Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Steel Truss Bridge over Pilang Jadau in Judaugaad Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4092 Sanction Cost: 171.43  lakh Span: 36.000 M
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 607        Package Name:  UDRP/AF/34(BR)        Tender Date: 19-06-2019        Current Status: Agreement signed        Achieved on Date: 21-11-2019

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/34(BR)      Contractor Name: M/S Utsav Associate
Start Date:  16-12-2019      Intended Completion Date:  08-11-2021      Original End Date:  15-12-2020
Total Bond Cost: 17142784.51 (171.43 lakh)        Variation Cost: -146505.81 (-1.47 lakh)    Hence Total Bond Cost is   16996278.7 (169.96 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 462834 for 54 days        LD Analysis for Milestone2: calculated LD is Rs 2511303 for 293 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job29.0525-04-202130-04-20211.00 Job1.00 Job16.9529.05
2.Foundation RHS1.00 Job7.4116-12-201907-10-20201.00 Job1.00 Job4.327.41
3.Foundation LHS1.00 Job7.4130-01-202011-05-20201.00 Job1.00 Job4.327.41
4.Abutment Superstructure RHS1.00 Job23.7326-02-202015-09-20201.00 Job1.00 Job13.8423.73
5.Abutment Superstructure LHS1.00 Job23.7307-07-202025-09-20201.00 Job1.00 Job13.8423.73
6.Fixing of chequered Plate/RCC Deck67.68 sqm8.0515-11-202031-03-202167.68 sqm67.68 sqm4.78.05
7.Steel Railing/crush barrier30.16 m3.0220-04-202125-04-202130.16 m30.16 m1.763.02
8.Approach Ramp /path 1.00 m10.3620-10-202015-04-20211.00 m1.00 m6.0510.36
9.Protection Work1.00 Job20.2918-09-202028-11-20201.00 Job1.00 Job11.8420.29
10.Errection Work1.00 Job7.6203-08-202015-04-20211.00 Job1.00 Job4.457.62
11.Fabrication Work1.00 job29.7720-06-202031-03-20211.00 job1.00 job17.3729.77
12.Fixing Bearing/Slab Casting1.00 job0.9807-04-202112-04-20211.00 job1.00 job0.570.98
Total Amount: 171.42 100   171.42
Remarks: No Remarks       Work Program Made On: 07-03-2020        Updation of work program on: 25-05-2022       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-January-202177.28  lakh
2.22-September-202115.08  lakh
3.26-November-202123.66  lakh
4.31-March-202224.44  lakh
5.31-May-202229.51  lakh
Total 169.97  lakh
% Payment 100 %
Advance Amount:  54.29  lakh        Recovered Amount:  54.29  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 257   No. of Test Done : 276    No. of Test Passed : 271   No. of Test Failed : 5   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 7
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-08-2021Pilang Judav Bridge Abutment A1 1st lift castingThese photos are already uploaded earlier but not shown in portal.Bipin Nautiyalunknownunknown See Pic
2.19-08-2021Pulang judav Bridge Abutment A1 1st lift Reinforcement checkingThese photos are already uploaded earlier but not shown in the portalBipin Nautiyalunknownunknown See Pic
3.19-08-2021Concrete sampling in cube mould for raft.Photos also uploaded during construction.Bipin Nautiyalunknownunknown See Pic
4.19-08-2021Pilang Judav Bridge Abutment A1 Raft castingPhotos also uploaded during construction.Bipin Nautiyalunknownunknown See Pic
5.17-08-2021Pilang Judav Bridge Abutment A2 Raft Reinforcement checked.Photos are already uploaded during construction but not shown in portal.Bipin Nautiyalunknownunknown See Pic
6.17-08-2021Pilang Judav Bridge Abutment A1 cap coarse aggregate gradation test in progress.Photos already uploaded during construction but not shown in portal.Bipin Nautiyalunknownunknown See Pic
7.25-07-2020Abutment A1 at Pilang judav BridgeAbutment A1 Raft concreting on progressBipin Nautiyalunknownunknown See Pic