50M Span Steel Truss Motor Bridge Korigaad
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4089 |
Sanction Cost: |
580.74 lakh |
Span:
|
50.000 M |
District: |
Uttarkashi |
Block: |
Bhatwari |
Constituency: |
Gangotri |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 605
Package Name: 
UDRP/AF/33(BR)
Tender Date: 24-01-2018
Current Status: Agreement signed
Achieved on Date: 29-06-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/33(BR)
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 07-07-2018
Intended Completion Date: 26-07-2020
Original End Date: 06-10-2019 |
Total Bond Cost: 49492438.24 (494.92 lakh)
Variation Cost: -2278279.47 (-22.78 lakh) Hence Total Bond Cost is 47214158.77 (472.14 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 11556382 for 467 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 125.00 m | 18.82 | 30-06-2019 | 15-11-2019 | 125.00 m | 125.00 m | 4.41 | 18.82 | 2. | PC/CC i/c Prime Coat, Tack Coat | 1.00 KM | 2.33 | 15-07-2020 | 25-07-2020 | 1.00 KM | 1.00 KM | 0.55 | 2.33 | 3. | Parapet | 258.00 No | 8.22 | 12-11-2019 | 31-12-2019 | 258.00 No | 258.00 No | 1.93 | 8.22 | 4. | Other Allied Works & Finishing Work | 1.00 Job | 0.51 | 21-08-2020 | 31-08-2020 | 1.00 Job | 1.00 Job | 0.12 | 0.51 | 5. | Foundation RHS | 1.00 Job | 66.46 | 15-07-2018 | 30-08-2018 | 1.00 Job | 1.00 Job | 15.57 | 66.46 | 6. | Foundation LHS | 1.00 Job | 12.00 | 01-09-2018 | 01-11-2018 | 1.00 Job | 1.00 Job | 2.81 | 12.00 | 7. | Abutment Superstructure RHS | 1.00 Job | 11.23 | 20-07-2018 | 29-08-2019 | 1.00 Job | 1.00 Job | 2.63 | 11.23 | 8. | Abutment Superstructure LHS | 1.00 Job | 44.14 | 01-03-2019 | 10-04-2019 | 1.00 Job | 1.00 Job | 10.34 | 44.14 | 9. | Steel Railing/crush barrier | 87.40 m | 5.56 | 10-03-2020 | 30-07-2020 | 87.40 m | 87.40 m | 1.3 | 5.56 | 10. | Approach Ramp /path | 105.00 m | 34.28 | 01-08-2019 | 15-03-2020 | 105.00 m | 105.00 m | 8.03 | 34.28 | 11. | Protection Work | 1.00 Job | 30.50 | 15-10-2018 | 15-11-2019 | 1.00 Job | 1.00 Job | 7.15 | 30.50 | 12. | Errection Work | 1.00 Job | 30.14 | 03-10-2019 | 15-01-2020 | 1.00 Job | 1.00 Job | 7.06 | 30.14 | 13. | Gabion work | 250.00 m | 32.91 | 01-09-2018 | 30-08-2019 | 250.00 m | 250.00 m | 7.71 | 32.91 | 14. | Fabrication Work | 1.00 job | 112.59 | 01-02-2019 | 01-10-2019 | 1.00 job | 1.00 job | 26.37 | 112.59 | 15. | Fixing Bearing/Slab Casting | 1.00 job | 15.09 | 01-01-2020 | 05-03-2020 | 1.00 job | 1.00 job | 3.54 | 15.09 | 16. | Back Wall/ Approach slab | 1.00 job | 2.11 | 16-02-2020 | 28-02-2020 | 1.00 job | 1.00 job | 0.5 | 2.11 |
Total Amount: |
426.89 |
|
100 |
426.89 |
|
Remarks:
No Remarks
Work Program Made On:
28-03-2019 } ?>
Updation of work program on:
04-12-2020
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 21-December-2018 | 51.00 lakh | 2. | 30-March-2019 | 13.81 lakh | 3. | 31-May-2019 | 52.98 lakh | 4. | 16-June-2019 | 25.16 lakh | 5. | 27-August-2019 | 17.69 lakh | 6. | 18-October-2019 | 106.20 lakh | 7. | 10-December-2019 | 20.58 lakh | 8. | 02-June-2020 | 40.03 lakh | 9. | 31-July-2020 | 55.04 lakh | 10. | 11-November-2020 | 1.50 lakh | 11. | 14-December-2020 | 39.64 lakh |
Total |
423.63 lakh |
% Payment |
89.73 % |
|
Advance Amount: 47.00 lakh
Recovered Amount: 47.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 758 No. of Test Done : 801 No. of Test Passed : 801 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 183 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-07-2020 | Km 10 | Wearing coarse work is complete. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
2. | 24-06-2020 | Km 10 | Expansion strip seal fixing work in progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
3. | 24-06-2020 | Km 10 | Abutment A2 side approach road. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
4. | 24-06-2020 | Km 10 | Deck slab rainforesment work in progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
5. | 24-06-2020 | Km 10 | Deck slab rainforesment work in progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
6. | 11-06-2020 | Km 10 | Site laboratory ruteen test on progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
7. | 11-06-2020 | Km 10 | Deck slab crash barrier rainforesment work in progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
8. | 07-06-2020 | Km 10 | Abutment A2 approach road primix carpet work completed.(cold mix) | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
9. | 07-06-2020 | Km 10 | Abutment A1 side approach road primix carpet work completed.(cold mix). | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
10. | 06-06-2020 | Km 10 | After seal coat rolling work in progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
11. | 06-06-2020 | Km 10 | After primix carpet seal coat work in progress at abutment A1 side. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
12. | 06-06-2020 | Km 10 | Prime coat spray work completed at abutment A1 side approach road. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
13. | 06-06-2020 | Km 10 | Prime coat spray work in progress at abutment A1 side. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
14. | 06-06-2020 | Km 10 | Drainage spouts. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
15. | 05-06-2020 | Korigaad bridge | Deck reinforcement work is in progress at korigaad bridge in district uttarkashi. | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
16. | 05-06-2020 | Korigaad bridge | Parapet white washing work is in progress at korigaad bridge in district uttarkashi. | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
17. | 04-06-2020 | Km 10 | Steel rainforesment work in progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
18. | 04-06-2020 | Km 10 | Drain spouts fixing discussion with contractor. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
19. | 04-06-2020 | Km 10 | Bitumen emulsion stock for approach road primix carpet work. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
20. | 04-06-2020 | Km 10 | Perapet white wash work in progress. | Neeraj Pathak | QC | DSC WB Bridge Uttarkashi | See Pic |
|
|