Bridge at Tulka Sirga Kunasa Badasu River
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4078 |
Sanction Cost: |
929.72 lakh |
Span:
|
90.000 M |
District: |
Uttarkashi |
Block: |
Mori |
Constituency: |
Purola |
Circle: |
|
DEA: |
DEA Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 655
Package Name: 
UDRP/AF/BR/58
Tender Date: 05-09-2020
Current Status: Agreement signed
Achieved on Date: 23-12-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/58
Contractor Name: Kailash Hillways Engineering Associates
|
Start Date: 08-01-2021
Intended Completion Date: 17-05-2023
Original End Date: 31-03-2022 |
Total Bond Cost: 89909594.59 (899.1 lakh)
Variation Cost: 8360183.91 (83.6 lakh) Hence Total Bond Cost is 98269778.5 (982.7 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1753245 for 39 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Other Allied Works & Finishing Work | 1.00 Job | 2.00 | 08-01-2021 | 26-09-2022 | 1.00 Job | 0.50 Job | 0.12 | 1.00 | 2. | Foundation RHS | 1.00 Job | 14.80 | 01-02-2021 | 10-06-2022 | 1.00 Job | 0.85 Job | 1.57 | 12.58 | 3. | Foundation LHS | 1.00 Job | 15.60 | 08-01-2021 | 31-12-2021 | 1.00 Job | 1.00 Job | 1.94 | 15.60 | 4. | Abutment Superstructure RHS | 1.00 Job | 101.40 | 20-02-2022 | 02-05-2022 | 1.00 Job | 0.00 Job | 0 | 0.00 | 5. | Abutment Superstructure LHS | 1.00 Job | 160.80 | 15-01-2022 | 11-06-2022 | 1.00 Job | 0.50 Job | 10.02 | 80.40 | 6. | Anchor Block Main Cable Reinforcement (3-4 Times) | 1.00 job | 165.92 | 04-05-2022 | 29-05-2022 | 1.00 job | 0.70 job | 14.47 | 116.14 | 7. | Anchor Block for Wind Cable: Reinforcement, Lewis | 1.00 job | 71.16 | 06-05-2022 | 02-06-2022 | 1.00 job | 0.00 job | 0 | 0.00 | 8. | Deck Cable laying, stretching and Fixing Transoms/Deck Slab | 2.00 no | 18.34 | 04-06-2022 | 22-06-2022 | 2.00 no | 0.00 no | 0 | 0.00 | 9. | Fixing of Saddle pulley along with Rib plate and | 4.00 no | 12.75 | 26-06-2022 | 08-07-2022 | 4.00 no | 0.00 no | 0 | 0.00 | 10. | Fixing Suspenders to Main cable with clamps and Ha | 114.00 no | 8.04 | 24-06-2022 | 10-07-2022 | 114.00 no | 0.00 no | 0 | 0.00 | 11. | Stretching Wind Guy cable, Fixing wind Ties with | 1528.00 m | 28.56 | 28-06-2022 | 15-07-2022 | 1528.00 m | 0.00 m | 0 | 0.00 | 12. | Fixing longitudinal Stringers/girders | 270.00 m | 10.25 | 20-06-2022 | 20-07-2022 | 270.00 m | 0.00 m | 0 | 0.00 | 13. | Fixing of chequered Plate/RCC Deck | 170.00 sqm | 6.72 | 23-07-2022 | 01-08-2022 | 170.00 sqm | 0.00 sqm | 0 | 0.00 | 14. | Steel Railing/crush barrier | 180.00 m | 0.20 | 01-08-2022 | 05-08-2022 | 180.00 m | 0.00 m | 0 | 0.00 | 15. | Approach Ramp /path | 100.00 m | 32.58 | 06-08-2022 | 10-08-2022 | 100.00 m | 30.00 m | 1.22 | 9.77 | 16. | Protection Work | 1.00 Job | 10.30 | 15-03-2021 | 06-09-2022 | 1.00 Job | 0.55 Job | 0.71 | 5.66 | 17. | Errection Work | 54.20 Job | 25.06 | 16-03-2022 | 28-07-2022 | 54.20 Job | 0.00 Job | 0 | 0.00 | 18. | Gabion work | 960.00 m | 27.60 | 20-04-2021 | 26-08-2022 | 960.00 m | 400.00 m | 1.43 | 11.50 | 19. | PCC in Foundation | 88.70 cum | 9.22 | 10-05-2021 | 25-01-2022 | 88.70 cum | 50.93 cum | 0.66 | 5.29 | 20. | Excavation in soil | 5732.40 cum | 9.80 | 15-03-2021 | 28-01-2022 | 5732.40 cum | 5732.40 cum | 1.22 | 9.80 | 21. | Fabrication Work | 54.20 job | 71.67 | 01-08-2021 | 15-03-2022 | 54.20 job | 54.20 job | 8.93 | 71.67 |
Total Amount: |
802.77 |
|
42.28 |
339.41 |
|
Remarks:
No Remarks
Work Program Made On:
20-02-2021 } ?>
Updation of work program on:
17-05-2022
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 03-September-2021 | 77.14 lakh | 2. | 26-November-2021 | 155.99 lakh | 3. | 05-February-2022 | 69.12 lakh | 4. | 31-March-2022 | 99.42 lakh | 5. | 10-May-2022 | 51.40 lakh | 6. | 15-June-2022 | 45.77 lakh | 7. | 06-July-2022 | 77.48 lakh | 8. | 20-October-2022 | 30.68 lakh | 9. | 24-November-2022 | 46.76 lakh | 10. | 29-December-2022 | 54.12 lakh | 11. | 14-February-2023 | 73.67 lakh | 12. | 25-March-2023 | 61.86 lakh | 13. | 08-May-2023 | 85.82 lakh | 14. | 21-August-2023 | 53.45 lakh |
Total |
982.68 lakh |
% Payment |
109.3 % |
|
Advance Amount: 20.00 lakh
Recovered Amount: 100.00 lakh
Balance to be Recovered -80.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 499 No. of Test Done : 511 No. of Test Passed : 500 No. of Test Failed : 2
No. of Test Result Awaited : 9
Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.47 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 113 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-06-2022 | BR 58 taluka sirga | Abutement A1 LHS 4th lift part 1 concrete completed | Manoj sain QC | ` | ` | See Pic |
2. | 25-06-2022 | BR 58 taluka sirga | Anchor block 4th lift Plum concrete work is in progress | Manoj sain QC | ` | ` | See Pic |
3. | 25-06-2022 | BR 58 Taluka sirga | Leval checking of Abutement A1 | Manp | ` | ` | See Pic |
4. | 25-06-2022 | BR 58 taluka sirga | RR work is in Progress in A1Side approach road | Manoj sain QC | ` | ` | See Pic |
5. | 17-06-2022 | BR 58 | Abutment A1 side main anchor block 3rd slab is in progress (Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
6. | 17-06-2022 | BR 58 | Abutment A1 third slab first lift has been completed Vijay Shekhar Naudiyal) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
7. | 17-06-2022 | BR58 | Taluka bridge A1 site main anchor block 3rd slab concrete work is on progress. | Yashpal Rawat | unknown | unknown | See Pic |
8. | 17-06-2022 | BR58 | Taluka bridge A1 site abument 3rd slab 1St lift concrete work is complete . | Yashpal Rawat | unknown | unknown | See Pic |
9. | 17-06-2022 | BR58 | Taluka bridge A1 site main anchor block 3rd slab reinforcement work is on is in progress. | Yashpal Rawat | unknown | unknown | See Pic |
10. | 10-06-2022 | BR58 | Taluka bridge A1 site 3rd lift shuttering work is on progress. | Yashpal Rawat | unknown | unknown | See Pic |
11. | 10-06-2022 | BR58 | taluka bridge A1 site 3rd lift shuttering work is on progress. | Yashpal Rawat | unknown | unknown | See Pic |
12. | 10-06-2022 | BR58 | Taluka bridge A1 site main anchor block shuttering work is on progress. | Yashpal Rawat | unknown | unknown | See Pic |
13. | 10-06-2022 | BR58 | Taluka bridge A1 site main anchor block concert work is on progress. | Yashpal Rawat | unknown | unknown | See Pic |
14. | 27-05-2022 | Taluka bridge A1 site main abutment 3rd part lift concert work is on progress. | BR 58 | Yashpal Rawat | unknown | unknown | See Pic |
15. | 27-05-2022 | BR58 | Taluka bridge A1 site main anchor block 2 nd lift part 2 plum concrete work done. | Yashpal Rawat | unknown | unknown | See Pic |
16. | 27-05-2022 | BR 58 Taluka sirga | Abutement A2 side leval checking is in progress | Manoj Sain QC | ` | ` | See Pic |
17. | 27-05-2022 | BR 58 Taluka sirga | Abutement A2 side leval checking | Manoj sain Qc | ` | ` | See Pic |
18. | 27-05-2022 | BR 58 Taluka sirga | A1 side Main Abutment 3rd lift part 2 concrete work is in Progress | Manoj sain Qc | ` | ` | See Pic |
19. | 26-05-2022 | BR 58 Taluka sirga | Abutment A1 side main anchor 2nd lift part 2 Plum concrete work done | Manoj sain QC | ` | ` | See Pic |
20. | 24-05-2022 | BR 58 | Mini crusher shifted abutment A2 side (Manoj Sain QC) | ????y ??????? ?????y?? ,? | unknown | unknown | See Pic |
|
|