Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge at Tulka Sirga Kunasa Badasu River Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4078 Sanction Cost: 929.72  lakh Span: 90.000 M
District: Uttarkashi Block: Mori Constituency: Purola Circle:
DEA: DEA Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 655        Package Name:  UDRP/AF/BR/58        Tender Date: 05-09-2020        Current Status: Agreement signed        Achieved on Date: 23-12-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/58      Contractor Name: Kailash Hillways Engineering Associates
Start Date:  08-01-2021      Intended Completion Date:  17-05-2023      Original End Date:  31-03-2022
Total Bond Cost: 89909594.59 (899.1 lakh)        Variation Cost: 8360183.91 (83.6 lakh)    Hence Total Bond Cost is   98269778.5 (982.7 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1753245 for 39 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Other Allied Works & Finishing Work 1.00 Job2.0008-01-202126-09-20221.00 Job0.50 Job0.121.00
2.Foundation RHS1.00 Job14.8001-02-202110-06-20221.00 Job0.85 Job1.5712.58
3.Foundation LHS1.00 Job15.6008-01-202131-12-20211.00 Job1.00 Job1.9415.60
4.Abutment Superstructure RHS1.00 Job101.4020-02-202202-05-20221.00 Job0.00 Job00.00
5.Abutment Superstructure LHS1.00 Job160.8015-01-202211-06-20221.00 Job0.50 Job10.0280.40
6.Anchor Block Main Cable Reinforcement (3-4 Times) 1.00 job165.9204-05-202229-05-20221.00 job0.70 job14.47116.14
7.Anchor Block for Wind Cable: Reinforcement, Lewis 1.00 job71.1606-05-202202-06-20221.00 job0.00 job00.00
8.Deck Cable laying, stretching and Fixing Transoms/Deck Slab 2.00 no18.3404-06-202222-06-20222.00 no0.00 no00.00
9.Fixing of Saddle pulley along with Rib plate and 4.00 no12.7526-06-202208-07-20224.00 no0.00 no00.00
10.Fixing Suspenders to Main cable with clamps and Ha114.00 no8.0424-06-202210-07-2022114.00 no0.00 no00.00
11.Stretching Wind Guy cable, Fixing wind Ties with 1528.00 m28.5628-06-202215-07-20221528.00 m0.00 m00.00
12.Fixing longitudinal Stringers/girders270.00 m10.2520-06-202220-07-2022270.00 m0.00 m00.00
13.Fixing of chequered Plate/RCC Deck170.00 sqm6.7223-07-202201-08-2022170.00 sqm0.00 sqm00.00
14.Steel Railing/crush barrier180.00 m0.2001-08-202205-08-2022180.00 m0.00 m00.00
15.Approach Ramp /path 100.00 m32.5806-08-202210-08-2022100.00 m30.00 m1.229.77
16.Protection Work1.00 Job10.3015-03-202106-09-20221.00 Job0.55 Job0.715.66
17.Errection Work54.20 Job25.0616-03-202228-07-202254.20 Job0.00 Job00.00
18.Gabion work960.00 m27.6020-04-202126-08-2022960.00 m400.00 m1.4311.50
19.PCC in Foundation88.70 cum9.2210-05-202125-01-202288.70 cum50.93 cum0.665.29
20.Excavation in soil5732.40 cum9.8015-03-202128-01-20225732.40 cum5732.40 cum1.229.80
21.Fabrication Work54.20 job71.6701-08-202115-03-202254.20 job54.20 job8.9371.67
Total Amount: 802.77 42.28   339.41
Remarks: No Remarks       Work Program Made On: 20-02-2021        Updation of work program on: 17-05-2022       
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.03-September-202177.14  lakh
2.26-November-2021155.99  lakh
3.05-February-202269.12  lakh
4.31-March-202299.42  lakh
5.10-May-202251.40  lakh
6.15-June-202245.77  lakh
7.06-July-202277.48  lakh
8.20-October-202230.68  lakh
9.24-November-202246.76  lakh
10.29-December-202254.12  lakh
11.14-February-202373.67  lakh
12.25-March-202361.86  lakh
13.08-May-202385.82  lakh
14.21-August-202353.45  lakh
Total 982.68  lakh
% Payment 109.3 %
Advance Amount:  20.00  lakh        Recovered Amount:  100.00  lakh        Balance to be Recovered  -80.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level): Glove
Detailed report of this subproject
Quality
No. of Test Required : 499   No. of Test Done : 511    No. of Test Passed : 500   No. of Test Failed : 2    No. of Test Result Awaited : 9     Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.47
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 113
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-06-2022BR 58 taluka sirgaAbutement A1 LHS 4th lift part 1 concrete completedManoj sain QC ` ` See Pic
2.25-06-2022BR 58 taluka sirgaAnchor block 4th lift Plum concrete work is in progressManoj sain QC ` ` See Pic
3.25-06-2022BR 58 Taluka sirgaLeval checking of Abutement A1Manp ` ` See Pic
4.25-06-2022BR 58 taluka sirgaRR work is in Progress in A1Side approach roadManoj sain QC ` ` See Pic
5.17-06-2022BR 58Abutment A1 side main anchor block 3rd slab is in progress (Vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
6.17-06-2022BR 58Abutment A1 third slab first lift has been completed Vijay Shekhar Naudiyal)????y ??????? ?????y?? ,?unknownunknown See Pic
7.17-06-2022BR58Taluka bridge A1 site main anchor block 3rd slab concrete work is on progress.Yashpal Rawatunknownunknown See Pic
8.17-06-2022BR58Taluka bridge A1 site abument 3rd slab 1St lift concrete work is complete .Yashpal Rawatunknownunknown See Pic
9.17-06-2022BR58Taluka bridge A1 site main anchor block 3rd slab reinforcement work is on is in progress.Yashpal Rawatunknownunknown See Pic
10.10-06-2022BR58Taluka bridge A1 site 3rd lift shuttering work is on progress.Yashpal Rawatunknownunknown See Pic
11.10-06-2022BR58taluka bridge A1 site 3rd lift shuttering work is on progress.Yashpal Rawatunknownunknown See Pic
12.10-06-2022BR58Taluka bridge A1 site main anchor block shuttering work is on progress.Yashpal Rawatunknownunknown See Pic
13.10-06-2022BR58Taluka bridge A1 site main anchor block concert work is on progress.Yashpal Rawatunknownunknown See Pic
14.27-05-2022Taluka bridge A1 site main abutment 3rd part lift concert work is on progress.BR 58Yashpal Rawatunknownunknown See Pic
15.27-05-2022BR58Taluka bridge A1 site main anchor block 2 nd lift part 2 plum concrete work done.Yashpal Rawatunknownunknown See Pic
16.27-05-2022BR 58 Taluka sirgaAbutement A2 side leval checking is in progressManoj Sain QC ` ` See Pic
17.27-05-2022BR 58 Taluka sirgaAbutement A2 side leval checkingManoj sain Qc ` ` See Pic
18.27-05-2022BR 58 Taluka sirgaA1 side Main Abutment 3rd lift part 2 concrete work is in ProgressManoj sain Qc ` ` See Pic
19.26-05-2022BR 58 Taluka sirgaAbutment A1 side main anchor 2nd lift part 2 Plum concrete work doneManoj sain QC ` ` See Pic
20.24-05-2022BR 58Mini crusher shifted abutment A2 side (Manoj Sain QC)????y ??????? ?????y?? ,?unknownunknown See Pic