Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

50M Span Steel Truss Motor Bridge Korigaad Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4089 Sanction Cost: 580.74  lakh Span: 50.000 M
District: Uttarkashi Block: Bhatwari Constituency: Gangotri Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 605        Package Name:  UDRP/AF/33(BR)        Tender Date: 24-01-2018        Current Status: Agreement signed        Achieved on Date: 29-06-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/33(BR)      Contractor Name: Kailash Hillways Engineering Associates
Start Date:  07-07-2018      Intended Completion Date:  26-07-2020      Original End Date:  06-10-2019
Total Bond Cost: 49492438.24 (494.92 lakh)        Variation Cost: -2278279.47 (-22.78 lakh)    Hence Total Bond Cost is   47214158.77 (472.14 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 11556382 for 467 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works125.00 m18.8230-06-201915-11-2019125.00 m125.00 m4.4118.82
2.PC/CC i/c Prime Coat, Tack Coat1.00 KM2.3315-07-202025-07-20201.00 KM1.00 KM0.552.33
3.Parapet258.00 No8.2212-11-201931-12-2019258.00 No258.00 No1.938.22
4.Other Allied Works & Finishing Work 1.00 Job0.5121-08-202031-08-20201.00 Job1.00 Job0.120.51
5.Foundation RHS1.00 Job66.4615-07-201830-08-20181.00 Job1.00 Job15.5766.46
6.Foundation LHS1.00 Job12.0001-09-201801-11-20181.00 Job1.00 Job2.8112.00
7.Abutment Superstructure RHS1.00 Job11.2320-07-201829-08-20191.00 Job1.00 Job2.6311.23
8.Abutment Superstructure LHS1.00 Job44.1401-03-201910-04-20191.00 Job1.00 Job10.3444.14
9.Steel Railing/crush barrier87.40 m5.5610-03-202030-07-202087.40 m87.40 m1.35.56
10.Approach Ramp /path 105.00 m34.2801-08-201915-03-2020105.00 m105.00 m8.0334.28
11.Protection Work1.00 Job30.5015-10-201815-11-20191.00 Job1.00 Job7.1530.50
12.Errection Work1.00 Job30.1403-10-201915-01-20201.00 Job1.00 Job7.0630.14
13.Gabion work250.00 m32.9101-09-201830-08-2019250.00 m250.00 m7.7132.91
14.Fabrication Work1.00 job112.5901-02-201901-10-20191.00 job1.00 job26.37112.59
15.Fixing Bearing/Slab Casting1.00 job15.0901-01-202005-03-20201.00 job1.00 job3.5415.09
16.Back Wall/ Approach slab1.00 job2.1116-02-202028-02-20201.00 job1.00 job0.52.11
Total Amount: 426.89 100   426.89
Remarks: No Remarks       Work Program Made On: 28-03-2019        Updation of work program on: 04-12-2020       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.21-December-201851.00  lakh
2.30-March-201913.81  lakh
3.31-May-201952.98  lakh
4.16-June-201925.16  lakh
5.27-August-201917.69  lakh
6.18-October-2019106.20  lakh
7.10-December-201920.58  lakh
8.02-June-202040.03  lakh
9.31-July-202055.04  lakh
10.11-November-20201.50  lakh
11.14-December-202039.64  lakh
Total 423.63  lakh
% Payment 89.73 %
Advance Amount:  47.00  lakh        Recovered Amount:  47.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 758   No. of Test Done : 801    No. of Test Passed : 801   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 183
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-07-2020Km 10Wearing coarse work is complete.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
2.24-06-2020Km 10Expansion strip seal fixing work in progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
3.24-06-2020Km 10Abutment A2 side approach road.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
4.24-06-2020Km 10Deck slab rainforesment work in progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
5.24-06-2020Km 10Deck slab rainforesment work in progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
6.11-06-2020Km 10Site laboratory ruteen test on progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
7.11-06-2020Km 10Deck slab crash barrier rainforesment work in progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
8.07-06-2020Km 10Abutment A2 approach road primix carpet work completed.(cold mix)Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
9.07-06-2020Km 10Abutment A1 side approach road primix carpet work completed.(cold mix).Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
10.06-06-2020Km 10After seal coat rolling work in progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
11.06-06-2020Km 10After primix carpet seal coat work in progress at abutment A1 side.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
12.06-06-2020Km 10Prime coat spray work completed at abutment A1 side approach road.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
13.06-06-2020Km 10Prime coat spray work in progress at abutment A1 side.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
14.06-06-2020Km 10Drainage spouts.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
15.05-06-2020Korigaad bridgeDeck reinforcement work is in progress at korigaad bridge in district uttarkashi.Deepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
16.05-06-2020Korigaad bridgeParapet white washing work is in progress at korigaad bridge in district uttarkashi.Deepak PantSite supervisiorUDRP AF Irrigation birahi See Pic
17.04-06-2020Km 10Steel rainforesment work in progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
18.04-06-2020Km 10Drain spouts fixing discussion with contractor.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
19.04-06-2020Km 10Bitumen emulsion stock for approach road primix carpet work.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic
20.04-06-2020Km 10Perapet white wash work in progress.Neeraj PathakQCDSC WB Bridge Uttarkashi See Pic