48m Steel Grider Bridle Bridge over Balganaga River at Village Kot
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4088 |
Sanction Cost: |
215.14 lakh |
Span:
|
48.000 M |
District: |
Tehri |
Block: |
Bhilangana |
Constituency: |
Ghanshali |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
undefined |
Type: |
Bridge |
|
Procurement: |
Package No.: 602
Package Name: 
UDRP/AF/30(BR)
Tender Date: 24-01-2018
Current Status: Agreement signed
Achieved on Date: 23-07-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/30(BR)
Contractor Name: Anil Mehta
|
Start Date: 03-08-2018
Intended Completion Date: 15-07-2020
Original End Date: 02-11-2019 |
Total Bond Cost: 17841142.17 (178.41 lakh)
Variation Cost: 151854.02 (1.52 lakh) Hence Total Bond Cost is 17992996.19 (179.93 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 4246396 for 476 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 0.00 Job | 0.00 | 15-10-2018 | 15-10-2018 | 1.00 Job | 1.00 Job | 0 | 0.00 | 2. | Foundation RHS | 1.00 Job | 7.89 | 13-12-2018 | 11-03-2019 | 1.00 Job | 1.00 Job | 5.18 | 7.89 | 3. | Foundation LHS | 1.00 Job | 7.89 | 19-11-2018 | 06-03-2019 | 1.00 Job | 1.00 Job | 5.18 | 7.89 | 4. | Fixing longitudinal Stringers/girders | 0.00 m | 0.00 | 10-08-2019 | 10-08-2019 | 0.00 m | 0.00 m | 0 | 0.00 | 5. | Fixing of chequered Plate/RCC Deck | 1.00 sqm | 8.37 | 05-11-2019 | 15-03-2020 | 1.00 sqm | 1.00 sqm | 5.49 | 8.37 | 6. | Steel Railing/crush barrier | 1.00 m | 3.19 | 20-12-2019 | 15-03-2020 | 1.00 m | 1.00 m | 2.1 | 3.19 | 7. | Approach Ramp /path | 70.00 m | 24.57 | 05-06-2019 | 15-03-2020 | 70.00 m | 70.00 m | 16.12 | 24.57 | 8. | Protection Work | 1.00 Job | 32.24 | 02-01-2019 | 15-05-2019 | 1.00 Job | 1.00 Job | 21.15 | 32.24 | 9. | Errection Work | 1.00 Job | 9.66 | 15-12-2019 | 15-03-2020 | 1.00 Job | 1.00 Job | 6.34 | 9.66 | 10. | Fabrication Work | 1.00 job | 33.68 | 10-10-2019 | 15-03-2020 | 1.00 job | 1.00 job | 22.09 | 33.68 | 11. | Abutment Substructure RHS | 1.00 Job | 12.47 | 20-03-2019 | 15-09-2019 | 1.00 Job | 1.00 Job | 8.18 | 12.47 | 12. | Abutment Substructure LHS | 1.00 Job | 12.47 | 22-03-2019 | 15-03-2020 | 1.00 Job | 1.00 Job | 8.18 | 12.47 |
Total Amount: |
152.43 |
|
100 |
152.43 |
|
Remarks:
No Remarks
Work Program Made On:
19-11-2018 } ?>
Updation of work program on:
25-11-2020
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-March-2019 | 25.05 lakh | 2. | 04-May-2019 | 19.75 lakh | 3. | 29-June-2019 | 9.69 lakh | 4. | 30-July-2019 | 12.80 lakh | 5. | 18-September-2019 | 8.22 lakh | 6. | 18-February-2020 | 38.66 lakh | 7. | 16-May-2020 | 18.55 lakh | 8. | 23-July-2020 | 34.20 lakh | 9. | 11-November-2020 | 13.03 lakh |
Total |
179.95 lakh |
% Payment |
100.02 % |
|
Advance Amount: 7.96 lakh
Recovered Amount: 7.96 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 112 No. of Test Done : 125 No. of Test Passed : 125 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 13 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-07-2020 | Kot Village 48M Steel Truss Bridge | Kot Village 48M Span Bridge Completed | Suresh Prasad | RE | BSC R&B WB Rudraprayag | See Pic |
2. | 29-07-2020 | Kot Village | Kot Village Bridge Work Complete at site. | Suresh Prasad | RE | BSC R&B WB Rudraprayag | See Pic |
3. | 16-02-2020 | Abutment A2 | BT coloumn erection work | AE Saurab Chauhan | Assistant Engineer | UDRP R&B Tehri | See Pic |
4. | 15-06-2019 | Abutment A2 | Noise pollution Test | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
5. | 15-06-2019 | Abutment A2 | Air monitoring test | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
6. | 15-06-2019 | Abutment A2 | Abutment 1st lift curing | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
7. | 11-03-2019 | Abutment A1 shaft concrete | Slum cone testing | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
8. | 11-03-2019 | Abutment A1 Raft Concrete | Abutment A1 Raft Concrete | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
9. | 16-02-2019 | Abutment A2 | Layout for Abutment A1 and A2 after Leveling course | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
10. | 16-02-2019 | Abutment A2 | Site visit World Bank | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
11. | 08-12-2018 | Fondation A2 | Foundation A2 Excavation | Saurab Chauhan | AE | UDRP R&B Tehri | See Pic |
12. | 17-11-2018 | Abutment A2 | Earth work in excavation of foundation abutment A2 | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
13. | 17-11-2018 | Abutment A1 | Site visit EE mam ,AE | Kuldeep Kumar Karanwal | JE | UDRP R&B Tehri | See Pic |
|
|