120m span bridle Suspension Bridge at Piplogi
Work Completed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4087 |
Sanction Cost: |
988.42 lakh |
Span:
|
120.000 M |
District: |
Tehri |
Block: |
Pratapnagar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 606
Package Name: 
UDRP/AF/29(BR)
Tender Date: 07-02-2018
Current Status: Agreement signed
Achieved on Date: 02-07-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/29(BR)
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 12-07-2018
Intended Completion Date: 27-07-2021
Original End Date: 11-10-2019 |
Total Bond Cost: 85440257.95 (854.4 lakh)
Variation Cost: 1331444.34 (13.31 lakh) Hence Total Bond Cost is 86771702.29 (867.72 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 37123680 for 869 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 22.63 | 25-04-2019 | 12-05-2021 | 1.00 Job | 1.00 Job | 2.92 | 22.63 | 2. | Foundation RHS | 0.00 Job | 0.00 | 13-12-2018 | 13-12-2018 | 0.00 Job | 0.00 Job | 0 | 0.00 | 3. | Foundation RHS (Step 2) | 1.00 Job | 2.59 | 16-05-2019 | 25-10-2020 | 1.00 Job | 1.00 Job | 0.34 | 2.59 | 4. | Foundation LHS | 0.00 Job | 0.00 | 15-02-2019 | 15-02-2019 | 0.00 Job | 0.00 Job | 0 | 0.00 | 5. | Foundation LHS (Step 2) | 1.00 Job | 2.59 | 20-04-2019 | 25-03-2020 | 1.00 Job | 1.00 Job | 0.34 | 2.59 | 6. | Abutment Superstructure RHS | 1.00 Job | 56.12 | 15-10-2020 | 01-01-2021 | 1.00 Job | 1.00 Job | 7.24 | 56.12 | 7. | Abutment Superstructure LHS | 1.00 Job | 56.12 | 15-08-2019 | 30-07-2020 | 1.00 Job | 1.00 Job | 7.24 | 56.12 | 8. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 170.37 | 15-07-2019 | 25-04-2021 | 1.00 job | 1.00 job | 21.99 | 170.37 | 9. | Anchor Block for Wind Cable: Reinforcement, Lewis | 1.00 job | 92.87 | 01-01-2020 | 30-04-2021 | 1.00 job | 1.00 job | 11.99 | 92.87 | 10. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 9.18 | 05-04-2021 | 15-04-2021 | 2.00 no | 2.00 no | 1.19 | 9.18 | 11. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 15.76 | 17-01-2021 | 15-04-2021 | 4.00 no | 4.00 no | 2.03 | 15.76 | 12. | Fixing Suspenders to Main cable with clamps and Ha | 154.00 no | 5.24 | 12-04-2021 | 22-04-2021 | 154.00 no | 154.00 no | 0.68 | 5.24 | 13. | Stretching Wind Guy cable, Fixing wind Ties with | 574.00 m | 20.35 | 19-04-2021 | 29-04-2021 | 574.00 m | 574.00 m | 2.63 | 20.35 | 14. | Fixing longitudinal Stringers/girders | 120.00 m | 12.48 | 27-04-2021 | 01-05-2021 | 120.00 m | 120.00 m | 1.61 | 12.48 | 15. | Fixing of chequered Plate/RCC Deck | 306.00 sqm | 4.65 | 02-05-2021 | 07-05-2021 | 306.00 sqm | 306.00 sqm | 0.6 | 4.65 | 16. | Steel Railing/crush barrier | 240.00 m | 8.93 | 07-05-2021 | 10-05-2021 | 240.00 m | 240.00 m | 1.15 | 8.93 | 17. | Approach Ramp /path | 100.00 m | 18.63 | 15-04-2021 | 04-05-2021 | 100.00 m | 100.00 m | 2.4 | 18.63 | 18. | Protection Work | 1.00 Job | 35.19 | 15-05-2019 | 05-05-2021 | 1.00 Job | 1.00 Job | 4.54 | 35.19 | 19. | Errection Work | 1.00 Job | 23.40 | 25-11-2020 | 15-04-2021 | 1.00 Job | 1.00 Job | 3.02 | 23.40 | 20. | Gabion work | 2400.00 m | 65.20 | 15-04-2019 | 01-05-2021 | 2400.00 m | 2400.00 m | 8.42 | 65.20 | 21. | PCC in Foundation | 261.00 cum | 8.50 | 25-04-2019 | 15-10-2020 | 261.00 cum | 261.00 cum | 1.1 | 8.50 | 22. | Excavation in soil | 5734.00 cum | 13.19 | 20-04-2019 | 15-10-2020 | 5734.00 cum | 5734.00 cum | 1.7 | 13.19 | 23. | Fabrication Work | 1.00 job | 130.75 | 30-04-2019 | 25-12-2019 | 1.00 job | 1.00 job | 16.88 | 130.75 |
Total Amount: |
774.74 |
|
100 |
774.74 |
|
Remarks:
No Remarks
Work Program Made On:
15-05-2019 } ?>
Updation of work program on:
03-04-2021
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 19-March-2020 | 212.36 lakh | 2. | 11-November-2020 | 208.17 lakh | 3. | 19-December-2020 | 43.64 lakh | 4. | 04-February-2021 | 42.14 lakh | 5. | 19-February-2021 | 17.54 lakh | 6. | 30-March-2021 | 95.09 lakh | 7. | 31-May-2021 | 70.78 lakh | 8. | 09-July-2021 | 59.20 lakh | 9. | 28-October-2021 | 32.07 lakh | 10. | 31-March-2022 | 20.59 lakh |
Total |
801.58 lakh |
% Payment |
92.38 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 746 No. of Test Done : 746 No. of Test Passed : 745 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 91.97 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 51 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-01-2022 | Piplogi BR-29 | Top view | Suresh Prasad | ` | ` | See Pic |
2. | 21-01-2022 | Piplogi BR-29 | Top view from Piplogi gaon | Suresh Prasad | ` | ` | See Pic |
3. | 21-01-2022 | Piplogi BR-29 | Side view from approach Piplogi gaon to suspension bridge Lambgaon | Suresh Prasad | ` | ` | See Pic |
4. | 21-01-2022 | Piplogi BR-29 | Piplogi ganow view from center of suspension bridge | Suresh Prasad | ` | ` | See Pic |
5. | 21-01-2022 | Piplogi BR-29 | Lambgaon view from center of suspension bridge | Suresh Prasad | ` | ` | See Pic |
6. | 21-01-2022 | Piplogi BR-29 | Project completed final view. Open the public. | Suresh Prasad | ` | ` | See Pic |
7. | 21-01-2022 | Piplogi BR-29 | LHS side Approach road with Temple from Lambgaon t to Piplogi | Suresh Prasad | ` | ` | See Pic |
8. | 21-01-2022 | Piplogi BR-29 | Approach road LHS side Lambgaon to Piplogi | Suresh Prasad | ` | ` | See Pic |
9. | 21-01-2022 | Piplogi BR-29 | Top View of suspension bridge | SURESH PRASAD | ` | ` | See Pic |
10. | 07-07-2021 | Piplogi BR-29 | Piplogi BR-29 | Suresh Prasad | ` | ` | See Pic |
11. | 07-07-2021 | Piplogi BR-29 | Piplogi BR-29 Suspension Bridge over Jalkur river Completed | Suresh Prasad | ` | ` | See Pic |
12. | 03-07-2021 | Piplogi BR-29 Helth Camp | Piplogi BR-29 Helth Camp | Suresh Prasad | ` | ` | See Pic |
13. | 03-07-2021 | Piplogi BR-29 Abutment A1 Side | Abutment A1 Side Tower and Anchor completed | Suresh Prasad | ` | ` | See Pic |
14. | 26-06-2021 | A2 side Anchor block white washing wip | A2 Side Anchor block white washing wip | PARAMBEER SINGH RAWAT | ` | ` | See Pic |
15. | 26-06-2021 | Tower erection work and decking work completed | Tower erection and decking work completed | PARAMBEER SINGH RAWAT | ` | ` | See Pic |
16. | 19-02-2021 | A1 side tower erection wip. | Tower erection wip. | PARAMBEER SINGH RAWAT | ` | ` | See Pic |
17. | 21-01-2021 | PIPLOGI Abutment A1 side Tower Erection work in progress. | Piplogi Suspension bridge Abutment A1 side tower erection wip | Deepak Pant | Site supervisior | UDRP AF Irrigation birahi | See Pic |
18. | 08-09-2020 | Abutment A1 | Anutment RCC and approach road wall | AE Saurab Chauhan | Assistant Engineer | UDRP R&B Tehri | See Pic |
19. | 13-08-2020 | A1 side anchor block 2nd lift wall shuttering wip | Anchor block 2nd lift wall shuttering wip | PARAMBEER SINGH RAWAT | unknown | unknown | See Pic |
20. | 29-07-2020 | Anchor block A1 side 2nd lift wall steel binding wip | Anchor block 2nd lift wall steel binding wip | PARAMBEER SINGH RAWAT | unknown | unknown | See Pic |
|
|