Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bridge at Village Jakhani Rodha Gadera Agreement signed
Project: UDRP-AF(Bridge/Slope) UID: 4076 Sanction Cost: 290.06  lakh Span: 36.000 M
District: Chamoli Block: Ghat Constituency: Tharali Circle:
DEA: DEA Karanprayag DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision Type: Bridge
Procurement:
Package No.: 652        Package Name:  UDRP/AF/BR/73        Tender Date: 05-09-2020        Current Status: Agreement signed        Achieved on Date: 23-12-2020

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/AF/BR/73      Contractor Name: Anil Mehta
Start Date:  08-01-2021      Intended Completion Date:  30-06-2022      Original End Date:  07-01-2022
Total Bond Cost: 30982576.96 (309.83 lakh)        Variation Cost: -1698509.92 (-16.99 lakh)    Hence Total Bond Cost is   29284067.04 (292.84 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 6769567 for 437 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Env. Man & Moni Plan1.00 Job5.2801-04-202128-05-20221.00 Job1.00 Job1.765.28
2.Other Allied Works & Finishing Work 1.00 Job1.7615-03-202128-05-20221.00 Job1.00 Job0.591.76
3.Foundation RHS1.00 Job10.5010-01-202131-05-20211.00 Job1.00 Job3.510.50
4.Foundation LHS1.00 Job10.5001-02-202101-06-20211.00 Job1.00 Job3.510.50
5.Abutment Superstructure RHS1.00 Job0.2805-04-202210-05-20221.00 Job1.00 Job0.090.28
6.Abutment Superstructure LHS1.00 Job0.2805-03-202210-03-20221.00 Job1.00 Job0.090.28
7.Steel Railing/crush barrier74.00 m1.3208-05-202212-05-202274.00 m74.00 m0.441.32
8.Approach Ramp /path 100.00 m29.6215-04-202217-06-2022100.00 m100.00 m9.8729.62
9.Protection Work1.00 Job69.4520-11-202122-06-20221.00 Job1.00 Job23.1569.45
10.Errection Work1.00 Job34.2005-02-202205-04-20221.00 Job1.00 Job11.434.20
11.Fabrication Work1.00 job68.7810-09-202120-11-20211.00 job1.00 job22.9368.78
12.Abutment Substructure RHS1.00 Job33.2510-06-202130-01-20221.00 Job1.00 Job11.0933.25
13.Abutment Substructure LHS1.00 Job33.2520-11-202130-01-20221.00 Job1.00 Job11.0933.25
14.Fixing Bearing/Slab Casting1.00 job1.5410-04-202210-05-20221.00 job1.00 job0.511.54
Total Amount: 300.01 100   300.01
Remarks: No Remarks       Work Program Made On: 23-01-2021        Updation of work program on: 25-01-2023       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-February-20214.94  lakh
2.31-May-202118.77  lakh
3.04-September-202110.95  lakh
4.22-November-202176.13  lakh
5.02-February-202234.95  lakh
6.26-March-202215.49  lakh
7.31-March-202235.53  lakh
8.21-May-202222.51  lakh
9.31-May-202226.43  lakh
Total 245.7  lakh
% Payment 79.3 %
Advance Amount:  15.79  lakh        Recovered Amount:  15.79  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 875   No. of Test Done : 875    No. of Test Passed : 874   No. of Test Failed : 1   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.84
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 88
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-06-2022Bridge from A1 sideBridge is ready for safe movementManish Rana ` ` See Pic
2.17-06-2022Jakhani-Rodha Bridge Br/73 District-ChamoliPicture from A2 sideEr Vipin Tomar, AE ` ` See Pic
3.17-06-2022Jakhani-Rodha Bridge Br/73 District-ChamoliBridge work almost CompleteEr. Vipin Tomar, AE ` ` See Pic
4.03-06-2022Jakhani-Rodha Gedhra Br/73Painting work completedEr. Vipin Tomar AE ` ` See Pic
5.26-04-2022Jakhani-RodhaConcrete pouring in protection retaining wallEr. Vipin Tomar, AE ` ` See Pic
6.31-03-2022Jakhni Rodha gadheraRR wall missionary work in progress behind Abutment A1PUNIT SINGH NEGI ` ` See Pic
7.31-03-2022Jakhni Rodha gadherastructure steel Erection work in progressPUNIT SINGH NEGI ` ` See Pic
8.28-03-2022Jhakni-Rodha Bridge, Br/73 , RudraprayagBearing InspectionEr.Vipin Tomar, AE ` ` See Pic
9.04-03-2022BR73DPT test in progress for POT PTFE BEARINGRohit Kumar Dubey ` ` See Pic
10.04-03-2022BR73POT PTFE Bearing testing in progressRohit Kumar Dubey ` ` See Pic
11.04-03-2022BR73POT PTFE Bearing testing in progressRohit Kumar Dubey ` ` See Pic
12.28-02-2022Jakhni Rodha gadheraSlump test M35 gread of concretePUNIT SINGH NEGI ` ` See Pic
13.28-02-2022Jakhni Rodha gadheraSlump test M35 gread of concretePUNIT SINGH NEGI ` ` See Pic
14.28-02-2022Jakhni Rodha gadheraConcrete pouring in protection wallPUNIT SINGH NEGI ` ` See Pic
15.24-02-2022Jakhni Rodha gadheraConcrete pouring in Abutment A2 retaining wallPUNIT SINGH NEGI ` ` See Pic
16.23-02-2022Jakhni Rodha gadheraConcrete pouring in Abutment A2 side retaining wallPUNIT SINGH NEGI ` ` See Pic
17.23-02-2022Jakhni Rodha gadheraM35 Cube testingPUNIT SINGH NEGI ` ` See Pic
18.20-02-2022Jhakni-Rodha Bridge, Chamoli (Br/73)Cube casting for M35Er. Vipin Tomar, AE ` ` See Pic
19.20-02-2022Jhakni-Rodha Bridge, Chamoli (Br/73)Measurement checked of ReinforcementEr. Vipin Tomar ` ` See Pic
20.20-02-2022Jhakani- Rodha Bridge, Chamoli (Br/73)Cube casting for M35Er. Vipin Toamr, AE ` ` See Pic