC work in progressSantosh Shukla ` ` See Pic
9.28-02-2022Ch 513.5 to 1060BC laying in ProgressChhatrapati Pant ` ` See Pic
10.28-02-2022Ch 513.5 to 1060 (A2 Side Approach)BC laying in progressChhatrapati Pant ` ` See Pic
11.28-02-2022Chainage 120 to 330BC laying in ProgressChhatrapati Pant ` ` See Pic
12.28-02-2022BR 35BC 1st grade Bitumen Extraction testSantosh Shukla ` ` See Pic
13.28-02-2022715 + 1030DBM laying in progressSantosh Shukla ` ` See Pic
14.25-02-2022Ch 120 to 715DBM laying in progressChhatrapati Pant ` ` See Pic
15.08-02-2022Ch 295 to 330A1 Side retaining wall foundation protection work( Gabion Wall) in progressChhatrapati Pant ` ` See Pic
16.17-01-2022Ch 190 Box CulvertBox Culvert wall 2nd lift concrete doneChhatrapati Pant ` ` See Pic
17.17-01-2022Ch190 Box CulvertBox Culvert concrete workChhatrapati Pant ` ` See Pic
18.15-01-2022A1 Abutment 295 + 230Protection workSantosh Shukla ` ` See Pic
19.15-01-2022Ch 295 to 330Protection work A1 sideChhatrapati Pant ` ` See Pic
20.15-01-2022Ch 190 Box CulvertReinforcement and Concrete work for Box Culvert BR35Chhatrapati Pant ` ` See Pic