Bridge at Village Jakhani Rodha Gadera
Agreement signed
|
Project: |
UDRP-AF(Bridge/Slope) |
UID: |
4076 |
Sanction Cost: |
290.06 lakh |
Span:
|
36.000 M |
District: |
Chamoli |
Block: |
Ghat |
Constituency: |
Tharali |
Circle: |
|
DEA: |
DEA Karanprayag |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
Type: |
Bridge |
|
Procurement: |
Package No.: 652
Package Name: 
UDRP/AF/BR/73
Tender Date: 05-09-2020
Current Status: Agreement signed
Achieved on Date: 23-12-2020 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/AF/BR/73
Contractor Name: Anil Mehta
|
Start Date: 08-01-2021
Intended Completion Date: 30-06-2022
Original End Date: 07-01-2022 |
Total Bond Cost: 30982576.96 (309.83 lakh)
Variation Cost: -1698509.92 (-16.99 lakh) Hence Total Bond Cost is 29284067.04 (292.84 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 6769567 for 437 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Env. Man & Moni Plan | 1.00 Job | 5.28 | 01-04-2021 | 28-05-2022 | 1.00 Job | 1.00 Job | 1.76 | 5.28 | 2. | Other Allied Works & Finishing Work | 1.00 Job | 1.76 | 15-03-2021 | 28-05-2022 | 1.00 Job | 1.00 Job | 0.59 | 1.76 | 3. | Foundation RHS | 1.00 Job | 10.50 | 10-01-2021 | 31-05-2021 | 1.00 Job | 1.00 Job | 3.5 | 10.50 | 4. | Foundation LHS | 1.00 Job | 10.50 | 01-02-2021 | 01-06-2021 | 1.00 Job | 1.00 Job | 3.5 | 10.50 | 5. | Abutment Superstructure RHS | 1.00 Job | 0.28 | 05-04-2022 | 10-05-2022 | 1.00 Job | 1.00 Job | 0.09 | 0.28 | 6. | Abutment Superstructure LHS | 1.00 Job | 0.28 | 05-03-2022 | 10-03-2022 | 1.00 Job | 1.00 Job | 0.09 | 0.28 | 7. | Steel Railing/crush barrier | 74.00 m | 1.32 | 08-05-2022 | 12-05-2022 | 74.00 m | 74.00 m | 0.44 | 1.32 | 8. | Approach Ramp /path | 100.00 m | 29.62 | 15-04-2022 | 17-06-2022 | 100.00 m | 100.00 m | 9.87 | 29.62 | 9. | Protection Work | 1.00 Job | 69.45 | 20-11-2021 | 22-06-2022 | 1.00 Job | 1.00 Job | 23.15 | 69.45 | 10. | Errection Work | 1.00 Job | 34.20 | 05-02-2022 | 05-04-2022 | 1.00 Job | 1.00 Job | 11.4 | 34.20 | 11. | Fabrication Work | 1.00 job | 68.78 | 10-09-2021 | 20-11-2021 | 1.00 job | 1.00 job | 22.93 | 68.78 | 12. | Abutment Substructure RHS | 1.00 Job | 33.25 | 10-06-2021 | 30-01-2022 | 1.00 Job | 1.00 Job | 11.09 | 33.25 | 13. | Abutment Substructure LHS | 1.00 Job | 33.25 | 20-11-2021 | 30-01-2022 | 1.00 Job | 1.00 Job | 11.09 | 33.25 | 14. | Fixing Bearing/Slab Casting | 1.00 job | 1.54 | 10-04-2022 | 10-05-2022 | 1.00 job | 1.00 job | 0.51 | 1.54 |
Total Amount: |
300.01 |
|
100 |
300.01 |
|
Remarks:
No Remarks
Work Program Made On:
23-01-2021 } ?>
Updation of work program on:
25-01-2023
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-February-2021 | 4.94 lakh | 2. | 31-May-2021 | 18.77 lakh | 3. | 04-September-2021 | 10.95 lakh | 4. | 22-November-2021 | 76.13 lakh | 5. | 02-February-2022 | 34.95 lakh | 6. | 26-March-2022 | 15.49 lakh | 7. | 31-March-2022 | 35.53 lakh | 8. | 21-May-2022 | 22.51 lakh | 9. | 31-May-2022 | 26.43 lakh |
Total |
245.7 lakh |
% Payment |
79.3 % |
|
Advance Amount: 15.79 lakh
Recovered Amount: 15.79 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 875 No. of Test Done : 875 No. of Test Passed : 874 No. of Test Failed : 1 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.84 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 88 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 20-06-2022 | Bridge from A1 side | Bridge is ready for safe movement | Manish Rana | ` | ` | See Pic |
2. | 17-06-2022 | Jakhani-Rodha Bridge Br/73 District-Chamoli | Picture from A2 side | Er Vipin Tomar, AE | ` | ` | See Pic |
3. | 17-06-2022 | Jakhani-Rodha Bridge Br/73 District-Chamoli | Bridge work almost Complete | Er. Vipin Tomar, AE | ` | ` | See Pic |
4. | 03-06-2022 | Jakhani-Rodha Gedhra Br/73 | Painting work completed | Er. Vipin Tomar AE | ` | ` | See Pic |
5. | 26-04-2022 | Jakhani-Rodha | Concrete pouring in protection retaining wall | Er. Vipin Tomar, AE | ` | ` | See Pic |
6. | 31-03-2022 | Jakhni Rodha gadhera | RR wall missionary work in progress behind Abutment A1 | PUNIT SINGH NEGI | ` | ` | See Pic |
7. | 31-03-2022 | Jakhni Rodha gadhera | structure steel Erection work in progress | PUNIT SINGH NEGI | ` | ` | See Pic |
8. | 28-03-2022 | Jhakni-Rodha Bridge, Br/73 , Rudraprayag | Bearing Inspection | Er.Vipin Tomar, AE | ` | ` | See Pic |
9. | 04-03-2022 | BR73 | DPT test in progress for POT PTFE BEARING | Rohit Kumar Dubey | ` | ` | See Pic |
10. | 04-03-2022 | BR73 | POT PTFE Bearing testing in progress | Rohit Kumar Dubey | ` | ` | See Pic |
11. | 04-03-2022 | BR73 | POT PTFE Bearing testing in progress | Rohit Kumar Dubey | ` | ` | See Pic |
12. | 28-02-2022 | Jakhni Rodha gadhera | Slump test M35 gread of concrete | PUNIT SINGH NEGI | ` | ` | See Pic |
13. | 28-02-2022 | Jakhni Rodha gadhera | Slump test M35 gread of concrete | PUNIT SINGH NEGI | ` | ` | See Pic |
14. | 28-02-2022 | Jakhni Rodha gadhera | Concrete pouring in protection wall | PUNIT SINGH NEGI | ` | ` | See Pic |
15. | 24-02-2022 | Jakhni Rodha gadhera | Concrete pouring in Abutment A2 retaining wall | PUNIT SINGH NEGI | ` | ` | See Pic |
16. | 23-02-2022 | Jakhni Rodha gadhera | Concrete pouring in Abutment A2 side retaining wall | PUNIT SINGH NEGI | ` | ` | See Pic |
17. | 23-02-2022 | Jakhni Rodha gadhera | M35 Cube testing | PUNIT SINGH NEGI | ` | ` | See Pic |
18. | 20-02-2022 | Jhakni-Rodha Bridge, Chamoli (Br/73) | Cube casting for M35 | Er. Vipin Tomar, AE | ` | ` | See Pic |
19. | 20-02-2022 | Jhakni-Rodha Bridge, Chamoli
(Br/73) | Measurement checked of Reinforcement | Er. Vipin Tomar | ` | ` | See Pic |
20. | 20-02-2022 | Jhakani- Rodha Bridge, Chamoli (Br/73) | Cube casting for M35 | Er. Vipin Toamr, AE | ` | ` | See Pic |
|
|