Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

48m Steel Grider Bridle Bridge over Balganaga River at Village Kot Work Completed
Project: UDRP-AF(Bridge/Slope) UID: 4088 Sanction Cost: 215.14  lakh Span: 48.000 M
District: Tehri Block: Bhilangana Constituency: Ghanshali Circle:
DEA: DEA Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: undefined Type: Bridge
Procurement:
Package No.: 602        Package Name:  UDRP/AF/30(BR)        Tender Date: 24-01-2018        Current Status: Agreement signed        Achieved on Date: 23-07-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/30(BR)      Contractor Name: Anil Mehta
Start Date:  03-08-2018      Intended Completion Date:  15-07-2020      Original End Date:  02-11-2019
Total Bond Cost: 17841142.17 (178.41 lakh)        Variation Cost: 151854.02 (1.52 lakh)    Hence Total Bond Cost is   17992996.19 (179.93 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 4246396 for 476 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 0.00 Job0.0015-10-201815-10-20181.00 Job1.00 Job00.00
2.Foundation RHS1.00 Job7.8913-12-201811-03-20191.00 Job1.00 Job5.187.89
3.Foundation LHS1.00 Job7.8919-11-201806-03-20191.00 Job1.00 Job5.187.89
4.Fixing longitudinal Stringers/girders0.00 m0.0010-08-201910-08-20190.00 m0.00 m00.00
5.Fixing of chequered Plate/RCC Deck1.00 sqm8.3705-11-201915-03-20201.00 sqm1.00 sqm5.498.37
6.Steel Railing/crush barrier1.00 m3.1920-12-201915-03-20201.00 m1.00 m2.13.19
7.Approach Ramp /path 70.00 m24.5705-06-201915-03-202070.00 m70.00 m16.1224.57
8.Protection Work1.00 Job32.2402-01-201915-05-20191.00 Job1.00 Job21.1532.24
9.Errection Work1.00 Job9.6615-12-201915-03-20201.00 Job1.00 Job6.349.66
10.Fabrication Work1.00 job33.6810-10-201915-03-20201.00 job1.00 job22.0933.68
11.Abutment Substructure RHS1.00 Job12.4720-03-201915-09-20191.00 Job1.00 Job8.1812.47
12.Abutment Substructure LHS1.00 Job12.4722-03-201915-03-20201.00 Job1.00 Job8.1812.47
Total Amount: 152.43 100   152.43
Remarks: No Remarks       Work Program Made On: 19-11-2018        Updation of work program on: 25-11-2020       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.18-March-201925.05  lakh
2.04-May-201919.75  lakh
3.29-June-20199.69  lakh
4.30-July-201912.80  lakh
5.18-September-20198.22  lakh
6.18-February-202038.66  lakh
7.16-May-202018.55  lakh
8.23-July-202034.20  lakh
9.11-November-202013.03  lakh
Total 179.95  lakh
% Payment 100.02 %
Advance Amount:  7.96  lakh        Recovered Amount:  7.96  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 112   No. of Test Done : 125    No. of Test Passed : 125   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 13
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-07-2020Kot Village 48M Steel Truss BridgeKot Village 48M Span Bridge CompletedSuresh PrasadREBSC R&B WB Rudraprayag See Pic
2.29-07-2020Kot VillageKot Village Bridge Work Complete at site.Suresh PrasadREBSC R&B WB Rudraprayag See Pic
3.16-02-2020Abutment A2BT coloumn erection workAE Saurab ChauhanAssistant EngineerUDRP R&B Tehri See Pic
4.15-06-2019Abutment A2Noise pollution TestSaurab ChauhanAEUDRP R&B Tehri See Pic
5.15-06-2019Abutment A2Air monitoring testSaurab ChauhanAEUDRP R&B Tehri See Pic
6.15-06-2019Abutment A2Abutment 1st lift curingSaurab ChauhanAEUDRP R&B Tehri See Pic
7.11-03-2019Abutment A1 shaft concreteSlum cone testingSaurab ChauhanAEUDRP R&B Tehri See Pic
8.11-03-2019Abutment A1 Raft ConcreteAbutment A1 Raft ConcreteSaurab ChauhanAEUDRP R&B Tehri See Pic
9.16-02-2019Abutment A2Layout for Abutment A1 and A2 after Leveling courseKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
10.16-02-2019Abutment A2Site visit World BankKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
11.08-12-2018Fondation A2Foundation A2 ExcavationSaurab ChauhanAEUDRP R&B Tehri See Pic
12.17-11-2018Abutment A2Earth work in excavation of foundation abutment A2Kuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic
13.17-11-2018Abutment A1Site visit EE mam ,AEKuldeep Kumar KaranwalJEUDRP R&B Tehri See Pic