Steel Truss Bridge over Pilang Jadau in Judaugaad
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4092 |
Sanction Cost: |
171.43 lakh |
Span:
|
36.000 M |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 607
Package Name: 
UDRP/AF/34(BR)
Tender Date: 19-06-2019
Current Status: Agreement signed
Achieved on Date: 21-11-2019 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/34(BR)
Contractor Name: M/S Utsav Associate
|
Start Date: 16-12-2019
Intended Completion Date: 08-11-2021
Original End Date: 15-12-2020 |
Total Bond Cost: 17142784.51 (171.43 lakh)
Variation Cost: -146505.81 (-1.47 lakh) Hence Total Bond Cost is 16996278.7 (169.96 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 462834 for 54 days
LD Analysis for Milestone2: calculated LD is Rs 2511303 for 293 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 29.05 | 25-04-2021 | 30-04-2021 | 1.00 Job | 1.00 Job | 16.95 | 29.05 | 2. | Foundation RHS | 1.00 Job | 7.41 | 16-12-2019 | 07-10-2020 | 1.00 Job | 1.00 Job | 4.32 | 7.41 | 3. | Foundation LHS | 1.00 Job | 7.41 | 30-01-2020 | 11-05-2020 | 1.00 Job | 1.00 Job | 4.32 | 7.41 | 4. | Abutment Superstructure RHS | 1.00 Job | 23.73 | 26-02-2020 | 15-09-2020 | 1.00 Job | 1.00 Job | 13.84 | 23.73 | 5. | Abutment Superstructure LHS | 1.00 Job | 23.73 | 07-07-2020 | 25-09-2020 | 1.00 Job | 1.00 Job | 13.84 | 23.73 | 6. | Fixing of chequered Plate/RCC Deck | 67.68 sqm | 8.05 | 15-11-2020 | 31-03-2021 | 67.68 sqm | 67.68 sqm | 4.7 | 8.05 | 7. | Steel Railing/crush barrier | 30.16 m | 3.02 | 20-04-2021 | 25-04-2021 | 30.16 m | 30.16 m | 1.76 | 3.02 | 8. | Approach Ramp /path | 1.00 m | 10.36 | 20-10-2020 | 15-04-2021 | 1.00 m | 1.00 m | 6.05 | 10.36 | 9. | Protection Work | 1.00 Job | 20.29 | 18-09-2020 | 28-11-2020 | 1.00 Job | 1.00 Job | 11.84 | 20.29 | 10. | Errection Work | 1.00 Job | 7.62 | 03-08-2020 | 15-04-2021 | 1.00 Job | 1.00 Job | 4.45 | 7.62 | 11. | Fabrication Work | 1.00 job | 29.77 | 20-06-2020 | 31-03-2021 | 1.00 job | 1.00 job | 17.37 | 29.77 | 12. | Fixing Bearing/Slab Casting | 1.00 job | 0.98 | 07-04-2021 | 12-04-2021 | 1.00 job | 1.00 job | 0.57 | 0.98 |
Total Amount: |
171.42 |
|
100 |
171.42 |
|
Remarks:
No Remarks
Work Program Made On:
07-03-2020 } ?>
Updation of work program on:
25-05-2022
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-January-2021 | 77.28 lakh | 2. | 22-September-2021 | 15.08 lakh | 3. | 26-November-2021 | 23.66 lakh | 4. | 31-March-2022 | 24.44 lakh | 5. | 31-May-2022 | 29.51 lakh |
Total |
169.97 lakh |
% Payment |
100 % |
|
Advance Amount: 54.29 lakh
Recovered Amount: 54.29 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 257 No. of Test Done : 276 No. of Test Passed : 271 No. of Test Failed : 5 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 7 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-08-2021 | Pilang Judav Bridge Abutment A1 1st lift casting | These photos are already uploaded earlier but not shown in portal. | Bipin Nautiyal | unknown | unknown | See Pic |
2. | 19-08-2021 | Pulang judav Bridge Abutment A1 1st lift Reinforcement checking | These photos are already uploaded earlier but not shown in the portal | Bipin Nautiyal | unknown | unknown | See Pic |
3. | 19-08-2021 | Concrete sampling in cube mould for raft. | Photos also uploaded during construction. | Bipin Nautiyal | unknown | unknown | See Pic |
4. | 19-08-2021 | Pilang Judav Bridge Abutment A1 Raft casting | Photos also uploaded during construction. | Bipin Nautiyal | unknown | unknown | See Pic |
5. | 17-08-2021 | Pilang Judav Bridge Abutment A2 Raft Reinforcement checked. | Photos are already uploaded during construction but not shown in portal. | Bipin Nautiyal | unknown | unknown | See Pic |
6. | 17-08-2021 | Pilang Judav Bridge Abutment A1 cap coarse aggregate gradation test in progress. | Photos already uploaded during construction but not shown in portal. | Bipin Nautiyal | unknown | unknown | See Pic |
7. | 25-07-2020 | Abutment A1 at Pilang judav Bridge | Abutment A1 Raft concreting on progress | Bipin Nautiyal | unknown | unknown | See Pic |
|
|